Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ZNX.V ·

ZincX Resources Provides Update on Metallurgical Test Work By Tongling

Metallurgy & Processing

FOR IMMEDIATE RELEASE

Contact: Investor Relations Monday, November 7, 2022

Phone (604) 684-2181 (No.2022-11-06)

[email protected]

ZincX Resources Provides Update on Metallurgical Test Work By

Tongling

Vancouver, British Columbia, Canada – Monday, November 7, 2022 – ZincX Resources Corp.

(“ZincX” or the “Company”, TSX Venture Exchange: ZNX, US: ZNCXF, FRA: M9R ) is pleased to

provide an update on the detailed metallurgical test work that is underway on the Cardiac Creek drill core

samples collected from the 2021 diamond drilling program. The samples were shipped to China in Q1 2022.

The test work is being conducted at the Hunan Research Institute and the work is being overseen by the

Company’s strategic partner Tongling Non-Ferrous Metals of China (Tongling).

The Company has been informed by Tongling that the initial phase of the planned metallurgical test work

is currently underway on the drill core. This includes waste disposal tests such as photoelectric waste

disposal, centrifugal waste disposal and decarbonization via flotation. Additional test work of the material is

ongoing. The Company is anticipating receiving additional information in the coming weeks.

The test work will include the following phases: (1) elimination of carbonaceous gangue on lead-zinc-silver

flotation; (2) lead-zinc flotation test; (3) beneficiation wastewater treatment and reuse test; (4) mineral

processing product inspection; (5) analysis of tailings dry heap storage method; and (6) mineral processing

technology and economic evaluation.

Mr. Peeyush Varshney, President and CEO commented,

“We are delighted to be working with our strategic partner Tongling to further enhance both the metallurgical

characteristics and economical potential of the deposit. We look forward to further updates from Tongling

on the ongoing metallurgical test work that is being carried out on the drill core from the Cardiac Creek

deposit.”

The 2021 Drill Program

The Company completed a large-diameter HQ diamond drill program in 2021 consisting of five holes

totalling 2,669 metres with an objective of acquiring mineralized drill core samples for advanced

metallurgical testing. The drill holes targeted specific areas of the deposit along the northwest, down-dip,

and southeast boundaries of the High-Grade core in order to provide samples that tests the variability of

the deposit across its strike and width. All five holes successfully tested the Cardiac Creek Zone with

excellent recovery of thick intervals of sphalerite-galena-barite mineralization. Greater than 500 HQ drill

core samples were submitted and analyzed. A total of six individual metallurgical samples were selected,

two from hole A-21-156B and one from each of the remaining drill holes. Individual samples averaged 228

kilograms and the total combined weight is in excess of 1350 kilograms. These samples will be used to

continue to investigate the metallurgical response of the mineralization with a focus on enhancing

recoveries and boosting concentrate grades for both zinc and lead.

The Akie Zn-Pb-Ag Project

The 100% owned Akie property is situated within the Kechika Trough, the southernmost area of the

regionally extensive Paleozoic Selwyn Basin and one of the most prolific sedimentary basins in the world

for the occurrence of SEDEX zinc-lead-silver and stratiform barite deposits.

Drilling on the Akie property by ZincX Resources since 2005 has identified a significant body of baritic-zinc-

lead SEDEX mineralization known as the Cardiac Creek deposit. The deposit is hosted by siliceous,

carbonaceous, fine-grained clastic rocks of the Middle to Late Devonian Gunsteel Formation.

The Company updated the estimate of mineral resources at Cardiac Creek in 2018, as follows:

5% Zinc Cut-Off Grade Contained Metal:

Category Tonnes

(million) Zn (%) Pb (%) Ag (g/t) Zn (B lbs) Pb (B lbs) Ag (M

oz)

Indicated 22.7 8.32 1.61 14.1 4.162 0.804 10.3

Inferred 7.5 7.04 1.24 12.0 1.169 0.205 2.9

The Company announced robust positive results from the 2018 Preliminary Economic Assessment (PEA).

The PEA envisages a conventional underground mine and concentrator operation with an average

production rate of 4,000 tonnes per day. The mine will have an 18-year life with potential to extend the life-

of-mine (LOM) through resource expansion at depth. Key parameters for the PEA are as follows:

Parameter Base Case1

Tonnes Mined 25.8 Mt

Mined Head Grades 7.6% Zn; 1.5% Pb; 13.08 g/t Ag

Tonnes Milled 19.7 Mt

Milled Head Grades (after DMS2 upgrade) 10.0% Zn; 1.9% Pb; 17.17 g/t Ag

Total Payable Metal (LOM) $3,960M3

Initial CAPEX $302.3M including $45.7M contingency

LOM Total CAPEX $617.9M including $58.5M contingency

All-in Total OPEX $102.4 per tonne milled

Pre-Tax NPV7% $649M

Pre-Tax IRR 35%

Pre-Tax Payback 2.6 years

After-Tax NPV7% $401M

After-Tax IRR 27%

After-Tax Payback 3.2 years

1. The base case used metal prices are calculated from the 3-year trailing average coupled with two year forward projection of the

average price; and are: US$1.21/lb for zinc, US$1.00/lb for lead and US$16.95 for silver. A CDN$/US$ exchange rate of 0.77 was

used. The NPV discount rate is 7%. 2. DMS = dense media separation. 3. All dollar amounts expressed in Canadian dollars.

The PEA is considered preliminary in nature and includes mineral resources, including inferred mineral resources that are considered

too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral

reserves. Mineral resources that are not mineral reserves have not yet demonstrated economic viability. Due to the uncertainty that

may be attached to mineral resources, it cannot be assumed that all or any part of a mineral resource will be upgraded to mineral

reserves. Therefore, there is no certainty that the results concluded in the PEA will be realized.

Kechika Regional Project

In addition to the Akie Project, the Company owns 100% of eight of eleven large, contiguous property blocks

that comprise the Kechika Regional Project including the advanced Mt. Alcock prospect. The Kechika

Regional Project also includes the Pie, Yuen and Cirque East properties which the Company maintains a

significant 49% interest with partners Teck Resources Limited (TSX: TECK.B) and Korea Zinc Co. Ltd

holding 51%. These properties collectively extend northwest from the Akie property for approximately 140

kilometres covering the highly prospective Gunsteel Formation shale; the main host rock for known SEDEX

zinc-lead-silver deposits in the Kechika Trough of northeastern British Columbia. These projects are located

approximately 260 kilometres north northwest of the town of Mackenzie, British Columbia, Canada.

Ken MacDonald P.Geo., Vice President of Exploration for the Company, is the designated Qualified Person

as defined by National Instrument 43-101 and is responsible for the technical information contained in this

release. Mike Makarenko P.Eng, JDS Energy and Mining, is the designated Qualified Person as defined by

National Instrument 43-101 and is responsible for the PEA technical information contained in this release.

(1) Murrell, M., and Roberts, W., 1990; Summary Report, 1989 Exploration Program on the Mt. Alcock Property, British Columbia Ministry of Energy, Mines and Petroleum

Resources, Assessment Report 19829A & B, 133p.

(2) Carne, R.C., 1980; Report on Diamond Drilling on the Bear and SI Claim Group, British Columbia Ministry of Energy, Mines and Petroleum Resources, Assessment Report

8626, 51p.

The TSX Venture Exchange has neither approved nor disapproved the contents of this press release.

ON BEHALF OF THE BOARD OF DIRECTORS

ZINCX RESOURCES CORP.

“PEEYUSH VARSHNEY”

PEEYUSH VARSHNEY, LL.B

CEO & CHAIRMAN