| FT.TO |
Fortune Minerals Limited |
2026-05-14 |
WaterNICO Mine Water Licence renewal |
NICO MineNorthwest Territories |
In review |
Wek’èezhìı Land and Water Board (WLWB) |
expires 2026-07-22allows Public hearings concluded; draft licence expected; current licence expires July 22 |
View ↗
|
| FT.TO |
|
|
Construction / operatingoperations permits |
Alberta hydrometallurgical facility (Lamont County)Alberta |
Planned |
— |
allows to follow engineering and air quality model |
|
| ADZ.V |
Adamera Minerals Corp. |
2026-05-13 |
Drill / explorationNotice of Work (IP survey component) |
South Hedley propertyBritish Columbiacopper-gold |
Granted |
B.C. Ministry of Mining and Critical Minerals |
allows Induced Polarization survey, 44 line-km, at Max copper-gold porphyry target; to start June2 releases since 2026-02-18 |
View ↗
|
| EMO.V |
Emerita Resources Corp. |
2026-05-13 |
Mining licence / leaseExploitation Permit |
Iberian Belt West ProjectHuelva Province, Andalucia, Spain |
In review |
Andalucian Environment Department in Huelva Province |
term 30-year term, extendable for two subsequent 30-year periodsallows Exploitation Permit application; public consultation is a stage of the approval processheld by Emerita Resources España S.L.U.9 releases since 2023-09-12 |
View ↗
|
| PBM.V |
Pacific Bay Minerals Ltd |
2026-05-12 |
Drill / explorationNotice of Work |
Haskins-Reed Critical Minerals ProjectBritish Columbiatungsten, copper, bismuth, silver, lead, zinc |
Applied |
BC Ministry of Mining and Critical Minerals |
term 5 yearsallows up to 120 diamond drill holes, up to 24,000 metres over 5 years; year-one program up to 30 holes |
View ↗
|
| GSR.V |
Gold Strike Resources Corp |
2026-05-12 |
Drill / explorationClass 3 Quartz Exploration Permit |
Gold Strike One ProjectYukon, Canadagold |
Granted |
Yukon Department of Energy, Mines and Resources |
term 10-yearallows Advanced exploration work including drilling; construction of a camp for up to 30 people; granted after positive recommendation from the Yukon Environmental and Socio-economic Assessment Board |
View ↗
|
| CNC.V |
Canada Nickel Company Inc. |
2026-05-12 |
Environmental assessmentDraft Impact Assessment Report |
Crawford Nickel ProjectCanada (federal)nickel |
In review |
Impact Assessment Agency of Canada (IAAC) |
allows Draft Impact Assessment Report published; includes IAAC preliminary conclusions and proposed conditions of approval. Penultimate stage of federal Impact Assessment process; final federal permitting decision expected early summer 2026.held by Canada Nickel Company Inc.2 releases since 2026-03-05 |
View ↗
|
| CNC.V |
|
|
Environmental assessmentImpact Statement responses |
Crawford Nickel ProjectCanada (federal)nickel |
Applied2025-12-30 |
Impact Assessment Agency of Canada (IAAC) |
allows Responses to IAAC comments submitted; IAAC confirmed they satisfy subsection 19(1) of the Act together with the original Impact Statement, which was submitted 2024-11-22.held by Canada Nickel Company Inc.5 releases since 2022-08-08 |
|
| CNC.V |
|
|
Environmental assessmentImpact Statement |
Crawford Nickel ProjectCanada (federal)nickel |
Applied2024-11-22 |
Impact Assessment Agency of Canada (IAAC) |
allows Impact Statement for Crawford submitted to IAAC; later comments dated 2025-05-30 required additional information.held by Canada Nickel Company Inc. |
|
| CNC.V |
|
|
Construction / operatingFinal federal permitting decision |
Crawford Nickel ProjectCanada (federal)nickel |
Planned |
Impact Assessment Agency of Canada (IAAC) |
allows Final federal permitting decision targeted by early summer 2026, following the draft report.held by Canada Nickel Company Inc. |
|
| FG.V |
Falcon Gold Corp |
2026-05-12 |
Drill / explorationexploration permit |
Central Canada ProjectOntario, Canadagold |
Granted |
Ontario Ministry of Energy and Mines |
allows diamond drilling, up to 20 drill holes totaling 2500 metres3 releases since 2025-11-11 |
View ↗
|
| NOAL.V |
NOA Lithium Brines Inc. |
2026-05-08 |
Drill / explorationbiannual renewal of environmental and social impact report for... |
Rio Grande ProjectSalta Province, Argentinalithium |
Renewed / amended |
— |
term biannualallows supports planned 2026 field activities |
View ↗
|
| OBUL.V |
One Bullion |
2026-05-07 |
Environmental assessmentEnvironmental Impact Statement (EIS) Approval – Section 12(1)(a)... |
Maitengwe Exploration ProjectBotswanagold |
Granted |
Department of Environmental Protection (DEP), Ministry of Environment and Tourism |
No. DEA/BOD/F/EXT/MNE 071 (8)term 2 yearsexpires 2028-04-20allows EIS approval for Maitengwe Exploration Project (PL 012/2018); renewal application due 3 months before expiryheld by Premier Gold Resources (Pty) Ltd |
View ↗
|
| LCE.V |
Century Lithium Corp |
2026-05-05 |
Plan of operations / noticeDraft Mine Plan of Operations |
Angel Island Lithium ProjectNevada, USAlithium |
In review |
U.S. Bureau of Land Management (BLM) |
allows Draft PoO submitted; BLM initial comments expected within the next month to complete final PoO5 releases since 2025-04-30 |
View ↗
|
| LCE.V |
|
|
Government / policyFAST-41 Transparency Project |
Angel Island Lithium ProjectNevada, USAlithium |
Granted |
Federal Permitting Council |
allows Federal permitting transparency and coordination under the Fixing America's Surface Transportation Act4 releases since 2025-08-06 |
|
| AML.V |
Akwaaba Mining Ltd |
2026-05-04 |
Drill / explorationProspecting license |
Kunsu projectAhafo Ano South District, Ashanti Region, Ghanagold |
Renewed / amended |
Minerals Commission of Ghana |
term 3 yearsexpires 2029-04-28allows approximately 141 km2; continue exploration activities |
View ↗
|
| GX.V |
Guardian Exploration Inc. |
2026-05-04 |
Drill / explorationClass 3 Quartz Exploration Permit |
Mount Cameron ProjectYukon, Canadasilver, lead, zinc |
Granted |
Department of Energy, Mines and Resources (EMR), Government of Yukon |
term 5 yearsallows Exploration incl. rapid resource delineation and greenfield exploration; granted after positive YESAB recommendation and FNNND consultation2 releases since 2024-10-07 |
View ↗
|
| EATH.CN |
New Earth Resources Corp. |
2026-05-01 |
Drill / explorationadditional state mineral lease |
Lucky Boy Uranium ProjectGila County, Arizona, USAuranium |
Granted |
Arizona State Land Department |
allows approximately 268 acres of additional state mineral lease land contiguous to the project |
View ↗
|
| TEX.CN |
Targa Exploration Corp. |
2026-04-30 |
Waterfinal water permit |
El ZanjonSanta Cruz, Argentinagold silver |
Granted |
Santa Cruz Ministry of Energy and Mining's Secretary of State for Water Resources |
allows to support a fully funded drill program |
View ↗
|
| TEX.CN |
|
|
Drill / explorationexploration drilling permits |
El ZanjonSanta Cruz, Argentinagold silver |
Granted |
— |
allows all permits for exploration drillingheld by Biz Latin Hub S.A.2 releases since 2026-01-08 |
|
| BLLG.CN |
Blue Lagoon Resources Inc. |
2026-04-30 |
Government / policyMajor priority project designation (Look West strategy) |
Baptiste Nickel ProjectBritish Columbianickel |
Granted |
Government of British Columbia |
allows Named a major priority project under B.C.'s Look West economic strategyheld by FPX Nickel Corp. |
View ↗
|
| BLLG.CN |
|
|
Government / policyCMO concierge service referral |
Baptiste Nickel ProjectBritish Columbianickel |
Granted |
— |
allows First project included in the CMO concierge serviceheld by FPX Nickel Corp. |
|
| FRED.V |
Fredonia Mining Inc |
2026-04-30 |
Drill / explorationgold and silver exploration license |
Judite propertySanta Cruz Province, Argentinagold, silver |
Granted |
— |
allows 4,913 hectares; acquired via competitive bidding after prior rights lapsed; settled ~US$25,000 outstanding concession fees |
View ↗
|
| ITR.V |
Integra Resources Corp |
2026-04-29 |
Environmental assessmentNEPA Decision Record (Final Environmental Assessment and FONSI) |
Wildcat Deposit, Nevada North ProjectPershing County, Nevadagold |
Granted |
United States Department of the Interior Bureau of Land Management (BLM) Humboldt River Field Office |
allows Authorizes the Final Environmental Assessment and Finding of No Significant Impact for Wildcat |
View ↗
|
| ITR.V |
|
|
Plan of operations / noticeReclamation Permit / Exploration Plan of Operations (EPO) |
Wildcat Deposit, Nevada North ProjectPershing County, Nevadagold |
Granted |
Nevada Division of Environmental Protection's Bureau of Mining Regulation and Reclamation (BMRR) |
allows Expanded exploration and development activities, drill roads and pads, expanded drilling; initial phase of disturbance with phased expansion subject to bonding2 releases since 2025-08-13 |
|
| CCM.TO |
Canagold Resources Ltd |
2026-04-29 |
Government / policyPriority major projects list designation (Look West) |
New Polaris Gold Antimony ProjectBritish ColumbiaGold, antimony |
Granted |
Government of British Columbia |
allows Priority project status: enhanced agency coordination, streamlined permitting |
View ↗
|
| FURY.TO |
Fury Gold Mines Limited |
2026-04-28 |
Environmental assessmentEnvironmental baseline studies |
Eau Claire Gold ProjectQuebec, Canadagold |
In review |
— |
term two yearsallows Field inventories of natural and human environments, establishing baseline for a future environmental impact assessment; carried out by Wassah |
View ↗
|
| FWZ.V |
Fireweed Metals Corp. |
2026-04-28 |
Drill / explorationsurface drilling permit |
Akie propertyBritish Columbia, CanadaZn-Pb-Ag |
Renewed / amended |
Ministry of Energy, Mines and Low Carbon Innovation |
term additional 2-year periodexpires 2028-12-31allows Covers the 11,580-hectare Akie property, including all three key thrust panels; previously set to expire 2026-12-31held by ZincX Resources Corp. |
View ↗
|
| GPH.V |
Graphite One Inc |
2026-04-27 |
Government / policyFAST-41 coverage |
Ohio advanced graphite materials and battery anode manufacturing facilityOhio, USAgraphite |
Planned |
Federal Permitting Dashboard (FAST-41) |
allows Company looks forward to pursuing FAST-41 coverage for the planned Ohio facility |
View ↗
|
| GPO.CN |
Gold Port Corporation |
2026-04-23 |
Mining licence / leaseMining Permits |
Groete Gold Copper ProjectGuyanaGold, Copper |
Renewed / amended |
Guyana Geology and Mines Commission |
term ensuing yearallows Three Mining Permits totaling 1,384 hectares |
View ↗
|
| TWR.V |
Tower Resources Ltd |
2026-04-23 |
Drill / explorationdiamond drilling program permit |
Rabbit NorthBritish Columbiagold |
Granted |
— |
allows Fifteen new drill sites approved; drilling planned at minimum ten sites2 releases since 2024-03-04 |
View ↗
|
| FF.TO |
First Mining Gold Corp |
2026-04-23 |
Environmental assessmentEnvironmental Assessment decision |
Springpole Gold ProjectCanadagold |
Renewed / amended |
Impact Assessment Agency of Canada (IAAC) |
expires 2026-06-30allows Voluntary short extension of the EA decision date from May 22, 2026 to June 30, 2026 to allow IAAC to complete the final EA report2 releases since 2026-01-07 |
View ↗
|
| QGR.V |
Q-Gold Resources Ltd. |
2026-04-21 |
Drill / explorationAngel's Camp exploration program authorization |
Quartz Mountain Gold ProjectOregon, USAgold |
Granted |
United States Forest Service (USFS) |
allows Angel's Camp geochemical soil sampling program, approx. 2,660 acres |
View ↗
|
| QGR.V |
|
|
Plan of operations / noticePlan of Operations |
Quartz Mountain Gold ProjectOregon, USAgold |
In review |
— |
allows Quartz Mountain metallurgical, density, hydrology, geotechnical and exploration drilling program |
|
| TICO.CN |
Talent Infinity Resource Developments Inc. |
2026-04-21 |
Drill / explorationMines Act mineral exploration permit |
Wildcat PropertyBritish Columbia |
Granted |
— |
term five-yearallows Up to 40 km of induced polarization ground geophysical surveying and up to 50 sonic overburden or diamond drill hole sites |
View ↗
|
| LEM.V |
Leading Edge Materials Corp. |
2026-04-19 |
Mining licence / leaseExploitation Concession (bearbetningskoncession) |
Norra KärrSwedenHeavy rare earth elements |
In review |
Swedish Government |
allows Mining Inspectorate recommended approval; final decision rests with the Swedish Governmentheld by Greenna Mineral AB (GMAB) |
View ↗
|
| VCU.V |
Vizsla Copper Corp |
2026-04-16 |
Drill / explorationMulti-Year Area Based (MYAB) permit under the BC Mines Act |
Copperview ProjectBritish Columbia, Canadacopper |
Granted |
BC Ministry of Mining and Critical Minerals |
term 5-yearallows Core drilling at multiple sites and limited construction and modification of exploration access trails; approved via Notice of Work application |
View ↗
|
| ARQ.CN |
Argo Gold Inc. |
2026-04-16 |
Drill / explorationmineral exploration permit |
Uchi Gold ProjectOntariogold |
Granted |
— |
— |
View ↗
|
| NTX.V |
NeoTerrex Minerals Inc |
2026-04-16 |
Drill / explorationmechanical trenching permits |
Gravitas projectQuébectungsten |
Granted |
— |
allows Petosa Tungsten zone trenching program |
View ↗
|
| NTX.V |
|
|
Drill / explorationexcavation permits |
Gravitas projectQuébeccopper-silver, copper-gold |
Granted |
— |
allows two areas: Galileo and Curie |
|
| NTX.V |
|
|
Drill / explorationtrenching permits |
Gravitas projectQuébecgold-silver-copper |
In review |
— |
allows Maxwell vein |
|
| MEO.CN |
Cameo Resources Inc. |
2026-04-15 |
Drill / explorationProspecting Licenses |
Katoro Gold PropertyTanzaniagold |
Renewed / amended |
— |
term three yearsexpires 2029-03allows Two Prospecting Licenses renewed |
View ↗
|
| GCN.V |
Goldcliff Resource Corporation |
2026-04-14 |
Drill / explorationMulti-Year Area-Based (MYAB) Notice of Work |
Kettle Valley gold-silver projectBritish Columbiagold-silver |
Renewed / amended |
B.C. Ministry of Mining and Critical Minerals |
expires 2028-03-28allows Extension supporting continued exploration including future drilling |
View ↗
|
| SEA.TO |
Seabridge Gold Inc |
2026-04-10 |
Land access / communityLicence of Occupation for the MTT route |
KSMBritish Columbiagold |
Granted |
Ministry of Mining and Critical Minerals of British Columbia (the Ministry) |
allows Licence of Occupation held for the MTT routeheld by Seabridge Gold |
View ↗
|
| SEA.TO |
|
|
Construction / operatingAuthorizations to construct MTT portals at three sites and about... |
KSMBritish Columbiagold |
Granted |
Ministry of Mining and Critical Minerals of British Columbia (the Ministry) |
allows Authorizations to construct the MTT portals at three sites, approximately 100 metres of tunnel length at each portal location (including over areas of Tudor mineral claims)held by Seabridge Gold |
|
| SLS.TO |
Solaris Resources Inc. |
2026-04-09 |
Mining licence / leaseMining Exploitation Agreements |
Warintza ProjectEcuadorcopper |
Planned |
Ecuador's Ministries of Energy and Mines and Environment |
allows targeting fully permitted project by end of 20262 releases since 2025-05-21 |
View ↗
|
| XIM.V |
Ximen Mining Corp. |
2026-04-09 |
WaterWater licence (Water Sustainability Act) - Venango property |
Kenville Gold ProjectBritish Columbiagold |
Granted |
regulatory authority |
allows Authorizes use of groundwater from a bedrock aquifer; covers the Venango property where the new underground portal and decline will be constructed2 releases since 2023-09-26 |
View ↗
|
| XIM.V |
|
|
WaterWater licence (Water Sustainability Act) - Election property |
Kenville Gold ProjectBritish Columbiagold |
Granted |
BC Ministry of Environment |
allows Authorizes use of groundwater from a bedrock aquifer; covers the adjoining Election property4 releases since 2019-08-07 |
|
| EFF.V |
1844 Resources Inc. |
2026-04-09 |
Drill / explorationdrilling permits |
SV2 (Sullipek/Vortex/Vallières) copper projectGaspé Peninsula, Québeccopper |
Granted |
— |
allows drilling permits; project fully drill-ready |
View ↗
|
| SOMA.V |
Soma Gold Corp |
2026-04-08 |
Mining licence / leasePTO (Permiso de Trabajo de Obra) mining permit |
Nechí ProjectDepartment of Bolívar, Colombiagold |
Applied |
— |
allows Underground development; approval expected before end of 2026; ~250 tpd feed to El Bagre Mill3 releases since 2024-09-30 |
View ↗
|
| SCLT.V |
Searchlight Resources Inc |
2026-04-08 |
Drill / explorationdrill and surface exploration permit |
Robinson Creek Gold ProjectSaskatchewan, Canadagold |
Granted |
Saskatchewan Ministry of Environment |
term two-yearallows surface exploration (prospecting, mapping) planned summer 2026, drilling to follow2 releases since 2026-03-19 |
View ↗
|
| LGD.TO |
Liberty Gold Corp. |
2026-04-03 |
Plan of operations / noticeMine Plan of Operations |
Black Pine Oxide Gold ProjectIdaho, USAgold |
In review |
United States Forest Service (USFS) and United States Bureau of Land Management (BLM) |
allows Deemed administratively complete in November 20252 releases since 2025-11-26 |
View ↗
|
| AEC.V |
Anfield Energy Inc. |
2026-04-02 |
Drill / explorationNotice of Intent (NOI) |
SM-18 uranium-vanadium projectColoradouranium-vanadium |
Applied |
— |
allows underground drilling program |
View ↗
|
| LEAP.V |
Quantum Critical Metals Corp |
2026-04-02 |
Drill / explorationdrilling permit |
NMX East ProjectJames Bay - Eeyou Istchee region, northern Québecgallium, rubidium, nickel |
Granted |
Ministère des Ressources naturelles et des Forêts |
term over the next two years (planned program)allows up to 121 diamond drill holes; muscovite-rich pegmatite dykes and ultramafic package2 releases since 2025-10-02 |
View ↗
|
| TCO.V |
Transatlantic Mining Corp |
2026-04-01 |
Plan of operations / noticePlan of Operation |
Golden Jubilee projectGranite County, Montana, USAgold |
Renewed / amended |
US Department of Agriculture |
expires 2026-12-31allows New drilling and dewatering at the Golden Jubilee mine; up to 1,000 m in 2 to 4 holes |
View ↗
|
| PMET.TO |
PMET Resources Inc. |
2026-04-01 |
Environmental assessmentEnvironmental and Social Impact Assessment (ESIA) |
Shaakichiuwaanaan CV5 Lithium ProjectCanada (federal)lithium |
Applied |
Impact Assessment Agency of Canada (IAAC) |
allows Federal impact assessment; public review period to follow |
View ↗
|
| SYH.V |
Skyharbour Resources Ltd |
2026-04-01 |
Drill / explorationdrill permit |
Moore Uranium ProjectSaskatchewanuranium |
Renewed / amended |
— |
term three-yearexpires 2029-03allows renewed drill permit for Moore Uranium Project |
View ↗
|
| CASC.CN |
Cascade Copper Corp. |
2026-03-31 |
Drill / explorationDrill permit |
Centrefire Copper-Gold ProjectOntario, Canadacopper-gold |
Granted |
— |
allows Maiden drilling program, up to 1000 m in four or five holes, planned to start Q2 20265 releases since 2025-12-30 |
View ↗
|
| BMM.V |
Black Mammoth Metals Corporation |
2026-03-31 |
Drill / exploration |
Amador Silver propertyLander County, Nevadasilver |
Granted |
Bureau of Land Management (BLM) |
allows Up to 6 drill sites, multiple boreholes per site |
View ↗
|
| UGD.V |
Unigold Inc |
2026-03-31 |
Drill / explorationdrilling permit / exploration work permit |
Neita Sur ConcessionDominican Republicgold-silver |
Renewed / amended |
Ministry of the Environment (MIMARENA) |
allows resume drilling at Neita Sur gold-silver deposits4 releases since 2023-05-03 |
View ↗
|
| UGD.V |
|
|
Environmental assessmentEnvironmental and Social Impact Assessment (ESIA) |
Candelones Oxide ProjectDominican Republicgold |
Planned |
Ministry of the Environment (MIMARENA) |
allows ESIA to proceed once Terms-of-Reference are received |
|
| PEAK.V |
Sun Peak Metals Corp. |
2026-03-31 |
Drill / explorationExploration licenses |
Saudi Arabia Round 9 exploration licensesSaudi Arabiagold, VMS base metals |
Granted |
Saudi Arabian Ministry of Industry and Mineral Resources (MIMR) |
allows Seven exploration licenses totaling 632 km² awarded via Round 9 licensing auction; 100% owned |
View ↗
|
| LIFT.V |
Li-FT Power Ltd. |
2026-03-31 |
Environmental assessmentEnvironmental Assessment |
Yellowknife Lithium ProjectNorthwest Territorieslithium |
Planned |
— |
allows 2026 environmental baseline data collection program supporting future permitting including Environmental Assessment3 releases since 2025-04-17 |
View ↗
|
| SEAS.CN |
Deep Sea Minerals Corp. |
2026-03-31 |
Drill / explorationSubsea Critical Mineral Exploration License Application |
Subsea Critical Mineral ExplorationUnited States (NOAA, Deep Seabed Hard Mineral Resources Act)polymetallic nodules |
In review |
National Oceanic and Atmospheric Administration (NOAA) |
allows Exploration license for about 150,000 square kilometers of seabed in the Central Pacific Clarion-Clipperton Zone and areas in the Western Pacific near Guam; application deemed in full compliance, now at certification stageheld by Deep Sea Rare Minerals, Inc. |
View ↗
|
| SEAS.CN |
|
|
Drill / explorationSubsea Critical Mineral Exploration License |
Subsea Critical Mineral ExplorationUnited States (NOAA, Deep Seabed Hard Mineral Resources Act)polymetallic nodules |
Planned |
National Oceanic and Atmospheric Administration (NOAA) |
allows Certification of the application (NOAA endeavors within about 100 days of full compliance), then proposal to issue the exploration license with Federal Register notice, at least 60-day public comment and public hearingheld by Deep Sea Rare Minerals, Inc. |
|
| GLAD.V |
Gladiator Metals Corp |
2026-03-30 |
Drill / explorationClass 3 Quartz Exploration Permit |
Whitehorse Copper ProjectYukon, Canadacopper |
Granted |
Government of Yukon |
term 5-yearallows Allows resource definition, resource expansion and systematic drilling along the Whitehorse Copper Belt3 releases since 2025-10-29 |
View ↗
|
| GLAD.V |
|
|
Environmental assessmentYESAB assessment positive recommendation |
Whitehorse Copper ProjectYukon, Canadacopper |
Granted |
Yukon Environmental and Socio-economic Assessment Board (YESAB) |
allows Positive recommendation preceding the Class 3 permit2 releases since 2025-10-29 |
|
| GLAD.V |
|
|
Land access / community |
Whitehorse Copper ProjectYukon, Canadacopper |
Granted |
Kwanlin Dün First Nation |
allows Positive consultation supporting the Class 3 permit |
|
| GLAD.V |
|
|
Land access / community |
Whitehorse Copper ProjectYukon, Canadacopper |
Granted |
Ta’an Kwäch’än Council |
allows Positive consultation supporting the Class 3 permit |
|
| PDN.TO |
Paladin Energy Ltd. |
2026-03-30 |
Environmental assessmentEnvironmental Impact Statement (EIS) approval |
Patterson Lake South (PLS) ProjectSaskatchewan, Canadauranium |
Contested |
Saskatchewan Minister of Environment |
allows Métis Nation–Saskatchewan applied for judicial review in the Saskatchewan Court of King's Bench to set aside the 19 February 2026 approval and seek an interim injunction2 releases since 2026-02-19 |
View ↗
|
| XGC.V |
Xali Gold Corp |
2026-03-30 |
Environmental assessmentDetailed Environmental Impact Assessment (EIA-d) |
Pico Machay Gold ProjectPerugold |
Planned |
— |
term typically 12 to 24 monthsallows longest lead-time component for permitting any mining operation in Peru3 releases since 2025-12-24 |
View ↗
|
| NTMC.CN |
Neotech Metals Corp |
2026-03-30 |
Government / policyOntario Junior Exploration Program (OJEP) funding |
Hecla-KilmerOntariorare earth; niobium |
Granted |
Ontario Junior Exploration Program (OJEP) |
allows Funding of up to C$200,000 toward eligible 2025 exploration expenditures (50% of eligible mineral exploration expenditure, max C$400,000) |
View ↗
|
| VRR.V |
VR Resources Ltd. |
2026-03-26 |
Drill / explorationNotice of Intent (NOI) drill permit |
New Boston projectNevada, USAmoly-tungsten-copper-silver |
Granted |
Nevada Bureau of Land Management (BLM) |
allows Eight potential drill sites in the Jeep Mine area; ~1,500 m drill program planned; reclamation bonding completed3 releases since 2023-11-14 |
View ↗
|
| ASHL.CN |
Ashley Gold Corp. |
2026-03-25 |
Drill / exploration |
Alto-Gardnar ProjectDryden, Ontariogold |
Granted |
— |
allows Up to 13 pads, line cutting and IP surveys4 releases since 2025-01-16 |
View ↗
|
| ASHL.CN |
|
|
Drill / exploration |
Vertebrae RidgeBritish Columbia |
In review |
— |
allows Permit pending issuance2 releases since 2025-10-30 |
|
| ASHL.CN |
|
|
Drill / exploration |
BurnthutDryden, Ontario |
Planned |
— |
allows Expand permit to include IP lines outside the Tak Patents2 releases since 2025-12-17 |
|
| SCOT.V |
Scottie Resources Corp |
2026-03-25 |
Environmental assessmentBC Environmental Assessment Act determination |
Scottie Gold Mine ProjectBritish Columbiagold |
Granted |
British Columbia Environmental Assessment Office (EAO) |
allows Project does not require an environmental assessment under the BC Environmental Assessment Act |
View ↗
|
| SCOT.V |
|
|
Environmental assessmentCanadian Impact Assessment Act determination |
Scottie Gold Mine ProjectCanadagold |
Granted |
Impact Assessment Agency of Canada |
allows Project does not require an impact assessment under the Canadian Impact Assessment Act |
|
| GXLD.CN |
Hi-View Resources Inc. |
2026-03-24 |
Land access / community |
Toodoggone PortfolioBritish Columbia |
Granted |
Kwadacha Nation |
allows Thanks to Kwadacha Nation for welcoming the company onto traditional territories; no agreement terms stated. |
View ↗
|
| GXLD.CN |
|
|
Land access / community |
Toodoggone PortfolioBritish Columbia |
Granted |
Takla Nation |
allows Thanks to Takla Nation for welcoming the company onto traditional territories; no agreement terms stated. |
|
| GXLD.CN |
|
|
Land access / community |
Toodoggone PortfolioBritish Columbia |
Granted |
Tsay Keh Dene Nation |
allows Thanks to Tsay Keh Dene Nation for welcoming the company onto traditional territories; no agreement terms stated. |
|
| GXLD.CN |
|
|
Drill / exploration |
Toodoggone PortfolioBritish Columbia |
Planned |
— |
allows A separate application is planned to support further IP surveying across the additional Hi-View Toodoggone Properties. |
|
| BIG.V |
Hercules Metals Corp |
2026-03-24 |
Land access / communityReal property lease with option to purchase |
Hercules ProjectWashington County, Idahocopper |
Granted |
Arm's length private landowner |
term eight-year leaseallows Exclusive right to conduct mineral exploration including drilling and geophysical surveys on ~1,472.65 acres of private land in Washington County, Idaho; option to purchase 100% interest; annual payments US$125,000held by Anglo-Bomarc, U.S., Inc. |
View ↗
|
| LGD.TO |
Liberty Gold Corp. |
2026-03-23 |
Government / policyFAST-41 Covered project permitting schedule |
Black Pine Oxide Gold ProjectIdaho, USAgold |
Granted |
Federal Permitting Improvement Steering Committee Council |
allows Coordinated federal and state permitting schedule posted to permitting dashboard3 releases since 2026-01-20 |
View ↗
|
| LGD.TO |
|
|
Construction / operating |
Black Pine Oxide Gold ProjectIdaho, USAgold |
Planned |
— |
allows State and federal permits for construction and operation: water management, heap leach operations, air quality, surface disturbance, reclamation |
|
| RLYG.V |
Riley Gold Corp |
2026-03-18 |
Plan of operations / noticeExploration Plan of Operations (EPO) |
PWCNevada, USAgold |
Planned |
Bureau of Land Management |
allows Exploration across 14 square kilometres (3,478 acres) boundary, up to 500 drill sites, up to 250 acres of disturbanceheld by Kinross Gold U.S.A., Inc. |
View ↗
|
| FAS.V |
First Andes Silver Ltd. |
2026-03-18 |
Drill / explorationExploration Licence |
Carrington ProjectNew South Wales, AustraliaAu-Ag-Pb-Sb |
Granted |
— |
No. EL 9873allows 160 km² exploration licence |
View ↗
|
| FAS.V |
|
|
Drill / explorationExploration Licence |
Stony Creek ProjectNew South Wales, AustraliaAu-Ag |
Granted |
— |
No. EL 9870allows 247 km² exploration licence |
|
| FAS.V |
|
|
Drill / explorationExploration Licence |
Dartmoor ProjectNew South Wales, AustraliaAg-Cu |
Granted |
— |
No. EL 9879allows 47 km² exploration licence |
|
| GSTR.CN |
Glenstar Minerals Inc. |
2026-03-17 |
Plan of operations / notice |
Wildhorse ProjectMineral County, Nevada |
Applied |
Bureau of Land Management (BLM) |
allows 13-hole reverse circulation drill program: 6 holes at Coca Cola Zone, 7 holes at Rattlesnake Zone |
View ↗
|
| ZAC.V |
Zacatecas Silver Corp. |
2026-03-16 |
Drill / explorationDrill permit (Informe Preventivo) |
Zacatecas Silver ProjectZacatecas State, Mexicosilver |
Granted |
Secretaría de Medio Ambiente y Recursos Naturales (SEMARNAT) |
allows El Cristo vein system; ~2,800 m of the 4,000 m 2026 drill program4 releases since 2025-11-10 |
View ↗
|
| ZAC.V |
|
|
Land access / communitySurface access agreements |
Zacatecas Silver ProjectZacatecas State, Mexicosilver |
Granted |
private landowners |
allows El Cristo; drill pad mobility across priority targets3 releases since 2025-11-13 |
|
| ASHL.CN |
Ashley Gold Corp. |
2026-03-13 |
Drill / explorationDiamond Drill Permit |
Gold Mountain ProjectBritish Columbia |
Granted |
— |
allows drill campaign |
View ↗
|
| PPX.V |
PPX Mining Corp. |
2026-03-12 |
OtherCertificate of Non-Existence of Archaeological Remains (CIRA) |
Igor ProjectLa Libertad, Peru |
Granted2026-03-03 |
Ministry of Culture |
No. 105-2026-DDC-LIB/MCallows Electrical transmission line, surface; confirms project area free of archaeological remains |
View ↗
|
| PPX.V |
|
|
Construction / operatingTechnical approval / Detailed Electrical Engineering approval |
Igor ProjectLa Libertad, Peru |
Granted2026-01-23 |
Distriluz (Hidrandina) |
No. HDNA-GR-0100-2026allows 13.8 kV Medium Voltage Utilization System (designed for 22.9 kV), max demand 1.5 MW, for grid connection of processing plant |
|
| CBR.V |
Cabral Gold Inc |
2026-03-10 |
Mining licence / leaseLicença Prévia (LP) for the Full Mining License |
Cuiú Cuiú Gold DistrictPará, Brazilgold |
Granted |
Environmental Council (COEMA) for the state of Pará |
allows Covers Phase 1 gold-in-oxide expansion to 1 Mtpa and Phase 2 hard rock development |
View ↗
|
| CBR.V |
|
|
Construction / operatingInstallation License (LI) for the Full Mining Licence (Portaria Da Lavra) |
Cuiú Cuiú Gold DistrictPará, Brazilgold |
Planned2026-03 |
— |
allows Request expected during March 2026 |
|
| CBR.V |
|
|
Construction / operatingOperating License (LO) for the Full Mining Licence (Portaria Da Lavra) |
Cuiú Cuiú Gold DistrictPará, Brazilgold |
Planned2026-03 |
— |
allows Request expected during March 2026 |
|
| LBNK.V |
LithiumBank Resources Corp |
2026-03-10 |
Drill / explorationWell license transfer |
Boardwalk ProjectAlberta, Canadalithium |
Granted |
— |
No. 104/01-12-069-22W5/00allows Suspended, past producing 1-12 well; 100% ownership; planned re-entry and deeper drilling through the Leduc formation |
View ↗
|
| LSTR.V |
Lodestar Metals |
2026-03-10 |
Plan of operations / noticeNotice of Intent (NOI) drilling permits |
Gold Run PropertyNevadagold |
Granted |
Bureau of Land Management (BLM) |
allows drilling permits; reclamation bond payment still to be confirmed before drilling |
View ↗
|
| NGEX.TO |
NGEx Minerals Ltd. |
2026-03-09 |
OtherAdditional sectoral permits |
Lunahuasi projectArgentinacopper-gold-silver |
Planned |
provincial and national authorities |
allows remaining permits needed to start underground development of exploration adit |
View ↗
|
| DLP.V |
DLP Resources Inc |
2026-03-09 |
Drill / exploration |
Esperanza copper-gold-molybdenum projectsouthern Perucopper-gold-molybdenum |
Granted |
— |
allows Permits and authorizations to construct drill platforms and access and conduct diamond drilling; ~3,000 m in seven holes |
View ↗
|
| WHY.V |
West High Yield (W.H.Y.) Resources Ltd. |
2026-03-09 |
Construction / operatingDraft highway access permit |
Record Ridge Industrial Mineral Mine project (RRIMM Project)British Columbia |
Granted |
British Columbia Ministry of Transportation and Transit (MOTT) |
allows Controlled project access from the provincial highway system, including Cascade Highway corridor; conditions still to be finalized |
View ↗
|
| JAG.TO |
Jaguar Mining Inc. |
2026-03-09 |
Government / policy |
Turmalina Mine (MTL Complex)Brazilgold |
Granted |
Environmental Emergency Office (NEA) |
allows Approval to begin operations at the mine and associated plants; NEA lifted the one remaining embargo on operations; tailings initially permitted as mine backfill |
View ↗
|
| JAG.TO |
|
|
Construction / operating |
Turmalina Mine (MTL Complex)Brazilgold |
Granted |
National Mining Agency (ANM) |
allows Required approvals preceding the NEA approval2 releases since 2025-10-14 |
|
| MOC.CN |
Mosaic Minerals Corp. |
2026-03-05 |
Drill / explorationauthorization for impact work |
Golden Island projectQuebecAu |
Granted |
Quebec Ministry of Natural Resources |
allows impact work |
View ↗
|
| MOC.CN |
|
|
Drill / explorationdrilling permits |
Golden Island projectQuebecAu |
Planned |
— |
allows for spring 2026 drilling campaign |
|
| NXE.TO |
NexGen Energy Ltd |
2026-03-05 |
Environmental assessmentEnvironmental Assessment approval |
Rook I ProjectCanada (federal)uranium |
Granted |
Canadian Nuclear Safety Commission (CNSC) |
allows Final EIS accepted by CNSC staff January 2025; federal EA review concludes with hearingsheld by NexGen Energy Ltd.18 releases since 2019-04-29 |
View ↗
|
| NXE.TO |
|
|
Construction / operatingLicence to Prepare Site and Construct |
Rook I ProjectCanada (federal)uranium |
Granted |
Canadian Nuclear Safety Commission (CNSC) |
allows Anticipated federal licence approvals following EA, before major construction7 releases since 2022-12-01 |
|
| NXE.TO |
|
|
Environmental assessmentEnvironmental Assessment approval |
Rook I ProjectSaskatchewanuranium |
Granted |
Saskatchewan Environmental Assessment |
allows Provincial EA completed8 releases since 2024-05-21 |
|
| BRC.V |
Blackrock Silver Corp |
2026-03-03 |
WaterWater Pollution Control Permit |
Tonopah West ProjectNevada, USAsilver |
Planned |
— |
allows Hydrogeological and geochemical data collection underway; anticipated by mid-2027 |
View ↗
|
| BRC.V |
|
|
Plan of operations / noticeModification to the Nevada Reclamation Permit |
Tonopah West ProjectNevada, USAsilver |
Planned |
— |
allows Based on surface disturbance from waste dump, stockpile and portal designs; anticipated by mid-2027 |
|
| SEAS.CN |
Deep Sea Minerals Corp. |
2026-03-03 |
OtherLicense application under the NOAA process |
Deep Sea Minerals Corp. NOAA license applicationUnited States |
Planned |
NOAA |
— |
View ↗
|
| NOM.CN |
Norsemont Mining Inc. |
2026-03-02 |
Environmental assessmentEnvironmental Impact Declaration (Declaración de Impacto Ambiental) (EID) |
Choquelimpie gold-silver-copper projectChilegold-silver-copper |
Planned |
— |
allows EID being prepared by DAES Consultores, targeted completion by December 2026; baseline studies March-November 2026 |
View ↗
|
| TRO.V |
Taranis Resources Inc. |
2026-03-02 |
Land access / communityMineral Tenure First Nations Consultation (MCCF) |
ThorBritish Columbia |
In review |
First Nations (Mineral Claims Consultation Framework, Ministry of Critical Minerals) |
allows Consultation on additional claims staked July 1, 2025 south and east of new mine clusters; sent out 2025-08-28; no comments received after 186 days2 releases since 2024-01-18 |
View ↗
|
| TRO.V |
|
|
Drill / explorationNotice of Work (NoW) |
ThorBritish Columbia |
Applied |
Front Counter B.C. |
allows Access to area east of Ferguson Creek to explore newly added portion of the property; receipt acknowledged Feb 3, 2026 |
|
| GGO.V |
Galleon Gold Corp |
2026-03-02 |
Construction / operatingMECP compliance approval for air and noise |
West Cache Gold ProjectOntariogold |
Granted |
Ontario Ministry of the Environment, Conservation and Parks (MECP) |
allows Air and noise compliance approval3 releases since 2023-11-16 |
View ↗
|
| ATHA.CN |
Athena Gold Corporation |
2026-03-02 |
Drill / explorationdrill permits |
Laird Lake projectOntariogold |
Granted |
— |
No. PR 25 00201allows maiden ~5,000 m diamond drill program3 releases since 2025-11-13 |
View ↗
|
| ATHA.CN |
|
|
Land access / communityExploration agreement |
Laird Lake projectOntariogold |
Granted |
Wabauskang First Nation (WFN) |
allows cooperative relationship; 100,000 common shares issued to WFN, subject to CSE approval |
|
| SALT.V |
Atlas Salt Inc. |
2026-02-27 |
Plan of operations / noticeEarly Works Development Plan and Environmental Management Plans |
Great Atlantic Salt ProjectNewfoundland and Labrador |
Granted |
Government of Newfoundland and Labrador |
— |
View ↗
|
| SALT.V |
|
|
Land access / communityBenefits Agreement |
Great Atlantic Salt ProjectNewfoundland and Labrador |
Granted |
Province of Newfoundland and Labrador |
allows Employment, procurement, training and community participation framework |
|
| ECU.V |
Element 29 Resources Inc |
2026-02-27 |
Drill / explorationDeclaración de Impacto Ambiental (DIA) environmental certification |
Paka ProjectPerúCu-Zn-Au-Ag |
Granted |
Perúvian Ministerio de Energía y Minas (MINEM) |
term up to five yearsallows up to 40 drilling platforms |
View ↗
|
| ECU.V |
|
|
Drill / explorationPrograma de Inicio de Actividades (PIA) drilling permit |
Paka ProjectPerúCu-Zn-Au-Ag |
Planned |
Perúvian Ministerio de Energía y Minas (MINEM) |
allows inaugural drilling program |
|
| ECU.V |
|
|
Land access / communityPrior Consultation (Consulta Previa) – Collective Impacts Report |
Paka ProjectPerúCu-Zn-Au-Ag |
Planned |
Ministerio de Cultura |
allows Collective Impacts Report being prepared for submission |
|
| ECU.V |
|
|
Drill / explorationFicha Técnica Ambiental (FTA) environmental certification |
Elida Porphyry Cu-Mo-Ag DepositPerúCu-Mo-Ag |
Granted |
— |
expires 2026-Q2allows authorizes up to 20 drilling platforms; existing, used for current drilling2 releases since 2026-01-06 |
|
| ECU.V |
|
|
Drill / explorationUpgraded DIA environmental certificate |
Elida Porphyry Cu-Mo-Ag DepositPerúCu-Mo-Ag |
Renewed / amended |
Ministerio de Energía y Minas (MINEM) |
allows supports PIA for up to 40 drilling platforms2 releases since 2026-01-06 |
|
| RFR.CN |
Renforth Resources Inc. |
2026-02-26 |
Drill / explorationForestry permit |
Victoria Nickel Sulphide Polymetallic Open Pit DepositQuebecnickel |
Granted |
— |
allows siting of 3 planned drill stations |
View ↗
|
| RFR.CN |
|
|
Plan of operations / noticeBulk sample permit |
Parbec Gold DepositQuebecgold |
Planned |
— |
allows environmental and geotechnical baseline studies to support bulk sample permitting2 releases since 2025-12-11 |
|
| MLP.V |
Millennial Potash Corp |
2026-02-24 |
Drill / explorationHaute Banio exploration permit |
Banio Potash ProjectGabonpotash |
Granted |
— |
term 3 years, renewable for 2 additional 3-year periodsallows 261.39 km2, contiguous with Mayumba exploration permit; includes marine coastline areas |
View ↗
|
| MOLY.TO |
Greenland Resources Inc. |
2026-02-24 |
Drill / explorationspecial exploration license |
Malmbjerg projectSemersooq region, Greenlandmolybdenum |
Granted |
government of Greenland |
No. MEL-S 2026-07allows 1,147.76 km2; explore for all minerals except hydrocarbons and radioactive elements; surrounds existing exploitation license |
View ↗
|
| OGW.V |
Ongwe Minerals Inc |
2026-02-24 |
Drill / explorationEPL7400 |
Omatjete ProjectNamibiagold |
Granted |
— |
No. EPL7400allows 36,600ha; Ongwe acquired 90% of Fallout Investments, which holds 100%held by Fallout Investments (Pty) Ltd |
View ↗
|
| OGW.V |
|
|
Drill / explorationEPL11268 |
Omatjete ProjectNamibiagold |
Applied |
Ministry of Industries Mines and Energy of Namibia |
No. EPL11268allows 8,200ha |
|
| CRCL.CN |
Corcel Exploration Inc. |
2026-02-24 |
Drill / explorationreclamation bond acceptance |
Yuma King projectArizonacopper, gold |
Granted |
US Bureau of Land Management (BLM) |
allows authorizes site preparation and drilling, ~1,500 m diamond core across 6-8 drill sites |
View ↗
|
| LVX.V |
Leviathan Metals Corp. |
2026-02-23 |
Drill / explorationTjemenik Exploration License |
Foča ProjectRepublika Srpska, Bosnia and Herzegovina |
Granted |
Ministry of Energy and Mining of Republika Srpska |
allows 50 square kilometers; expands Foča Project to 150.7 square kilometers2 releases since 2025-04-17 |
View ↗
|
| LVX.V |
|
|
Drill / explorationPodovi Exploration License |
Foča ProjectRepublika Srpska, Bosnia and Herzegovina |
In review |
— |
allows 50 square kilometers, west of Marevo |
|
| GAMA.V |
Gamma Resources Ltd. |
2026-02-23 |
Drill / explorationNotice of Intent (NOI) |
Mesa Arc Uranium ProjectNew Mexico, USAuranium |
Applied |
U.S. Forest Service (USFS) |
allows Exploration drilling of approx. 10–12 holes up to 500 ft deep, 50' x 50' drill pads, ~800 ft new access road |
View ↗
|
| XGC.V |
Xali Gold Corp |
2026-02-22 |
Land access / communityCommunity authorization for exploration activities |
Pico Machay Gold ProjectPerugold |
Granted |
Community of Santa Ana |
term long-termallows Authorization to further advance mining exploration activities3 releases since 2025-12-24 |
View ↗
|
| CDN.CN |
CDN Maverick Capital Corp. |
2026-02-20 |
Drill / explorationAuthorization of impact-causing exploration work permit (ATI) |
Nottaway PropertyQuébec |
Granted2026-02-16 |
— |
term 3 yearsallows diamond drilling |
View ↗
|
| DML.TO |
Denison Mines Corp. |
2026-02-19 |
Construction / operatingLicence to Prepare Site & Construct a Mine and Mill |
Wheeler River Uranium ProjectCanada (federal)uranium |
Granted |
Province of Saskatchewan |
allows Phoenix ISR uranium mine2 releases since 2025-08-07 |
View ↗
|
| GEMC.V |
Global Energy Metals Corporation |
2026-02-18 |
Drill / explorationExploration Permit for Minerals (EPM) |
Millennium ProjectQueensland, AustraliaCopper-Cobalt-Gold-Graphite |
Applied |
— |
allows Two sub-blocks surrounding existing Millennium mining leases; to allow drilling of gap zone and graphite extensionsheld by Millennium Joint Venture |
View ↗
|
| CLZ.V |
Canasil Resources Inc. |
2026-02-18 |
Drill / explorationDrill permit |
Vizcaino Gold-Silver ProjectDurango State, Mexicogold-silver |
Applied |
— |
allows Phase 1 1,050 m in 6 HQ holes; Phase 2 1,450 m in 8 holes; includes provisions for follow-on drilling. Expected by end Q1 2026 or early Q2 20262 releases since 2026-01-12 |
View ↗
|
| DEF.V |
Defiance Silver Corp |
2026-02-12 |
Land access / communitylong-term surface access agreement |
Green Earth ProjectSonora, Mexico |
Granted |
— |
term five yearsallows Victoria target; right to conduct surface exploration, drilling, and engineering studies |
View ↗
|
| EATH.CN |
New Earth Resources Corp. |
2026-02-12 |
Mining licence / leasestate mineral lease |
Lucky Boy Uranium ProjectArizona, USAuranium |
Applied |
Arizona State Land Department |
allows approx. 268 acres of additional state mineral lease land contiguous to the project |
View ↗
|
| STLR.TO |
STLLR Gold Inc |
2026-02-12 |
OtherRecovery of Minerals permit |
Hollinger Tailings ProjectOntario, Canadagold |
Granted |
Ontario Ministry of Energy and Mines |
allows First permit issued under Ontario's Recovery of Minerals regime; enables additional technical work |
View ↗
|
| GRL.V |
GreenLight Metals Inc |
2026-02-11 |
Drill / exploration |
Bend VMS ProjectWisconsincopper-gold |
Granted |
Wisconsin Department of Natural Resources (WDNR) |
allows Conditional approval for exploration drilling on Soo Line Mineral Parcel, up to ~7,000 metres, up to 15 drill padsheld by Green Light Wisconsin LLC2 releases since 2025-05-28 |
View ↗
|
| GRL.V |
|
|
Drill / exploration |
Bend VMS ProjectWisconsincopper-gold |
Granted |
— |
allows Authorization for exploration drilling on Soo Line Mineral Parcel, up to ~7,000 metresheld by Green Light Wisconsin LLC |
|
| GRL.V |
|
|
Drill / explorationprospecting permit |
Bend VMS ProjectWisconsincopper-gold |
In review |
U.S. Forest Service and Bureau of Land Management |
allows Prospecting permit application on adjacent federal lands; drilling expansion planned later in 2026held by Green Light Wisconsin LLC |
|
| PCFC |
PCFC |
2026-02-11 |
Drill / exploration |
Claudia Project |
Granted |
— |
allows drilling of new high-priority targets; number of permits not stated |
View ↗
|
| AUME.V |
Auriginal Mining Corp |
2026-02-10 |
Drill / explorationexploration work permits (ATI) |
Roger ProjectQuebecCu-Au |
Granted |
— |
allows All necessary work and site preparation permits for 5,200 m diamond drill program |
View ↗
|
| AUOZ.CN |
Emperor Metals Inc. |
2026-02-10 |
OtherUpdated closure plan |
Lac Pelletier Mine PropertyQuebecgold |
Planned2026-03 |
MRNF |
allows Closure plan update to be submitted for review and comment by end of March; regulatory review and approval anticipated by end of June 20262 releases since 2025-05-07 |
View ↗
|
| MERC.CN |
Mercado Minerals Ltd. |
2026-02-10 |
Drill / explorationexploration drill permit |
Copalito ProjectSinaloa, Mexicosilver |
Granted |
— |
allows Authorizes use of existing and newly constructed drill pads; initial 3,000-metre diamond drill program |
View ↗
|
| ATY.V |
Atico Mining Corporation |
2026-02-09 |
OtherRegistration in the Waste and Waste Generator Registry (GDPR) |
La Plata projectEcuador |
Granted |
Ministry of Environment, Water and Ecological Transition (MAATE) |
— |
View ↗
|
| ATY.V |
|
|
OtherRegistration in the Chemical Substances Registry (RSQ) |
La Plata projectEcuador |
Granted |
Ministry of Environment, Water and Ecological Transition (MAATE) |
— |
|
| ATY.V |
|
|
Land access / communityCitizen participation / environmental consultation |
La Plata projectEcuador |
Granted2025-08 |
population residing in the Area of Direct Influence |
allows more than 90% expressed support for granting of the Environmental License3 releases since 2022-11-14 |
|
| NXE.TO |
NexGen Energy Ltd |
2026-02-09 |
Mining licence / leaseCNSC approval (Part 2 Commission Hearing) |
Rook I ProjectSaskatchewan, Canadauranium |
In review |
Canadian Nuclear Safety Commission (CNSC) |
allows Final step in federal regulatory process before CNSC approval decision; Part 2 hearing Feb 9-12, 20262 releases since 2025-11-19 |
View ↗
|
| NXE.TO |
|
|
Land access / community |
Rook I ProjectSaskatchewan, Canadauranium |
Granted |
Four Indigenous Nations in the Local Priority Area (LPA) |
allows Nations speaking at hearing in support of approval of the Project |
|
| EDM.V |
EDM Resources Inc. |
2026-02-09 |
OtherFisheries Act Authorization (FAA) |
Scotia MineNova Scotia, Canada (federal) |
Applied |
Department of Fisheries and Oceans (DFO) |
allows Federal approval for extension of the Scotia Mine's main pit; DFO confirmed receipt and will commence review and consultation |
View ↗
|
| BLLG.CN |
Blue Lagoon Resources Inc. |
2026-02-06 |
Mining licence / leasemining permit |
Dome Mountain Gold and Silver ProjectBritish Columbiagold, silver |
Granted2025-02 |
— |
allows full mining permit; underground mining |
View ↗
|
| BLLG.CN |
|
|
Land access / community |
Dome Mountain Gold and Silver ProjectBritish Columbiagold, silver |
Granted |
Lake Babine First Nation (LBN) |
allows First Nation support for project2 releases since 2023-12-15 |
|
| UUU.CN |
Uranium One Mining Corp. |
2026-02-06 |
Environmental assessmentEnvironmental Licences |
Yuty Prometeo–San Jose Uranium ProjectParaguayuranium |
Granted |
— |
allows Four Environmental Licences covering entire land position; final environmental approvals required |
View ↗
|
| UUU.CN |
|
|
Drill / explorationProspection Permit |
Yuty Prometeo–San Jose Uranium ProjectParaguayuranium |
Applied |
Vice Ministry of Mining and Energy (VMME) |
allows Full-scale uranium exploration authorization across the project area |
|
| QIMC.CN |
Quebec Innovative Materials Corp. |
2026-02-05 |
Drill / explorationNotice of Approval for Phase 1 drilling notification |
Bennett Hill ProjectNova Scotiahydrogen |
Granted |
Nova Scotia Department of Natural Resources and Renewables |
allows Phase 1 three-hole drill campaign, East Advocate area2 releases since 2026-02-04 |
View ↗
|
| QIMC.CN |
|
|
Drill / explorationDrilling regulatory approval |
Eatonville ProjectNova Scotiahydrogen |
Granted |
Nova Scotia Department of Natural Resources and Renewables |
allows Phase 1 three-hole drill campaign, West Advocate; previously announced approval2 releases since 2026-02-04 |
|
| NIOB.CN |
North American Niobium and Critical Minerals Corp. |
2026-02-05 |
Drill / explorationAuthorization for Impact-Causing Exploration Work (ATI) |
Bardy and Blanchette projectsQuébec, Canada |
Applied |
— |
allows Initial ATI application covering both Bardy and Blanchette projects; required prior to diamond drilling; MRNF review may take ~3 months |
View ↗
|
| RDG.V |
Ridgeline Minerals Corp |
2026-02-05 |
Plan of operations / noticePlan of Operations exploration permit |
Swift ProjectNevadagold |
Granted |
— |
allows 200 acres of exploration disturbance; supports drillingheld by Nevada Gold Mines |
View ↗
|
| SRS.CN |
Sorrento Resources Ltd. |
2026-02-05 |
Drill / exploration |
Rodgers Cove Gold ProjectNewfoundland and Labradorgold |
Granted |
— |
allows approximately 1,500 to 2,000 metres of diamond drilling planned |
View ↗
|
| QMET.CN |
QMET.CN |
2026-02-05 |
Drill / explorationNotice of Approval |
West Advocate area, Cumberland CountyNova Scotianatural hydrogen |
Granted |
Nova Scotia regulators |
allows authorizing drilling activities for natural hydrogen explorationheld by Québec Innovative Materials Corp. (QIMC) |
View ↗
|
| WDO.TO |
Wesdome Gold Mines Ltd |
2026-02-03 |
Construction / operatingCertificate of Authorization |
Kiena Mine – Presqu'île ZoneQuébecgold |
Renewed / amended |
— |
allows Updated Certificate of Authorization for Presqu'île Zone |
View ↗
|
| STCU.CN |
Star Copper Corp. |
2026-02-03 |
Drill / explorationDrill permit |
Copperline PropertyBritish Columbiacopper-silver |
Applied |
— |
allows Drill permit for 2026 program |
View ↗
|
| EMPS.CN |
EMP Metals Corp. |
2026-01-30 |
Drill / explorationRe-entry permit |
Project AuroraSaskatchewanlithium |
Granted |
Saskatchewan Ministry of Energy and Resources |
allows re-entry and testing of a brackish water well near the Project Aurora Demonstration Plant site2 releases since 2026-01-29 |
View ↗
|
| EMPS.CN |
|
|
Water |
Project AuroraSaskatchewanlithium |
Granted |
Water Security Agency |
allows re-entry and testing of a brackish water well near the Project Aurora Demonstration Plant site2 releases since 2026-01-29 |
|
| WEX.V |
Western Exploration Inc |
2026-01-28 |
Plan of operations / noticeNotice of Intent (NOI) to submit a Mine Plan of Operations |
Aura Project (Doby George deposit)Nevada, USA |
Granted |
United States Forest Service (USFS) |
allows NOI submitted December 1, 2025; accepted by USFS |
View ↗
|
| WEX.V |
|
|
Environmental assessmentNational Environmental Policy Act (NEPA) environmental reports |
Aura Project (Doby George deposit)Nevada, USA |
Planned2027-Q2 |
United States Forest Service (USFS) |
allows Baseline studies by Stantec begin Feb 2026 over 14 months; NEPA reports targeted for submission Q2 2027 |
|
| SKE.TO |
Skeena Resources Limited |
2026-01-28 |
Construction / operatingEnvironmental Management Act (EMA) permit |
Eskay Creek Gold-Silver ProjectBritish Columbia, Canadagold-silver |
In review |
BC Major Mine Office (MMO) |
allows Final EMA permit expected February 20264 releases since 2023-01-17 |
View ↗
|
| AUEX.CN |
Advanced Gold Exploration Inc. |
2026-01-28 |
Drill / exploration |
Doyle PropertyOntariogold |
Planned |
— |
allows 3,000-metre diamond drilling program, spring 2026 |
View ↗
|
| SKE.TO |
Skeena Resources Limited |
2026-01-27 |
Environmental assessmentEnvironmental Assessment Certificate (EAC) |
Eskay CreekBritish Columbia, Canadagold / silver |
Granted |
B.C. Minister of Mining & Critical Minerals and B.C. Minister of Environment & Parks |
allows Eskay Creek Gold-Silver Project, 100%-ownedheld by Skeena Resources Limited |
View ↗
|
| RKR.V |
Rokmaster Resources Corp |
2026-01-27 |
Drill / explorationDuncan South Permit (Multi-year Area Based Exploration Permit, MYAB Permit) |
Duncan Lake ProjectBritish Columbia, Canadazinc |
Renewed / amended |
British Columbia Ministry of Mining and Critical Minerals |
term two-year extensionallows Up to 26 drill sites and 15 trenches over the next two years; covers No.3, No.2 and No.1 Zones2 releases since 2025-10-16 |
View ↗
|
| SM.V |
Sierra Madre Gold and Silver Ltd |
2026-01-27 |
OtherCambia de Suelos (CUS) change of land use |
Tlacotal propertyEstado de Mexico, Mexico |
Granted |
— |
allows Federal change in land use status from agriculture/forestry to mining, 34.7 hectares; staging area for East District exploration |
View ↗
|
| SM.V |
|
|
Land access / communityLand purchase agreements |
Tlacotal propertyEstado de Mexico, Mexico |
Granted |
— |
term 30-year leaseallows Land purchase agreements covering Tlacotal permit area plus adjacent 33.1 hectares; option to purchase to be exercised upon receipt of ownership transfer documentation |
|
| SM.V |
|
|
Land access / communityLopez Option to Purchase and lease extension |
La Guitarra silver-gold complexEstado de Mexico, Mexico |
Granted |
Lopez (private landowner) |
term additional 30 yearsallows Option to purchase private lands southwest of and under the tailings impoundment facility; lease extended 30 years |
|
| SM.V |
|
|
OtherTailings facility expansion permit |
La Guitarra silver-gold complexEstado de Mexico, Mexico |
Planned |
— |
allows Expansion of current tailings storage facility |
|
| GCR.CN |
GoldCoast Resource Corp. |
2026-01-27 |
Drill / explorationOffshore Reconnaissance Licenses |
Offshore License Area, GhanaGhanagold |
Granted |
Minerals Commission of Ghana |
term 12 months initial term, renewableallows Ten contiguous offshore reconnaissance licenses covering approximately 10,000 square kilometres along Ghana's western offshore continental shelfheld by GoldCoast Resource Corp. |
View ↗
|
| NEXU.CN |
Nexus Uranium Corp. |
2026-01-26 |
Environmental assessmentNEPA public scoping |
Chord uranium projectSouth Dakota, USAuranium |
In review2026-01 |
U.S. Forest Service (USFS) |
allows Federal lands; public scoping commenced mid-January 2026held by Clean Nuclear Energy Corp.4 releases since 2025-09-25 |
View ↗
|
| SCM.CN |
Steadright Critical Minerals Inc. |
2026-01-24 |
Mining licence / leaseMining License |
Copper ValleyMoroccocopper, lead, silver |
Applied |
— |
allows Mining licence application for the Copper Valley historic copper-lead-silver project, lodged by former owner EMTF Sarl and now handled by NSM Capital Sarlheld by EMTF Sarl2 releases since 2026-01-20 |
View ↗
|
| FPX.V |
FPX Nickel Corp |
2026-01-23 |
Environmental assessmentFederal Impact Assessment - Initial Project Description |
Baptiste Nickel ProjectCanada (federal)nickel |
In review |
Impact Assessment Agency of Canada (IAAC) |
allows IPD submitted and accepted; public comment period Feb 5 to Mar 9, 20263 releases since 2023-09-06 |
View ↗
|
| SCM.CN |
Steadright Critical Minerals Inc. |
2026-01-22 |
Mining licence / leaseTitanBeach One Mining License |
TitanBeach OneMoroccotitanium |
Applied |
— |
No. 4039307allows Receipt anticipated in near termheld by NSM Capital Sarl3 releases since 2026-01-20 |
View ↗
|
| QIMC.CN |
Quebec Innovative Materials Corp. |
2026-01-21 |
Environmental assessmentBaseline environmental assessment |
Bennett Hill Study Area, Advocate AreaNova Scotianatural hydrogen |
In review |
— |
allows Preliminary results of baseline environmental assessment by Strum Consulting: no SAR lichen, no black ash, no pileated woodpecker cavities, no material constraints |
View ↗
|
| FAS.V |
First Andes Silver Ltd. |
2026-01-20 |
Drill / explorationExploration licence |
Carrington ProjectNew South Wales, Australiasilver |
Granted |
NSW Resources |
No. ELA 6982term 6 yearsallows Conditional grant; final grant subject to security deposit of A$10,000 per licence and annual rental fees totaling A$9,960 (all three licences)held by Southern Star Pty Ltd. |
View ↗
|
| FAS.V |
|
|
Drill / explorationExploration licence |
Stony Creek ProjectNew South Wales, Australiasilver |
Granted |
NSW Resources |
No. ELA 6983term 6 yearsallows Conditional grant; final grant subject to security deposit of A$10,000 per licence and annual rental fees totaling A$9,960 (all three licences)held by Southern Star Pty Ltd. |
|
| FAS.V |
|
|
Drill / explorationExploration licence |
Dartmoor ProjectNew South Wales, Australiasilver |
Granted |
NSW Resources |
No. ELA 6981term 6 yearsallows Conditional grant; final grant subject to security deposit of A$10,000 per licence and annual rental fees totaling A$9,960 (all three licences)held by Southern Star Pty Ltd. |
|
| SRC.V |
Stakeholder Gold Corp |
2026-01-20 |
Drill / explorationClass 1 Exploration Notification |
Ballarat Gold-Copper ProjectYukon Territory, CanadaGold-Copper |
Granted |
— |
allows Exploration and drilling, including drill testing of Skye Gold Zone and Loki Copper Zone2 releases since 2025-03-11 |
View ↗
|
| TBK.V |
Trailbreaker Resources Ltd. |
2026-01-19 |
Drill / explorationMulti-Year Area-Based (MYAB) Mines Act permit |
Coho propertyBritish Columbia, Canadacopper-gold |
Granted |
BC Ministry of Mining and Critical Minerals |
term 5-yearexpires 2030-12-18allows Diamond drilling from up to 50 drill pads; up to 15 km access trails; 20 line-km ground geophysics; temporary work camp |
View ↗
|
| GPG.V |
Grande Portage Resources Ltd |
2026-01-19 |
Plan of operations / notice2026 Plan of Operations (drill permit) |
New Amalga Gold ProjectSoutheast Alaskagold |
Granted |
— |
allows up to 4,300 m diamond drilling, up to 14 drillholes, instrumentation, surface mapping, trench sampling3 releases since 2024-11-25 |
View ↗
|
| FL.V |
Frontier Lithium Inc |
2026-01-15 |
Land access / communityProcess agreement |
PAK Lithium ProjectOntariolithium |
Granted |
Deer Lake First Nation |
allows Process agreement for permitting of potential all-season road access and mine and mill under 1P1P; builds on exploration agreements since 20162 releases since 2025-03-07 |
View ↗
|
| FL.V |
|
|
Land access / communityProcess agreement |
PAK Lithium ProjectOntariolithium |
Granted |
Sandy Lake First Nation |
allows Process agreement for permitting of potential all-season road access and mine and mill under 1P1P; builds on exploration agreements since 2016 |
|
| FL.V |
|
|
Government / policyOne Project, One Process (1P1P) designation |
PAK Lithium ProjectOntariolithium |
Granted |
Ontario |
allows Anticipated 24-month 1P1P timeline for completion of provincial permitting2 releases since 2025-10-29 |
|
| BMM.V |
Black Mammoth Metals Corporation |
2026-01-15 |
Drill / exploration |
Leadore Silver-Lead-REE propertyLemhi County, Idahosilver-lead-REE |
Granted |
Bureau of Land Management (BLM) |
allows Up to 12 drill sites on BLM-administered lands |
View ↗
|
| SRS.CN |
Sorrento Resources Ltd. |
2026-01-15 |
Drill / explorationPermit to drill |
Bottom Brook ProjectNewfoundlandrare earth |
Granted |
— |
allows Core drilling; minimum 3,000 metres planned across Bottom Brook and Rodgers Cove |
View ↗
|
| ITR.V |
Integra Resources Corp |
2026-01-14 |
Government / policyFAST-41 Transparency Projects Program selection |
DeLamar Heap Leach ProjectIdaho, United Statesgold-silver |
Granted |
Federal Permitting Improvement Steering Council (the "Permitting Council") |
allows Project-specific federal permitting timetable posted to Federal Permitting Dashboard |
View ↗
|
| VG.V |
Volcanic Gold Mines Inc. |
2026-01-13 |
Construction / operatingconstruction license |
Era Dorado ProjectGuatemalagold |
Granted |
— |
allows underground mine; early works commencedheld by Aura Minerals Inc. |
View ↗
|