PMET Resources Submits Environmental and Social Impact Assessment (ESIA) for the Shaakichiuwaanaan CV5 Lithium Project to Federal and Provincial Governments

Permits & Approvals

PMET Resources Inc.

Suite 900 - 1801 McGill College, Montreal, Qc, Canada, H3A 1Z4

www.pmet.ca / TSX: PMET / ASX: PMT / OTC: PMETF / FSE: R9GA

PMET Resources Submits Environmental and Social Impact

Assessment (ESIA) for the Shaakichiuwaanaan CV5 Lithium

Project to Federal and Provincial Governments

April 1, 2026 – Montreal, QC, Canada April 1, 2026 – Sydney, Australia

HIGHLIGHTS

• ESIA Submission: PMET Resources ("PMET" or the "Company") has submitted its

Environmental and Social Impact Assessment (ESIA) for the Shaakichiuwaanaan CV5

Lithium Project, marking the most significant milestone in the Project’s permitting journey

to date. The project is subject to both a provincial and federal impact assessment, both of

which have been submitted for review by respective authorities.

• Technical Foundation: The ESIA, together with the Feasibility Study released in

October 2025, provides the comprehensive data required for government review of the

Shaakichiuwaanaan Lithium Project. The ESIA submission marks the culmination of

over four years of rigorous baseline data collection, technical evaluations, and

extensive engagement with the Cree communities, local sta keholders, and

government partners across all regulatory levels.

• The ESIA encompasses a comprehensive multidisciplinary analysis covering:

o Environmental Baseline Studies : air quality, water resources, terrestrial and

aquatic ecosystems, soil and geology.

o Indigenous consultation and engagement : extensive dialogue with the Cree

Nation, cultural heritage and traditional land use.

o Socio and economic assessment : impacts on employment, community

infrastructure and supply chain benefits.

o Cumulative Effects assessment: assessment of combined impacts with other

projects in the region.

o Climate and Greenhouse Gas Considerations : The climate resilience an d

accounting of total greenhouse gas emissions from the project is included.

o Impact mitigation and management: detailed strategies to minimize

environmental and social effects

Grace Barrasso, PMET EVP of ESG and Corporate Affairs , commented: "The submission

of this ESIA represents the culmination of years of rigorous scientific field work and meaningful dialogue

with our Cree partners. Our goal is to develop Shaakichiuwaanaan as a model for sustainable critical

mineral extraction in North America, ensuring that the environmental and social values of the Eeyou Istchee

are protected while contributing to the global energy transition."

Ken Brinsden, PMET CEO and President , stated: "Moving from discovery to a formal ESIA

submission and a completed Feasibility Study in roughly four years is a testament to the quality and scale

of Shaakichiuwaanaan and the dedication of our team. Congratulations to our team and external advisors

for their contributions to our premier project , creating a strong platform for our continuing engagement

with the Cree and regulators as our project continues down the development pipeline."

PMET RESOURCES INC. (THE “COMPANY” OR “PMET”) (TSX: PMET) (ASX: PMT)

(OTCQX: PMETF) (FSE: R9GA) is pleased to announce the submission of the Environmental

and Social Impact Assessment (ESIA) for its 100% -owned Shaakichiuwaanaan Lithium

Project, located in the Eeyou Istchee James Bay region of Quebec.

The ESIA is a critical regulatory requirement under Section 22 of the James Bay and Northern

Quebec Agreement (JBNQA). Concurrently with the provincial submission, PMET will also be

submitting the ESIA to the federal Impact Assessment Agency of Canada (IAAC) . THESE

SUBMISSIONS, alongside the Positive CV5 Lithium -Only Feasibility Study delivered in late 2025,

forms the dual pillars of the government’s mine authorization process. Together, these documents

detail the technical viability, environmental safeguards, and social integration of the pro posed

hybrid open-pit and underground mine.

LOOKING AHEAD

Following submission of the ESIA, the Federal government will initiate a public review period to

invite comments from communities, regulators and project stakeholders. The report will be

available on the Shaakichiuwaaan Mining Project Page published on the Canadian Impact

Assessment Registry at: https://iaac-aeic.gc.ca and Québec portals.

The Company remains committed to maintaining a transparent and timely approval process,

working closely with all levels of government and the Cree Nation to bring this world-class lithium

asset into production over the coming years.

ABOUT PMET RESOURCES INC.

PMET Resources Inc. is a pegmatite critical mineral exploration and development company focused

on advancing its district -scale 100% -owned Shaakichiuwaanaan Property located in the Eeyou

Istchee James Bay region of Quebec, Canada, which is accessible year -round by all -season road

and proximal to regional hydro-power infrastructure.

In late 2025, the Company announced a positive lithium -only Feasibility Study on the CV5

Pegmatite for the Shaakichiuwaanaan Property and declared a maiden Mineral Reserve of 84.3 Mt

at 1.26% Li2O (Probable)1. The study outlines the potential for a competitive and globally significant

high-grade lithium project targeting up to ~800 ktpa spodumene concentrate using a simple Dense

Media Separation (“DMS”) only process flowsheet. Further, the results highlight

1 See Feasibility Study news release dated October 20, 2025. Probable Mineral Reserve cut-off grade is 0.40% Li2O (open-pit) and 0.70%

Li2O (underground). Underground development and open-pit marginal tonnage containing material above 0.37% Li2O are also included in the

statement. Effective Date of September 11, 2025.

Shaakichiuwaanaan as a potential North American critical mineral powerhouse with significant

opportunity for tantalum and caesium in addition to lithium.

The Project hosts a Consolidated Mineral Resource2 totalling 108.0 Mt at 1.40% Li2O and 166 ppm

Ta2O5 (Indicated) and 33.4 Mt at 1.33% Li2O and 155 ppm Ta2O5 (Inferred), and ranks as a top ten

lithium pegmatite globally in size. Additionally, the Project hosts the world’s largest pollucite-

hosted caesium pegmatite Mineral Resource at the Rigel and Vega zones with 0.69 Mt at 4.40%

Cs2O (Indicated), and 1.70 Mt at 2.40% Cs2O (Inferred).

For further information, please contact us at [email protected] or by calling +1 (604) 279- 8709, or

visit www.pmet.ca. Please also refer to the Company’s continuous disclosure filings, available under

its profile at www.sedarplus.ca and www.asx.com.au, for available exploration data.

This news release has been approved by

“KEN BRINSDEN”

Kenneth Brinsden, President, CEO, & Managing Director

Olivier Caza-Lapointe

Head, Investor Relations

T: +1 (514) 913-5264

E: [email protected]

DISCLAIMER FOR FORWARD-LOOKING INFORMATION

This news release contains “forward -looking statements” and “forward -looking information”

within the meaning of applicable securities laws.

All statements, other than statements of present or historical facts, are forward -looking

statements. Forward -looking statements involve known and unknown risks, uncertainties and

assumptions and accordingly, actual results could differ materially from those expressed or implied

in such statements. You are hence cautioned not to place undue reliance on forward- looking

statements. Forward -looking statements are typically identified by words such as “plan”,

“development”, “growth”, “continued”, “intentions”, “expectations”, “emerging”, “evolving”,

“strategy”, “opportunities”, “anticipated”, “potential”, “additional”, “on track”, “prospects”,

“estimated”, “enhancing”, “strengthen”, “target”, “believes”, “next steps” , “looking ahead”,

“remains committed”, “to bring” , “coming years” or variations of such words and phrases or

statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be

taken, occur or be achieved.

Forward-looking statements include, but are not limited to, statements concerning the permitting

process for the Shaakichuwaanaan Project.

2 The Consolidated MRE (CV5 + CV13 pegmatites), which includes the Rigel and Vega caesium zones, totals 108.0 Mt at 1.40% Li2O, 0.11%

Cs2O, 166 ppm Ta2O5, and 66 ppm Ga, Indicated, and 33.4 Mt at 1.33% Li 2O, 0.21% Cs2O, 155 ppm Ta2O5, and 65 ppm Ga, Inferred,

and is reported at a cut-off grade of 0.40% Li2O (open-pit), 0.60% Li2O (underground CV5), and 0.70% Li2O (underground CV13). A grade

constraint of 0.50% Cs2O was used to model the Rigel and Vega caesium zones. The Effective Date is June 20, 2025 (through drill hole CV24-

787). Mineral Resources are not Mineral Reserves as they do not have demonstrated economic viability. Mineral Resources are inclusive of

Mineral Reserves.

Forward-looking statements are based upon certain assumptions and other important factors that,

if untrue, could cause actual results to be materially different from future results expressed or

implied by such statements. There can be no assurance that forward-looking statements will prove

to be accurate. Key assumptions upon which the Company’s forward-looking information is based

include, without limitation, the results of the Feasibility Study released in October 2025, the ability

to complete an updated Feasibility Study for the CV5 Pegmatite with the addition of tantalum as a

co-product, as well as a Preliminary Economic Assessment for the broader Project inclusive of

lithium, caesium, and tantalum, that proposed exploration work on the Property and the results

therefrom will continue as expected, the accuracy of reserve and resource estimates, the

classification of resources and the assumptions on which the reserve and resource estimates are

based, long-term demand for lithium (spodumene), tantalum (tant alite), and caesium (pollucite)

supply, and that exploration and development results continue to support management’s current

plans for the Property’s development.

Forward-looking statements are also subject to risks and uncertainties facing the Company’s

business, any of which could have a material adverse effect on the Company’s business, financial

condition, results of operations and growth prospects. Readers should review the detailed risk

discussion in the Company’s most recent Annual Information Form filed on SEDAR+, for a fuller

understanding of the risks and uncertainties that affect the Company’s business and operations.

Although the Company believes its expectations are based upon reasonable assumptions and has

attempted to identify important factors that could cause actual actions, events or results to differ

materially from those described in forward -looking statements, there may be other factors that

cause actions, events or results not to be as anticipated, estimated or intended. There can be no

assurance that forward -looking information will prove to be accurate. If any of the risks or

uncertainties mentioned above, which are not exhaustive, materialize, actual results may vary

materially from those anticipated in the forward-looking statements.

The forward- looking statements contained herein are made only as of the date hereof. The

Company disclaims any intention or obligation to update or revise any forward-looking statements,

whether as a result of new information, future events or otherwise, except to the extent required

by applicable law. The Company qualifies all of its forward-looking statements by these cautionary

statements.

COMPETENT PERSON STATEMENT (ASX LISTING RULES)

The information in this news release that relates to the Feasibility Study (“FS”) for the

Shaakichiuwaanaan Project, which was first reported by the Company in a market announcement

titled “ PMET Resources Delivers Positive CV5 Lithium -Only Feasibility Study for its Large -Scale

Shaakichiuwaanaan Project” dated October 20, 2025 (Montreal time) is available on the Company’s

website at www.pmet.ca , on SEDAR+ at www.sedarplus.ca and on the ASX website at

www.asx.com.au. The production target from the Feasibility Study referred to in this news release

was reported by the Company in accordance with ASX Listing Rule 5.16 on the date of the original

announcement. The Company confirms that, as of the date of this news releas e, all material

assumptions and technical parameters underpinning the production target in the original

announcement continue to apply and have not materially changed.

The Mineral Resource and Mineral Reserve Estimates in this release were first reported by the

Company in accordance with ASX Listing Rule 5.8 in market announcements titled "World's Largest

Pollucite-Hosted Caesium Pegmatite Deposit " dated July 20, 2025 (Montreal time) and “ PMET

Resources Delivers Positive CV5 Lithium -Only Feasibility Study for its Large- Scale Shaakichiuwaanaan

Project” dated October 20, 2025 (Montreal time) and are available on the Company’s website at

www.pmet.ca, on SEDAR+ at www.sedarplus.ca and on the ASX website at www.asx.com.au. The

Company confirms that, as of the date of this news release, it is not aware of any new information

or data verified by the competent person that materially affects the information included in the

relevant announcement and that all material assumptions and technical parameters underpinning

the estimates in the relevant announcement continue to apply and have not materially changed.

The Company confirms that, as at the date of this announcement, the form and context in which

the competent person’s findings are presented have not been materially modified from the original

market announcement.