Drill Results

YORBEAU RESOURCES INC.

110 Place Crémazie, Suite 430, Montréal, QC, H2P 1B9

www.yorbeauresources.com

PRESS RELEASE

FOR IMMEDIATE RELEASE

YORBEAU COMPLETED LAST DRILL HOLE AT SCOTT - GAP LENS STILL OPEN TO THE

EAST

 15.3 metres of 7.2% zinc, 0.8% copper and 34.6 g/t silver

Montréal, February 7, 2017 - Yorbeau Resources Inc. (TSX: YRB.A) (the “Company” or “Yorbeau”) is

pleased to report on recent diamond drilling results at its 100% owned Scott Lake project in Quebec.

Drill hole SC -88W intersected a 15.3 metre long interval of combined stringer (mostly) and massive

sulphides in the last hole of the drilling program to explore the Gap Lens. This hole was a 90 metre step

out to the east of hole SC-87W3 which had intersected over 20.6 metres of 5.9% zinc, 0.7% copper and

50.9 g/t silver (press release of November 23, 2016), and a 75 metre step out to the east of hole SC-87W2

which had intersected 46.3 metres of massive sulphides grading 9.7 % zinc (press release of October 20,

2016). The mineralized interval in SC-88W, as were all previous intercepts released by the Company on

the Gap Lens, are located outside of the mineral resources as currently estimated at the Scott project (see

attached Figure 1).

Assay results are shown below:

DDH SC-88W Section 1750W (weighted averages)

From

(m)

To

(m)

Length

(m)

Cu

%

Zn

%

Au

g/t

Ag

g/t Remarks

929.0 944.3 15.3 0.8 7.2 0.2 34.6

Stringer and

massive sulphides

(Gap Lens)

Hole SC -88W was a wedge -cut above original hole SC -88 which did not intersect mineralization and

ended in barren intrusive rocks of the Chibougamau Pluton at the expected position of the G ap Lens

horizon. However, hole SC-88 did intersect mineralization related to West Lens about 80 metres north of

the Gap Lens horizon.

Assay results are shown below:

DDH SC-88 Section 1750W (weighted averages)

From

(m)

To

(m)

Length

(m)

Cu

%

Zn

%

Au

g/t

Ag

g/t

Remarks

YORBEAU RESOURCES INC.

110 Place Crémazie, Suite 430, Montréal, QC, H2P 1B9

www.yorbeauresources.com

863.8 874.5 10.7 0.4 3.2 0.5 34.1

stringer and

massive sulphides

(West Lens) with

minor mafic dykes

including

863.8 868.2 4.4 0.1 6.1 1.0 18.3

massive sulphides

(West Lens) with

minor mafic dykes

As this is still preliminary drilling on the above mineralization, the exact shape and true width cannot be

determined with certainty and t he core lengths displayed in the above table s do not represent the true

thickness of the mineralization. However, at the depth of the mineralized zone in SC-88W, the dip of the

hole was at 29 degrees and the horizontal thickness of the Gap Lens mineralization therefore represents

13.4 metres. Hole SC-88W was a wedge-cut about 52 metres above hole SC-88 (see attached Figure 1).

Company president Gérald Riverin stated: “ We are pleased to have completed our 18 month drilling

program on the Gap Lens which represents an exciting new discovery, and happy to see that the very last

hole of the program still intersected over 15 metres of mineralization , showing that Gap Lens still

continues further east. The published assays were the last remaining ones to be received on the Gap Lens ,

and we expect now the on -going revised resource estimate to be released very shortly by Roscoe Postle

Associates.”

The Scott Lake property, 100% owned by Yorbeau , already hosts a number of polymetallic massive

sulphide lenses. A resource estimate on Scott Lake was commissioned by Cogitore Resources and

prepared by RPA in 2011. The RPA estimate showed combined inferred resources of 5.45 million tonnes

grading 1.2% copper, 4.6% zinc, 0.2 g/t gold and 34 g/t silver, using an NSR cut -off of $80 per tonne

(Technical Report prepared by Roscoe Postle Associates and filed by Cogitore Resources in 2011). A

revised estimate was commissioned by Yorbeau in 2016, and will be c ompleted and filed shortly with a

Technical Report.

All drill core discussed in this press release was logged and marked up for assay at the Company’s secure

facility in Chibougamau, Quebec. Drill core for assay was split in half. Half of the core was shipped in

sample bags with appropriate standards, duplicates and replicates used for quality control purposes. The

other half of the core is retained for future reference. Samples were shipped to Laboratoire ALS Chemex

of Val d’Or.

Work is carried out by the personnel of Yorbeau, under the supervision of Gérald Riverin, PhD, P. Geo.

He is a qualified person (as defined by NI 43-101) and has reviewed and approved the content of this

release.

About Yorbeau Resources Inc.

The Company’s 100% controlled Rouyn Property contains four known gold deposits in the 6 -km-long

Augmitto-Astoria corridor situated on the western half of the property. Two of the four deposits, Astoria

and Augmitto, have substantial underground infrastructure and have been the subject of NI 43 -101

technical reports that include resource estimates. The Company recently announced signing a n Option

YORBEAU RESOURCES INC.

110 Place Crémazie, Suite 430, Montréal, QC, H2P 1B9

www.yorbeauresources.com

Agreement with an affiliate of Kinross Gold Corporation to pursue exploration on the Rouyn Property

(see press release dated October 25, 2016) . In 2015, the Company expanded its exploration property

portfolio by acquiring strategic base metal properties in prospective areas of the Abitibi Belt of Quebec

and Ontario that also feature infrastructure favourable for mining development. The newly acq uired base

metal properties include Scott Lake which hosts important mineral resources. The Company also owns

the Beschefer project immediately adjacent to SOQUEM’s B -26 deposit and where, regionally,

exploration interest has been increasing.

More informa tion on the Company may be found on the Company’s website at

www.yorbeauresources.com.

For further information, please contact:

Gérald Riverin, Ph D., P. Geo

President

Yorbeau Resources Inc.

[email protected]

Tel : 819-279-1336

G. Bodnar Jr.

Vice President

Yorbeau Resources Inc.

[email protected]

Tel.: 514-384-2202

Toll free in North America: 1-855-384-2202

Forward-looking statements: Except for statement of historical fact, all statements in this news release,

without limitation, regarding new projects, acquisitions, future plans and objectives are forward -looking

statements which involve risks and uncertain ties. There can be no assurance that such statements will

prove to be accurate; actual results and future events could differ materially from those anticipated in

such statements.