Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ZNX.V ·

ZincX Announces Positive Preliminary Economic Assessment for the Cardiac Creek (Akie Property) Zinc-Lead-Silver Deposit

Economic Studies

FOR IMMEDIATE RELEASE

Contact: Investor Relations Wednesday, June 20, 2018

Phone (604) 684-2181 (No.2018-06-09)

[email protected]

ZincX Announces Positive Preliminary Economic Assessment

for the Cardiac Creek (Akie Property) Zinc-Lead-Silver Deposit

Vancouver, British Columbia, Canada – Wednesday, Ju ne 20, 2018 – ZincX Resources Corp.

(“ZincX” or “the Company”, TSX Venture Exchange: ZN X) is pleased to announce it has received

positive and robust results from the recently commissioned independent Preliminary Economic Assessment

(“PEA”) for the 100% owned zinc-lead-silver Cardiac Creek deposit located on the Akie property in

northeast British Columbia, Canada.

Economic Highlights:

• Estimated pre-tax NPV 7% of $649M ($401M after-tax)

• Estimated pre-tax 35% IRR (27% after-tax)

• Estimated pre-tax 2.6 year payback (3.2 year payback after-tax)

• PEA contemplates a 4,000 tonne per day underground mine and 3,000 tonne per day

concentrator with an 18-year mine life

• Total mine production of 25.8 million tonnes of which 19.7 million tonnes are processed

• Initial CAPEX (excluding contingency) estimated at $256.7M; total of $302.3M including $45.7M in

contingency

• Payable metal production over life-of-mine is 3,268M lbs of zinc & 362M lbs of lead

• Average annual production of 178M lbs of payable zinc and 20M lbs of payable lead at an all-in

operating cost of $102.38/tonne milled

• Total payable metal LOM is $3,960M; or $201/tonne milled

• Saleable zinc and lead concentrates with no penalty elements (clean concentrate )

• There are no net smelter royalties owed ( 0% NSR )

• Opportunities for continued refinement through additional studies including upgrading lead and

silver recoveries and reducing operating costs

• The Cardiac Creek deposit remains open at depth with potential to increase mine life

• Akie and Kechika Regional combined offer district-scale potential for new discoveries

The PEA is considered preliminary in nature and incl udes mineral resources, including inferred mineral re sources that are considered too speculative

geologically to have the economic considerations app lied to them that would enable them to be categorized as mineral reserves. Mineral resources that

are not mineral reserves have not yet demonstrated e conomic viability. Due to the uncertainty that may be attached to mineral resources, it cannot be

assumed that all or any part of a mineral resource will be upgraded to mineral reserves. Therefore, there is no certainty that the results concluded in the

PEA will be realized.

“The positive results outlined in the PEA demonstrate a robust, stand-alone base metal project with a large

and potentially growing resource base, all-season a ccess; good rail and road infrastructure and amenab le

to conventional mining and milling practices common to similar projects. We are delighted with the str ong

results of the PEA and intend to now move to advance the project through feasibility, permitting and towards

production. This project has significant exposure to zinc given the almost 10 to 1 zinc to lead ratio

in payable metal production over life-of-mine.

We have a strong competitive advantage that will appeal to mining and investment partners, including 100%

ownership, 0% NSR, long-term mineral tenure securit y, good stable jurisdiction, and strong First Natio n

community support. The PEA demonstrates low risk ec onomics and well-established mining and milling

techniques,” stated Mr. Peeyush Varshney, President and CEO.

Additional optimization studies are anticipated to improve the overall economics. Specific areas of

advancement include:

• Additional metallurgical variability testing to op timize metal recoveries and include silver as a

payable

• Optimize dense media separation (DMS) circuit by u sing a coarser grind in future testing

• Investigate optimal grinding size to improve lead liberation

• Reduce reagent and collector dosages to reduce mil l OPEX

• Continue discussions with rail companies to furthe r reduce transportation costs to Trail smelter

• Exploration potential remains open at depth at the Cardiac Creek deposit and significant upside

remains as higher grades seem to be improving with depth. Further drill testing is required to

delineate the down-dip potential

• District-scale exploration potential exists over t he 800 square kilometre highly prospective land

package. Additional focused exploration is planned

PEA Results

The PEA was completed by JDS Energy & Mining Inc. (JDS) of Vancouver, British Columbia. JDS is widely

known in the mining space for fit-for-purpose desig n and fundamentally sound technical engineering

studies. All inputs are based on budget quotations , peer comparisons and JDS’ recent experience in

projects of similar scope. All figures are quoted in CDN$ unless otherwise noted.

The PEA envisages a conventional underground mine a nd concentrator operation with a small

environmental footprint measuring approximately 20 hectares in size upon startup, growing to

approximately 35 hectares at closure. The mine will produce an average production rate of 4,000 tonnes

per day (tpd) principally from longhole stoping. Mu ch of the waste rock and the majority of the volume of

mill tailings will be placed back underground as ce mented backfill. The remainder of filtered tailings will be

stacked in a surface filtered tailings facility located near the mill.

The mine will have an 18-year life with potential t o extend the life-of-mine (LOM) through resource

expansion at depth. Key parameters for the PEA are summarized in the tables below.

The estimated pre-tax NPV 7% is $649M, with a 35% IRR and 2.6 year payback ; post-tax NPV 7% is $401M,

with a 27% IRR and 3.2 year payback .

Total payable LOM metal production is expected to b e 3,268 million pounds of zinc and 362 million

pounds of lead . Silver is not expected to be a payable due to rel atively low head grade and anticipated

smelter deductions. Future metallurgical work will continue to optimize the lead and zinc circuits to improve

recoveries and potentially add silver as a payable metal.

The pre-production capital cost (CAPEX) is estimated at $256.7M, for a total of $302.3M including $45.7M

contingency . Sustaining capital is estimated at $302.7M, for a total of $315.6M including $12.9M

contingency .

The total estimated capital cost over LOM, including closure costs but net of salvage value, is estimated at

$559.4M; for a total of $617.9M including $58.5M contingency. The majority of mine construction is

expected to take approximately 24 months.

The average on-site all-in operating costs (OPEX) t otal $102.38 per tonne processed, which includes

$38.13 per tonne mined for mining, $33.13 per tonne milled for milling, $2.87 per tonne milled for tailings

and DMS rejects, and $16.33 per tonne milled for general and administrative (G&A).

The base case used metal prices are calculated from the 3 year trailing average coupled with two year

forward projection of the average price; and are: US$1.21/lb for zinc , US$1.00/lb for lead and US$16.95

for silver . A CDN$/US$ exchange rate of 0.77 was used. The NPV discount rate is 7% .

Table 1: Summary of Key Parameters

Parameter Base Case Spot Price 1

Mine Life 18 years

Mine Production Rate 4,000 tpd

Plant Throughput (LOM

average; after DMS) 3,000 tpd

Tonnes Mined 25.8 Mt

Mined Head Grades 7.6% Zn; 1.5% Pb; 13.08 g/t Ag

Tonnes Milled 19.7 Mt

Milled Head Grades (after

DMS upgrade) 10.0% Zn; 1.9% Pb; 17.17 g/t Ag

Total Payable Metal (LOM) $3,960M $4,888M

Total Operating Expenses

(LOM) $2,014M $2,014M

Net (Pre-tax) Operating

Income (LOM) $1,946M $2,874M

Net Pre-tax Cash Flow (LOM)

$1,328M

$74M/year

$2,257M

$125M/year

Net After-tax Cash Flow (LOM) $870M

$48M/year

$1,459M

$81M/year

Pre-Tax NPV 7% $649M $1,160M

Pre-Tax IRR 35% 52%

Pre-Tax Payback 2.6 years 1.8 years

After-Tax NPV 7% $401M $727M

After-Tax IRR 27% 40%

After-Tax Payback 3.2 years 2.2 years

1. Spot prices at close of London Metal Exchange on June 15, 2018: US$1.42/lb Zn; US$1.08/lb Pb; US$16.95/oz Ag

Table 2: Summary of Capital Expenditures

Capital Costs Initial ($M) Sustaining ($M) LOM Total ($M)

Mining 58.2 260.0 318.2

Site Development 7.5 0.7 8.2

Mineral Processing 78.8 11.8 90.6

Tailings Management 5.0 8.3 13.3

On-Site Infrastructure 55.1 6.3 61.4

Off-Site Infrastructure 1.0 0.2 1.2

Project Indirects 28.0 5.1 33.2

Engineering and Project Management 17.4 1.5 18.8

Owner Costs 5.6 - 5.6

Closure - 8.9 8.9

Total 256.7 302.7 559.4

Contingency 45.7 12.9 58.5

Total 302.3 315.6 617.9

$/Tonne mined 11.71 12.22 23.92

Table 3: Summary of Operating Costs

Average Operating Costs Per tonne milled LOM

Mining $50.05* $984.7M

Processing $33.13 $651.7M

Tailings & DMS Rejects $2.87 $56.5M

G&A $16.33 $321.3M

All-in Total OPEX $102.38 $2,014.1M

*38.13/tonne mined

Table 4: Summary of Payable Metal Production

Metal Per annum (avg M lbs/yr) LOM (M lbs)

Zinc 178 3,268

Lead 20 362

Total Payable

Metal $ LOM $/tonne milled

$3,960 $201

Table 5: Sensitivity Analysis

-$0.10 Base Case +$0.10

Zinc (US$/lb.) US$1.11 US$1.21 US$1.31

Lead (US$/lb.) US$0.90 US$1.00 US$1.10

Pre-tax

NPV 7% $389M $649M $908M

IRR 25% 35% 44%

Payback 3.5 years 2.6 years 2.1 years

Post-tax

NPV 7% $234M $401M $567M

IRR 20% 27% 34%

Payback 4.1 years 3.2 years 2.7 years

Table 6: Exchange Rate Sensitivity Analysis

-0.02 Base Case +0.02

CDN$:US$ 0.75 0.77 0.79

Pre-tax

NPV 7% $718M $649M $583M

IRR 37% 35% 33%

Payback 2.5 years 2.6 years 2.8 years

Infrastructure

The Akie property is accessible year-round by a net work of all-weather logging roads leading north fro m

Mackenzie, BC. It is expected that the Company will share in road maintenance expenses with other

resource users including local forestry licensees and mining companies. Mackenzie is connected to the BC

provincial highway network via Highway 39 that bran ches off of Highway 97. No road or bridge upgrades

are anticipated and road maintenance costs are fact ored into the concentrate trucking costs from site to

Mackenzie.

Power will be generated onsite using liquefied natural gas (LNG) powered portable generators each with a

2,500 kW capacity. The connected load is estimated to be less than 18 megawatts.

A modular 250 person all-weather camp will be constructed and installed during the pre-production period,

and will serve both the construction and lifetime operation phases of the project.

JDS evaluated several concentration transportation options to deliver concentrate from the Akie projec t to

either the Port of Prince Rupert (for shipment overseas to an Asian smelter) or to the Trail Smelter located

in southeastern BC and owned by Teck Resources. Two options for each destination were evaluated for

transporting zinc concentrate; these included truck ing the entire distance from site to the final dest ination;

or trucking from site to Mackenzie, BC, and then vi a rail from Mackenzie to the final destination. It is

assumed that a rail load out facility at Mackenzie BC will be available for use.

After a careful assessment of cost it was determined that the most efficient transportation option for zinc is

to truck haul the concentrate from site to Mackenzie and load onto rail cars for delivery to the Trail smelter.

Zinc concentrate will be initially shipped bulk in covered ore hauler trailers and then by covered gon dola

rail cars. The lead concentrate will be truck haule d direct from site to the Trail smelter. Lead conce ntrate

will be shipped in sealed bags or totes, inside 20’ shipping containers, which act as double containment as

a safety precaution. The containers are limited to 20’ length due to weight restrictions and because CN Rail

does not have the ability to cost effectively handle and manage the 20’ containers, rail is not a viable option

for the lead concentrate.

Mining & Processing

The PEA is based on a conventional underground mine similar to other operations in Canada. The deposit

will be accessed via a main underground production haulage way with secondary ingress/egress provided

by a secondary portal and a vent raise to surface. Stope spacing is estimated at 20 metres. Mining dilution

is estimated at 15% with 95% recovery predicted.

Given the steep dip of the deposit (-75 degrees) th e deposit is amenable to longitudinal longhole open

stoping as the main method of underground mining. Underground mining equipment will include twin boom

jumbos, longhole drills, LHD scoop trams, haul trucks and support mobile equipment.

A concentrator with conventional milling and flotat ion is envisaged to be built on-site. The process p lant

contemplates 3,000 tonnes per day throughput and will include 3-stage crushing circuit, a DMS circuit and

a grinding circuit using ball mills. Sequential zinc and lead flotation circuits will incorporate cleaning stages.

The concentrate dewatering will use thickeners and pressure filters.

Recent metallurgical testwork conducted in 2017 and announced on the 9 th of April, 2018 was utilized by

the PEA. This work indicates that marketable zinc a nd lead concentrates could be produced from the

deposit with no deleterious substances or penalty elements.

Knight Piésold Ltd. (KP), a consultant to JDS, deve loped the tailings, waste and water management plan

for the PEA. KP assessed tailings management technologies and potential storage locations to support the

study. KP and JDS concluded that the preferred wast e management strategy is to store Potentially Acid

Generating (PAG) waste rock and the bulk of the tailings (approx. 70%) in mined-out underground stopes ,

based on the geochemical characteristics of the was te materials and the need for structural backfill. The

remaining waste materials, including Non-Potentially Acid Generating (NPAG) waste rock, DMS rejects and

the balance of tailings not used for backfill (appr ox. 30%), will be stored on surface in a filtered t ailings

management facility (TMF), which allows the DMS reject and filtered tailings to be co-mingled into a single

facility. A separate water management pond is included for managing process water and storm water runoff

from the surface of the TMF.

Next Planned Steps:

The Company will be working closely with its mining consultants and advisors to plot a course forward for

the most cost effective and efficient development o f the Cardiac Creek deposit. The Company anticipate s

more detailed engineering assessments leading to a Pre-feasibility Study.

2018 Plans:

• Recently announced diamond drill program on the Ak ie property including drill targets on other

known mineralised occurrences, including the Sitka showing and the North Lead Zone

• A satellite structural analysis will be completed on the northern portion of the Kechika Regional

properties providing the Company with seamless deta iled structural analysis over its entire Akie

and Kechika Regional claims holdings; representing 140 kilometres of highly prospective and

thrust-repeated Gunsteel Formation, the known host rock for SEDEX mineral occurrences and

deposits in the Kechika Trough. Complete coverage w ill aid in target definition for future drill

programs

• Continue examining cost effective means to conduct the planned and permitted 2-year

underground drill program which has been designed to carry out infill drilling on the Cardiac Creek

deposit from close-spaced drill centres from an underground platform, enabling year-round drilling

and advancement of the project towards a PFS level

• Continue baseline environmental studies to facilit ate further permitting and advancement of the

project

Qualified Persons

The PEA was led by JDS, an independent consulting f irm, and will be incorporated into a National

Instrument 43-101 (“NI 43-101”) technical report to be filed on SEDAR and the Company’s website within

45 days of this release.

Various personnel at JDS or their sub-consultants a re Qualified Persons and responsible for portions o f

this news release; and are identified as follows: M ichael Makarenko (P.Eng.) mining; Richard Goodwin

(P.Eng.) mining; Richard Boehnke (P.Eng.) infrastru cture/transportation; Kelly McLeod (P.Eng.) mill

processing; and Jim Fogarty (P.Eng. - Knight Piésol d) tailings disposal. A full list of Qualified Pers ons

contributing to the PEA will be summarized in the NI 43-101 technical report.

The Akie Zn-Pb-Ag Project

The 100% owned Akie property is situated within the Kechika Trough, the southernmost area of the

regionally extensive Paleozoic Selwyn Basin and one of the most prolific sedimentary basins in the wor ld

for the occurrence of SEDEX zinc-lead-silver and stratiform barite deposits.

Drilling on the Akie property by ZincX Resources (f ormerly Canada Zinc Metals Corp) since 2005 has

identified a significant body of baritic-zinc-lead SEDEX mineralization known as the Cardiac Creek deposit.

The deposit is hosted by siliceous, carbonaceous, fine grained clastic rocks of the Middle to Late Devonian

Gunsteel Formation.

With additional drilling completed in 2017, the Com pany has updated the estimate of mineral

resources at Cardiac Creek, as follows:

5% Zinc Cut-Off Grade Contained Metal:

Category Tonnes

(million) Zn (%) Pb (%) Ag (g/t) Zn (Blbs) Pb (Blbs) Ag (Moz)

Indicated 22.7 8.32 1.61 14.1 4.162 0.804 10.3

Inferred 7.5 7.04 1.24 12.0 1.169 0.205 2.9

In addition to the Akie Project, the Company owns 100% of eight of eleven large, contiguous property blocks

that comprise the Kechika Regional Project includin g the advanced Mt. Alcock prospect. The Kechika

Regional Project also includes the Pie, Yuen and Ci rque East properties within which the Company

maintains a significant 49% interest with partners Teck Resources Limited (TSX: TECK.B) and Korea Zinc

Co. Ltd. These properties collectively extend north west from the Akie property for approximately 140

kilometres covering the highly prospective Gunsteel Formation shale; the main host rock for known SEDEX

zinc-lead-silver deposits in the Kechika Trough of northeastern British Columbia. These projects are located

approximately 260 kilometres north northwest of the town of Mackenzie, British Columbia, Canada.

Ken MacDonald P.Geo., Vice President of Exploration for the Company, is the designated Qualified Person

as defined by National Instrument 43-101 and is res ponsible for the technical information contained in this

release.

The TSX Venture Exchange has neither approved nor disapproved the contents of this press release.

ON BEHALF OF THE BOARD OF DIRECTORS

ZINCX RESOURCES CORP.

“PEEYUSH VARSHNEY”

PEEYUSH VARSHNEY, LL.B

CEO & CHAIRMAN