Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

YRB.TO ·

Yorbeau reports positive Preliminary Economic Assessment of Scott Zinc-Copper Deposit in Québec.

Economic Studies

YORBEAU RESOURCES INC.

110 Place Crémazie, Suite 430, Montréal, QC, H2P 1B9

www.yorbeauresources.com

PRESS RELEASE

FOR IMMEDIATE RELEASE

Yorbeau reports positive Preliminary Economic Assessment of Scott Zinc-Copper

Deposit in Québec.

 Project indicates pre-tax IRR of 16.5% with an NPV8 of $144 million.

Montréal, November 20, 2017 - Yorbeau Resources Inc. (TSX: YRB) (the “Company” or

“Yorbeau”) is pleased to announce results of a Preliminary Economic Assessment (“PEA”)

prepared by Normand Lécuyer, P.Eng. and Jeff Sepp P.Eng. of Roscoe Postle Associates Inc.

(“RPA”).

Under the base case PEA the Scott mineralized material is fed to a new 2,500 tonne-per-day

concentrator plant located at the mine site. Results indicate positive economics with a pre-

production capital expenditure of $215 million, a net pre-tax cash flow of $516 million, an

Internal Rate of Return (“IRR”) of 16.5%, a pre-tax Net Present Value (“NPV”) of $144 million

at an 8% discount rate, and a mine life of 15 years. Tables 1, 2 and 3 show summaries of LOM

estimated project capital costs and operating costs for the base case scenario.

Table 1: Scott Project Preliminary Economic Assessment Highlights:

(based on US$1.30/lb Zn, US$3.50/lb Cu, US$23/oz Ag, US$1500/oz Au and Canadian dollar

exchange rate of US$0.80) - all values in Canadian $’s unless noted otherwise)

Base Case: All Ramp Scenario with New Concentrator at Mine Site

Net Cash Flow  Pre-tax Net Cash Flow of $515.8 million

IRR  Pre-tax IRR of 16.5% with a 6-year payback

NPV  Pre-tax NPV(8%) of $144.0 million

Operating Costs  Life of mine (“LOM”) Opex Costs of $89.02/tonne mined (includes

mining, milling, G&A and Environmental)

Capex  Pre-production capital of $215.47 million,

 Sustaining capital cost of $113.2 million

Production Average peak annual payable production

YORBEAU RESOURCES INC.

110 Place Crémazie, Suite 430, Montréal, QC, H2P 1B9

www.yorbeauresources.com

(Payable)  Zinc (years 9 – 12) : 75 million lbs. Zn in 72,405 t of concentrate

 Copper (years 5 – 8) : 15 million lbs. Cu in 28,467 t of concentrate

 Silver (years 5 – 8) : 395,835 oz in Cu concentrate

Mine Life  Planned mine life of 15 years

LOM Mill Feed  Estimated Plant Feed of 12,024,000 tonnes grading 4.14% Zn, 0.81%

Cu, 26.59 g/t Ag and 0.24 g/t Au over LOM

Mill Recoveries

 Average LOM recoveries : Zn: 87% , Cu : 85%

 Ag : 45% reporting to the Cu concentrate,

 Au : 63% reporting to the Cu concentrate

MINING AND DEVELOPMENT

The preproduction mine development is carried out by a mining contractor and turned over to the

mine crews in year one. Contractor rates were used for the preproduction period while manpower

estimates were made for the owner operators commencing in year one of the mine production.

Although a shaft scenario was considered, an all ramp system was selected as the most

appropriate and the mineralized zones are therefore accessed via a ramp system. The Scott

Project will take approximately two to three years of initial development to prepare the mine for

production. Mining during the LOM will include 50% mineralized material from Longitudinal

LH stopes, 26% from Transverse LH stopes, 11% from Cut and Fi ll stopes, and 13% from

development. The Stringer type mineralization will be mined using the Longitudinal stoping

method and thus represents a large portion of the production profile.

RPA has used a sublevel interval of 20 m, as no geotechnical work has been completed to

sufficiently assess the ground support requirements. There is an opportunity to potentially

increase the sublevel interval however only for the Transverse stopes while maintaining good

control of the mineralization limits and mining dilut ion. Once more geotechnical work is

completed, level spacings may be increased, reducing capital and operating costs. The ramp

option achieves production more quickly than a shaft option, however, peak production is not

achieved for 4 years, and limited t o 2,350 tpd, due to the development required to establish

sufficient working levels.

PROCESSING

A concentrator would have to be built on site and the mill production mirrors the mine

production. The mill feed would produce copper and zinc concentrates a ssumed to be

commercially viable. Mill recoveries for the concentrates based on early metallurgical test work

are shown in Table 1. The test work is considered incomplete and values for gold recoveries in

the concentrate need to be verified. In RPA’s opi nion, additional testing of the massive sulphide

YORBEAU RESOURCES INC.

110 Place Crémazie, Suite 430, Montréal, QC, H2P 1B9

www.yorbeauresources.com

material and the stringer material independent of each other are required to adequately

understand the metallurgical response and obtainable marketable concentrate products.

The recoveries used in this initial analysis and shown in Table 1 are based on the assumption of

further optimization relative to metallurgical testing completed to date. The testing has indicated

a high consumption of lime, required to adjust the pH valu es in the circuit. The limited testing

will necessitate additional work to properly assess the processing cost from the point of view of

reagent consumption.

Table 2: Scott Project Preliminary Economic Assessment – Operating Costs:

Cost ($/t milled)

Mining 54.14

Processing 27.49

General & Administration 7.40

TOTAL 89.02

Numbers may not add due to rounding.

Table 3: Scott Project Preliminary Economic Assessment – Pre-production Capital Costs:

$(millions)

Mining 52.58

Processing 60.00

Infrastructure 15.78

Tailings 4.65

Sub Total 133.01

EPCM* 46.55

Contingency 35.92

TOTAL 215.47

*EPCM : Engineering Procurement Construction Management

Numbers may not add due to rounding.

YORBEAU RESOURCES INC.

110 Place Crémazie, Suite 430, Montréal, QC, H2P 1B9

www.yorbeauresources.com

RECOMMENDATIONS

Among several recommendations made by RPA, the following are of note :

 The Study is based in part on Inferred Mineral Resources that are considered too

speculative geologically to have economic considerations applied to them. Therefore,

additional in-fill diamond drilling to bring Inferred Resources to the Indicated category is

required before further economic studies are considered. Given the level of accuracy

needed for the drilling, an underground exploration program may have to be considered.

 A preliminary evaluation of an all-ramp versus ramp and shaft modes of access showed

that the shaft scenario would increase the daily mining rate while lowering the operating

and sustaining capital costs, however, at the expense of higher pre-production capital

expenses. Additional tonnage discovered at depth may give additional support to the shaft

scenario and it is recommended to continue exploring the mineralized system at depth

and in particular west of the Gwillim Lake fault.

 An underground exploration program, involving a ramp and drill accesses, would provide

a head start on mine development, with a positive impact on project economics.

 The mine design and schedule were based on preliminary knowledge of ground

conditions and rock mechanics. To support the next stage of mine design it is

recommended to perform prefeasibility -level geotechnical studies, as part of the

underground exploration program.

 Estimated mill recoveries for the concentrates are based on early metallurgical test

work. The test work is still incomplete and additional testing of the massive sulphide

mineralization and the stringer mineralization independent of each other are required to

adequately understand the metallurgical response during processing of both types of

mineralized material for the life of th e mine and to obtain marketable concentrate

products.

 Discussion with the Province of Québec and the Canadian Environmental Assessment

Agency should be initiated to confirm Environmental Assessment (EA), permit and

approvals requirements. Environmental baseline data collection and engagement with

Indigenous communities should also be initiated.

“We are very excited about the results of the PEA study on Scott, which provides a strong, initial

foundation for eventual development of a new mine in the Chibougamau camp.” stated Dr.

Gérald Riverin, Yorbeau’s President. “The ideal location of the project in an area already blessed

with all necessary infrastructure has led to maintaining infrastructure capital costs to a relatively

low level when compared to similar zinc projects. The horizontal widths and favorable geometry

of the mineralized zones support the use of low cost long hole mining methods which had a big

positive impact on the results of the study. Yorbeau is now in a position to evaluate a number of

options to develop the Scott deposit.”

The project has been valued using a discounted cash flow (DCF) approach. This method of

valuation requires projecting yearly cash inflows, or revenues, and subtracting yearly cash

outflows such as operating costs and capital costs. At this early stage of the study, royalties and

provincial or federal taxes have not been included. Cash flows are taken to occur at the middle of

YORBEAU RESOURCES INC.

110 Place Crémazie, Suite 430, Montréal, QC, H2P 1B9

www.yorbeauresources.com

each period. The resulting net annual cash flows are discounted back to the first year of

valuation, and totaled to determine net present values (NPVs) at the selected 8 percent discount

rates. The internal rate of return (IRR) is calculated as the discount rate that yields a zero NPV.

The payback period is calculated as the time needed to recover the initial capital spent.

For readers to fully understand the information in this news release, they should read the

Technical Report supporting the PEA in its entirety, including all qualifications, assumptions and

exclusions that relate to the PEA, which will be filed on SEDAR at www.sedar.com and on the

Yorbeau Resources website at www.yorbeauresources.com within 45 days of the date of this

news release. The Technical Report is intended to be read as a whole, and sections should not be

read or relied upon out of context.

The PEA is considered preliminary in nature and includes economic analysis that is based, in

part, on Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative

geologically to have the economic considerations applied to them that would allow them to be

categorized as Mineral Reserves, and there is no certainty that the results will be realized.

Mineral Resources are not Mineral Reserves because they do not have demonstrated economic

viability.

Qualified Persons

Work at Yorbeau is carried out under the supervision of Gérald Riverin, PhD, P. Geo. He is a

qualified person (as defined by NI 43-101) and has reviewed and approved the content of this

release. The Technical Report and PEA referred to in this press were prepared by Normand

Lécuyer and Jeff Sepp. Both are employees of RPA and are independent of Yorbeau. By virtue

of their education and relevant experience, they are “Qualified Persons” for the purpose of

National Instrument 43-101. Normand Lécuyer and Jeff Sepp have read and approved the

contents of this press release as it pertains to the disclosed mining, milling and cost estimate

aspects.

About Yorbeau Resources Inc.

The Company’s 100% controlled Rouyn Property contains four known gold deposits in the

6-km-long Augmitto -Astoria corridor situated on the western half of the property. Two of the

four deposits, Astoria and Augmitto, have substantial underground infrastructure and have been

the subject of NI 43 -101 technical reports that include resource estimates. The Company has

signed an Option Agreement with an affiliate of Kinross Gold Corporation to pursue exploration

on the Rouyn Property (see press release dated October 25, 2016). In 2015, the Company

expanded its exploration property portfolio by acquiring strategic base metal properties in

prospective areas of the Abit ibi Belt of Quebec and Ontario that also feature infrastructure

favourable for mining development. The newly acquired base metal properties include Scott

Lake which hosts important mineral resources.

More information on the Company may be found on the Co mpany’s website at

www.yorbeauresources.com.

YORBEAU RESOURCES INC.

110 Place Crémazie, Suite 430, Montréal, QC, H2P 1B9

www.yorbeauresources.com

For further information, please contact:

Gérald Riverin, Ph D., P. Geo

President

Yorbeau Resources Inc.

[email protected]

Tel : 819-279-1336

G. Bodnar Jr.

Vice President

Yorbeau Resources Inc.

[email protected]

Tel.: 514-384-2202

Toll free in North America: 1 -855-384-

2202

Forward-looking statements: Except for statement of historical fact, all statements in this news

release, without limitation, regarding new projects, acquisitions, future plans and objectives are

forward-looking statements which involve risks and uncertainties. There can be no assurance

that such statements will prove to be accurate; actual results and future events could differ

materially from those anticipated in such statements. The results of the economic analysis

represent forward-looking information, as defined under Canadian securities laws, that is

subject to a number of known and unknown risks, uncertainties and other factors that may cause

actual results to differ materially from those presented in the PEA. RPA is of the opinion that the

accuracy of the results is in the range of industry wide commonly accepted scoping studies.