Frontier Lithium Signs Process Agreements with Deer Lake and Sandy Lake First Nations and Advances Permitting Under Ontario's One Project, One Process Framework

Permits & Approvals

Frontier Lithium Signs Process Agreements

with Deer Lake and Sandy Lake First Nations

and Advances Permitting Under Ontario's One

Project, One Process Framework

GREATER SUDBURY, ON

,

Jan. 15, 2026

/CNW/ - Frontier Lithium Inc. (TSXV: FL) (OTC: LITOF)

(FRA: HL2) ("Frontier" or the "Company") is pleased to announce that it has entered into process

agreements with Deer Lake First Nation and

Sandy Lake First Nation

. The agreements reflect a

commitment to proceed in a manner that recognizes the regulatory requirements of the project as

well as a commitment to respect Anishinninew laws and protocols which will help further build

relationships that support the advancement of project permitting processes for potential all-season

road access, and the potential construction and operation of a mine and mill.

These process agreements are intended to provide structure, transparency, and predictability for all

parties as technical studies and permitting activities progress under the One Project, One Process

(1P1P) framework. The agreements reflect a shared commitment to early engagement, information

sharing, and supporting meaningful participation throughout both First Nations and Crown approval

processes. This is consistent with both Anishinninew laws and protocols, and with

Ontario's

stated

objective that Indigenous communities be closely involved from the outset of comprehensive project

reviews and that approvals be streamlined without weakening environmental protections.

With the implementation of these agreements and

Ontario's

1P1P framework, Frontier is positioned

to advance permitting in a more coordinated and efficient manner, aligning provincial requirements

while maintaining a strong focus on consultation and environmental stewardship, and respecting

Anishinninew laws and protocols. The agreements with

Deer Lake

and

Sandy Lake First Nations

build on the last decade of relationship building including the exploration agreements that have been

in place since 2016.

"These process agreements represent what Frontier considers a best practice for how exploration

and mining companies approach Indigenous engagement," said

Trevor Walker

, President and CEO

of Frontier Lithium. "We are excited to keep moving forward, and we view these agreements as

essential to ensuring that any consideration of the Project proceeds in a coordinated manner that

integrates Indigenous perspectives with provincial regulatory processes. We are committed to

learning from and working with Deer Lake First Nation and

Sandy Lake First Nation

, guided by

Anishinninew law, in a way that is respectful and grounded in their responsibilities to the land."

"Deer Lake First Nation has been clear that any development in our territory must proceed with

transparency, respect, and meaningful participation from our community," stated Chief

Lenard

Mamakeesick

of Deer Lake First Nation. "Our process agreement is an important step in setting out

how we will be engaged as Frontier's project moves through

Ontario's

One Project, One Process

framework, and reflect how our concerns about the land, water, and future generations will be heard

and considered."

"

Sandy Lake First Nation

has a responsibility to protect our lands, waters, and future generations.

These process agreements create clarity around how information will be shared and how our laws

and protocols will be respected as the Project is considered. We look forward to working

cooperatively with Frontier through a structured process that supports transparency, community

participation, and careful consideration of potential development."

"

Ontario

is proving that you can move major critical mineral projects forward through real

partnership," said Stephen Lecce,

Ontario

Minister of Energy and Mines. "

Ontario's

One Project,

One Process designation for Frontier Lithium's PAK project is driving this job creating project

forward with speed and in meaningful partnership with Deer Lake First Nation and

Sandy Lake First

Nation

so that we build the mines

Ontario

needs to power the clean economy of the future."

Through these process agreements, Frontier and the participating First Nations are establishing a

clear, coordinated framework to support the disciplined and transparent consideration of the project.

This approach is intended to align with the Province's stated goal of reducing government review

timelines by 50% and Frontier's anticipated 24-month 1P1P timeline for the completion of Provincial

permitting. Throughout this process, a commitment to respecting and learning Anishinninew laws and

protocols, environmental protections, and community priorities will remain central to decision-making.

ON BEHALF OF THE BOARD OF DIRECTORS

Trevor Walker

, President & CEO

About Frontier Lithium

Frontier Lithium Inc. is a pre-production mining company with an objective to become a strategic and

integrated supplier of premium spodumene concentrates as well as battery-grade lithium salts to the

growing electric vehicle, and energy storage markets in

North America

. The Company's PAK Lithium

Project maintains the largest land position and resource in a premium lithium mineral district located

in

Ontario's

Great Lakes region.

About the PAK Lithium Project

The PAK Lithium Project is a fully integrated critical minerals initiative in

Ontario

, developing a high-

grade, large scale lithium resource. Operated as a joint venture between Frontier (92.5%) and

Mitsubishi Corporation (7.5%), the project is advancing in parallel with a mine and mill, north of

Red

Lake, Ontario

and a downstream lithium conversion facility in

Thunder Bay, Ontario

, which are both

key to supporting a secure domestic lithium supply for the clean energy transition. A 2025 Mine and

Mill Feasibility Study (FS), prepared by DRA Global Limited and entitled National Instrument 43-101

Technical Report FS PAK Lithium Project, Mine and Mill, outlines a 31-year Project life with an after-

tax net present value of

$932 million

at an 8% discount rate and an after-tax internal rate of return of

17.9%.These results have been disclosed in the Company's press release dated

May 28, 2025

, and

the accompanying technical report was filed on SEDAR+ (

www.sedarplus.ca

) on

July 9, 2025

.

Cautionary Note Regarding Forward-Looking Statements

This news release includes certain statements that may be deemed "forward-looking statements".

All statements in this release, other than statements of historical fact constitute forward-looking

statements. Forward looking statements contained in this news release may include, but are not

limited to, the EY study estimates including but not limited to gross spending, GDP, wages, full time

equivalent employment and possible tax revenue, the PAK Lithium Project and its estimated

economics, and statements with respect to: capital requirements and private and/or public financing

initiatives and completion of these financings (if any), estimated mineral resources, estimated capital

costs to construct a mine and conversion facilities, estimated operating costs, estimated cash flows,

net present value, the Feasibility Study and statements that address future production, resource and

reserve potential, exploration drilling, exploitation activities and events or developments that the

Company expects, including but not limited to capital and operating costs, timelines, internal rates of

return, and project development milestones.

Forward-looking statements involve inherent risks and uncertainties. Risk factors that could cause

actual results to differ materially from those in forward looking statements include: market prices for

commodities, increases in capital or operating costs, construction risks, availability of infrastructure

including roads, regulatory and permitting risks, exploitation and exploration successes, continued

availability of capital and financing, financing costs, and general economic, market or business

conditions. Investors are cautioned that any such statements are not guarantees of future

performance and those actual results or developments may differ materially from those projected in

the forward-looking statements. For more information on the Company, please review the

Company's public filings available at

www.sedarplus.ca

.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is

defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy

or accuracy of this release.

SOURCE

Frontier Lithium Inc.

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/January2026/15/c8776.html

%SEDAR: 00008434E

For further information:

Company Contact Information: Bora Ugurgel, Senior Manager, Investor

Relations, 2614 Belisle Drive, Val Caron, Greater Sudbury, Ontario, P3N 1B3 CANADA, T. +001

705.897.7622, F. +001 705.897.7618

CO: Frontier Lithium Inc.

CNW 09:01e 15-JAN-26