XXIX's Opemiska PEA Confirms Positive Development Potential
XXIX's Opemiska PEA Confirms Positive
Development Potential
Highlights:
Total payable copper across Opemiska 17 year mine life
:
715 million pounds of copper
409 thousand ounces of gold
2.08 million ounces of silver
Robust after-tax base case economics:
C$505M after-tax NPV8% (C$897 after-tax NPV8% using spot pricing)
27.2% after-tax IRR (39.3% after-tax IRR using spot pricing)
Rapid payback:
2.3-year Base Case payback of C$617M initial capital resulting from upfront
high-grading.
Potential High-grade annual recovered payable production across the first six years:
59 million pounds of copper per year
34 thousand ounces of gold per year
174 thousand ounces of silver per year
Low Cost Producer:
Opemiska is in the lower quartile of the cost curve with US$1.03/lb C1 cash
cost net of by-product credits across the first six years. US$1.40/lb net of by-product credits over
the life of mine.
Significant leverage to rising copper and gold prices, with
$4.40
billion in life of mine
revenue
70.7% copper
27.9% gold
1.4% silver
Plenty of Resource upside including Cooke gold zone with active drilling underway.
Toronto, Ontario--(Newsfile Corp. - October 21, 2025) - XXIX Metal Corp. (TSXV: XXIX)
(OTCQB: QCCUF) (FSE: 5LW0) ("
XXIX
" or the "Company") is pleased to announce the completion of a
Preliminary Economic Analysis ("
PEA
")
[1]
on its Opemiska copper project (
"Opemiska"
), located in
Chapais, Québec. The PEA evaluates the potential economic viability of Opemiska's mineral resources
and is the first economic study on Opemiska since Falconbridge closed its underground mining
operations in 1991.
"This is a significant milestone for Opemiska and XXIX. The results clearly indicate Opemiska's potential
as a profitable operation Furthermore, the high-grade early years of the mine has resulted in a low C1
cash cost of US$1.03/lb (net of by-product credits) over the first six years, and US$1.40/lb (net of by-
product credits) over the 17-year life of mine, placing the project in the lower quartile of the cost curve,"
said Guy Le Bel, CEO of XXIX.
"This project has the potential to bring in significant benefits to all
stakeholders involved, including the town of Chapais and surrounding communities."
Project Overview
The 100%-owned Opemiska spans 21,333 hectares in Quebec's Chapais-Chibougamau region, with
significant infrastructure in place. Opemiska comprises four past-producing mines, two of which
(Springer and Perry) underpin the current PEA. Cooke, a third past-producing mine located ~3km east
of the proposed pit is currently being evaluated for its gold resource potential.
Figure 1)
Location of the Opemiska Project
The PEA envisions an open pit mining and milling operation with a processing capacity of 12,500
tonnes per day, over a 17-year life of mine ("LOM"). The project has been optimized by sequencing the
open pit mining extraction schedule in four distinct phases and by segregating mineralized material to
process higher value material upfront. The optimized processing schedule demonstrates an average
annual production of 62 million lbs of copper, 38 thousand ounces of gold and 193 thousand ounces of
silver over the first six years of production and 44 million lbs of copper, 27 thousand ounces of gold and
130 thousand ounces of silver over the entire LOM.
Table 1 presents a summary of operating and financial highlights from the PEA, using Base Case and
Spot Pricing assumptions. A foreign exchange of C$1.35 to US$1.00 has been used for this economic
analysis.
Table 1) Operating and Financial Summary (Base Case unless specified otherwise)
Parameter
Units
Values
General
Base Case
Spot Pricing
Copper price
US$/lb
4.35
4.75
Gold price
US$/oz
3,000
4,300
Silver price
US$/oz
30.00
54.00
Exchange rate
CAD:USD
1.35
1.38
Mine life
years
17
Total mill feed
million tonnes
77.2
Strip ratio
Waste to mineralized
material
3.7
Economics (Pre-tax)
Base Case
Spot Pricing
Net present value (NPV8%)
C$ millions
793.0
1,442.1
Internal rate of return (IRR)
%
32.1%
48.5%
Payback
years
2.3
1.7
LOM Annual Cash Flow
C$ millions
102.3
170.1
LOM Cumulative Cash Flow
C$ millions
1,748
2,905.3
Economics (After-tax)
Base Case
Spot Pricing
Net present value (NPV8%)
C$ millions
505.2
897.2
Internal rate of return (IRR)
%
27.2%
39.3%
Payback
years
2.3
1.8
LOM Annual Cash Flow
C$ millions
67.7
108.5
LOM Cumulative Cash Flow
C$ millions
1,156.8
1,853.0
LOM Revenue
US$ millions
4,398
5,264
% Copper
%
70.7%
64.5%
% Gold
%
27.9%
33.4%
% Silver
%
1.4%
2.1%
Production
Throughput
tpd
12,500
Year 1 - 6
LOM
Copper equivalent grade
%
1.01%
0.70%
Copper grade
%
0.69%
0.48%
Gold grade
g/t
0.33
0.23
Silver grade
g/t
1.67
1.12
Copper equivalent production
Mlb
545
1,098
Copper production
Mlb
375
753
Gold production
koz
229
464
Silver production
koz
1,160
2,231
Copper Recovery
%
92.0%
Gold Recovery
%
79.9%
Silver Recovery
%
80.3%
Operating Costs
Year 1 - 6
LOM
Mining
C$/t mined
4.02
4.39
Mining
C$/t milled
29.07
20.66
Processing
C$/t milled
10.62
10.62
Waste and water management
C$/t milled
0.11
0.08
G&A
C$/t milled
3.16
3.16
Total (before selling costs and royalty)
C$/t milled
42.97
34.52
Selling costs
C$/t milled
7.87
5.45
Royalty
C$/t milled
1.03
0.71
Total (after selling costs and royalty)
C$/t milled
51.86
40.69
Year 1 - 6
LOM
C1 Cash Cost
US$/lb Cu (net of by-
products)
1.03
1.40
C3 Cash Cost
US$/lb Cu (net of by-
products)
1.96
2.50
Capital Costs
Initial capital
C$ millions
617.3
Initial Capex net of CTM-ITC (Net Initial Capex)
[2]
C$ millions
467.7
Sustaining capital
C$ millions
390.9
Closure costs
C$ millions
40.0
Sensitivities
A sensitivity analysis was completed to reflect Opemiska's economics under multiple copper and gold
pricing scenarios.
Table 2)
Sensitivity to Copper and Gold Pricing
Copper Price Sensitivity
-15%
-10%
-5%
$4.35/lb
5%
10%
15%
NPV8%
287.9
361.1
433.2
505.2
576.9
648.1
718.8
IRR
19.7%
22.3%
24.8%
27.2%
29.6%
31.8%
34.0%
Payback
2.7
2.5
2.4
2.3
2.2
2.1
1.9
NPV to Net Initial CAPEX
3
0.6
0.8
0.9
1.1
1.2
1.4
1.5
Profitability Index
1.6
1.8
1.9
2.1
2.2
2.4
2.5
Gold Price Sensitivity
-45%
-30%
-15%
$3,000/oz
15%
30%
45%
NPV8%
252.4
337.2
421.4
505.2
588.8
671.9
754.5
IRR
18.4%
21.5%
24.4%
27.2%
29.9%
32.5%
35.1%
Payback
2.8
2.6
2.4
2.3
2.2
2.0
1.9
NPV to Net Initial CAPEX
3
0.5
0.7
0.9
1.1
1.3
1.4
1.6
Profitability Index
1.5
1.7
1.9
2.1
2.3
2.4
2.6
Mineral Resources
Opemiska's production profile is contemplated as a 55% subset of the pit constrained indicated and
inferred mineral resource estimate ("
MRE
") previously announced on
June 3, 2025
. As such, the PEA is
preliminary in nature and includes inferred mineral resources that are considered too speculative
geologically to have the economic considerations applied to them that would enable them to be
categorized as mineral reserves, and there is no certainty that the PEA will be realized. Figure 2
compares the MRE resource constraining pit to the open pit envisioned in the PEA.
Figure 2)
MRE Constraining Pit Shell vs. PEA Pit Shell
Mining - A Phased Approach
The PEA contemplates a conventional open pit truck-and-shovel operation with a 12,500 tpd (4.6 Mtpa)
processing rate over 17-year LOM, with an average strip ratio of 3.7 to 1. The mine plan has been
optimized across four phases for a rapid payback on initial capital supported by strong annual cash flow.
The four mining phases are detailed as follows: starter pits in both Springer and Perry (Phase 1), an
intermediate pushback in Springer (Phase 2), the depletion of Perry (Phase 3), and the depletion of
Springer (Phase 4). The 17-year LOM incorporates 13 years of direct mill feed from open pit operations
and 4 years of stockpile rehandling. The open pit operation has also been optimized to delay any impact
to the neighbouring town of Chapais to the end of Phase 3 and beginning of Phase 4. Figure 3 outlines
the 13-year mine production schedule.
Figure 4 - 7 shows the pit outline for each the four phases.
Figure 3) Mineralized Material Mined (By Phase)
Figure 4)
Phase 1 - Springer and Perry Starter Pits
Figure 5)
Phase 2 - Springer Pushback
Figure 6)
Phase 3 - Perry Depletion
Figure 7)
Phase 4 - Springer Depletion
Processing & Metallurgy
The PEA envisions a typical flotation metallurgical flowsheet for the recovery of a copper concentrate
with gold and silver, that is amenable to smelting. The flowsheet (Figure 8) incorporates 2 stage
crushing, SAG/ball mill grinding, rougher flotation, concentrate regrind and cleaner flotation followed by
concentrate thickening and filtration, resulting in a final concentrate with a copper grade of 20%. The
tailings are thickened, filtered and trucked to the co-disposal facility where encapsulation with waste rock
will be promoted.
The process plant will treat 4.6 Mt/y of mineralized material, at an average throughput of 12,500 t/d. The
grinding and flotation design availability is 8,059 hours per year or 92%. The crushing design availability
is 5,694 hours per year or 65%. The tailings and concentrate filtration design availability is 7,183 hours
per year or 84%. Average life-of-mine recoveries, based on testwork, and supported by historical
operations data
[3]
, are estimated to be 92% for copper, 80% for gold and silver. Figure 9 outlines mill
production schedule across the 17-year LOM.
Figure 8) Process Flow Sheet
Metallurgical testing was completed on a composite sample at SGS (Quebec City) in 2023. The
composite was made up of core, sourced from intervals weighted proportionally to the deposit
mineralized domains and intersecting all lithologies. The purpose of this testwork was to evaluate the
metallurgical performance and environmental properties of mineralized material from the Opemiska
deposit through conventional flotation processes and provide material inputs to inform the PEA design.
The testwork results indicated copper recoveries to concentrate of approximately 92%.
Figure 9) Production Schedule
Capital & Operating Costs
Initial capital is estimated at C$617M over a 2-year construction period, and is based on the costs
outlined in Table 3, below:
Table 3) Breakdown of Initial Capital
Initial Capital Expenditure
Cost
(C$M)
Infrastructure
16.2
Electricity and Communications
27.0
Tailings Management
14.5
Water Management
6.9
Mining Equipment
45.6
Process Plant
271.0
Indirects
106.2
Contingency
121.4
Capitalized Operating Costs
8.4
Initial Capital
617.3
Clean Technology Manufacturing Investment Tax Credit (CTM-ITC)
(149.6)
Initial Capital (net of Clean Technology Manufacturing Investment Tax Credit)
467.7
The Company may be eligible to receive the Clean Technology Manufacturing Investment Tax Credit
(CTM-ITC).
This legislation has been enacted on June 20, 2024. XXIX expects to receive ~$149.6M in
CTM-ITC as 100% of revenue for Opemiska is generated from sale of copper concentrate, copper being
one of six qualifying materials. There is no guarantee the Company will be able to access the CTM-ITC. If
the CTM-ITC does not become available, the total capital cost including contingency will increase by the
amounts shown in this row.
Sustaining capital over the LOM is estimated at $390.9M, while closure costs are estimated at $40.0M.
Operating costs are estimated at C$34.52/tonne processed, based on the costs outlined in Table 4,
below. Costs pertaining to transportation, placement and compaction of the tailings have been included
as part of the mining cost.
Table 4) LOM Unit Operating Costs
Unit Cost
Unit
Cost
Mining
C$/t mined
4.39
Mining
C$/t processed
20.66
Processing
C$/t processed
10.62
Waste and water management
C$/t processed
0.08
G&A
C$/t processed
3.16
Total
C$/t processed
34.52
C1 Cash costs over the LOM are estimated at US$1.40/lb Cu (net of by-product credits), with C1 cash
cost during Years 1 - 6 being US$1.03/lb Cu. A breakdown of C1 cash cost is outlined in Table 5, below:
Table 5) C1 Cash Cost Breakdown (Base Case)
C1 Cash Cost (US$/lb)
Year 1 - 6
LOM
Mining
1.61
1.65
Processing
0.59
0.85
Waste and Water Management
0.01
0.01
G&A
0.18
0.25
Transportation and Logistics
0.30
0.30
TCs / RCs
0.14
0.14
Gold by-product credit
-1.70
-1.72
Silver by-product credit
-0.09
-0.08
Total C1 Cash Cost
1.03
1.40
Economic Analysis Results
The PEA highlights Base Case NPV8% of C$505M with a corresponding IRR of 27.2% and a 2.3-year
payback period. Under Spot Pricing, NPV8% increases to C$897M, with a corresponding IRR of 39.3%
and a 1.8-year payback.
Assumptions, including commodity pricing and exchange rate used as part of
the economic analysis is outlined in Table 6, below:
Table 6) Commodity Price & Exchange Rate Assumptions
Assumption
Base Case
Spot Pricing
Copper price (US$/lb)
4.35
4.75
Gold price (US$/oz)
3,000
4,300
Silver price (US$/oz)
30
54
CAD : USD
1.35
1.38
Opemiska On-site Infrastructure
Opemiska's site layout comprises the processing plant, power infrastructure, tailings management
facility and administrative buildings. Figure 10 outlines Opemiska's envisioned site layout.
Figure 10) Opemiska Site Layout
Tailings Management
XXIX will utilize filtered tailings management, providing multiple advantages over conventional tailings
management strategies.
Filtered tailings management does not utilize tailings ponds, mitigating
stakeholder risk exposure to catastrophic failure and flooding and/or uncontrolled leaks or seepage.
Filtered tailings management sees tailings treated through filters prior to being deposited in layers,
stacked and compacted on specially designed platform lined with a geomembrane.
As part of the
filtration process, water is removed from the mixture resulting in drier material-similar to soil such as a
fine
sand. Using such technology and tailings management strategy assists in streamlining progressive
reclamation activities.
Opportunities
Evaluate ore sorting as a mechanism to further improve processing head grades of lower grade
stockpiled material.
Mineral sorting can also lead to optimized costs by rejecting waste material earlier
in the process, potentially increasing overall economics.
Evaluate potential mineralized material at the bottom of the envisioned pit as well as mineralized
material outside of the envisioned pit to further boost project economics.
Future testwork programs will investigate the potential to further improve concentrate grades, which
would reduce concentrate mass to be transported and improve payability. Mineralogical analysis also
revealed the potential to recover coarse gold via gravity concentration; future testwork will be conducted
to confirm.
Testwork to be performed on filtered tailings will investigate their compaction potential which could allow
reducing the overall height and footprint of the co-disposal facility.
Next Steps and Upcoming Catalysts
Exploration of Cooke Gold Zone - Q4 2025 / Q1 2026
A 6,000-metre drill program has commenced at Cooke to determine potential for a near surface
resource that could complement Opemiska's existing resource base. Cooke was a past producing
underground mine with two parallel gold structures that have not been mined to surface. Historically,
Cooke produced 1.97 million tonnes grading 5.04 g/t gold and 0.66% Copper
[4]
. Cooke has up to 200
metres of crown pillar intact, increasing potential for high-grade near surface gold mineralization.
Prefeasibility Study - 2026 - onwards
XXIX will continue to progress Opemiska towards a Pre-Feasibility Study ("PFS").
As such, the
company will have to complete additional studies including:
Environmental Baseline Studies:
XXIX will commence environmental baseline studies in 2026 to
assess potential impacts of Opemiska and potential future mining operations.
Environmental
baseline studies are critical paths of the mine permitting process, ensuring that companies are
complying with the applicable environmental regulation and current practice recommendations.
Metallurgical Studies: The company will pursue metallurgical testing to confirm/optimize the
flowsheet design, characterize the tailings for filtration and acid generation potential, characterize
waste for acid generation/neutralization potential and evaluate ore sorting for the low grade
material.
Geotechnical Studies:
The purpose of these studies is to confirm assumptions on slope angles in
the pit, and the stability of the co-disposition facility.
Stakeholder Engagement:
XXIX commits to constant transparent dialogue with the communities
where we operate. In 2026, we will organize a number of meetings to discuss how the proposed
project can be bonified to the benefits of the citizens.
3D Geological Model Upgrade: The Opemiska 3D geological model will be upgraded prior to
commencing the PFS.
Outstanding Risk Factors
The XXIX technical team has identified several key risks that could impact the development of the
Opemiska Project. These are being carefully evaluated and will be addressed in future engineering and
economic studies:
1
.
Proximity to the Town of Chapais: The conceptual pit in the current PEA partially overlaps with the
town boundary. This could raise social acceptance issues and may require trade-off studies or
additional capital for development solutions.
2
.
Historical Assay Validation: Drill core from mining operations between 1953 and 1991 no longer
exists, meaning historical mine assays cannot be directly verified. While limited twin-hole drilling
supports their general reliability, a geostatistical validation study was done during the process of
the 2025 MRE and the QP was able to validate historical assays using information coming from
valid and QAQC-proof recent holes. Additional detailed validation programs will be needed as the
project advances.
3
.
Geotechnical Considerations: Known geotechnical challenges include:
1
.
Rock:
a)
Open stopes in the eastern pit wall
b)
The Venture Sill, which dips toward the pit wall and may affect slope stability
c)
The Gwillim Fault, which may pose a water inflow risk if it hosts an aquifer
Despite these concerns, the host rock is generally strong and well-suited to open-pit
mining.
d)
The host rock competency is confirmed, in part, by the stability of the glory hole
sidewalls over the past 40 years.
2
.
Tailings and foundation soils:
a)
The feasibility of tailings filtration has not yet been demonstrated.
b)
The geotechnical properties, characteristics, and behavior of filtered tailings have not
yet been established.
c)
The geotechnical properties, characteristics, and behavior of the foundation soils have
not yet been established.
4
.
Geochemical, Hydrogeological and Water Treatment and Management Consideration
1
.
The mine waste environment has not yet been studied for environmental characteristics to
confirm its potential for acid generation and metal leaching.
2
.
The hydrogeological context is unknown and requires further study to assess the potential
impacts of mining activities.
3
.
The effects of mining activities on water quality (both groundwater and surface water) have
not yet been evaluated, and the need for water treatment should be assessed.
4
.
Comprehensive water balance yet to be completed
5
.
Historical Stope Modeling: Digitized historical stopes from the Springer and Perry mines may not
perfectly align with the current 3D models. Some mined-out areas may not fully match up with
mineralized zones, introducing potential grade uncertainty. The Company considers this
manageable for now but will re-digitize certain areas as development progresses.
6
.
The sale terms for the concentrate are indicative and based on historical terms. The LOM
concentrate offtake has not yet been negotiated.
About XXIX Metal Corp.
XXIX is advancing its Opemiska and Thierry Copper projects, two significant Canadian copper assets.
The Opemiska Project, one of Canada's highest-grade open pitable copper deposits, spans 21,333
hectares in Quebec's Chapais-Chibougamau region, with strong infrastructure and nearby access to the
Horne Smelter. An October 2025 Preliminary Economic Assessment outlined a 12,500 tpd open pit
operation over a 17-year mine life, generating an after-tax NPV8% of $505M, IRR of 27.2%, and a 2.3-
year payback period ($4.35/lb copper price, $3,000/oz gold price, $30/oz silver price).
The Thierry
Project hosts the K1 (near-surface) and the past-producing K2 (underground & surface) zones (see
XXIX news release dated October 1, 2024 for details regarding resources). Thierry has significant
infrastructure in place including an all-season road, an airport within 5km, a provincial power grid within
8km, and nearby rail. With these two high-potential projects, the Company has solidified its position as a
key player in the Canadian copper sector and has established itself as one of Eastern Canada's largest
copper developer.
QP Statement
The technical information contained in this news release has been reviewed and approved by Denis
McNichols, P.Geo and géo., Vice President Exploration for XXIX Metal, a Qualified Person, as defined
in "National Instrument 43-101, Standards of Disclosure for Mineral Projects.
The independent qualified persons for the PEA, as defined by National Instrument ("NI") 43-101, are
Renee Barrette, ing., Principal Metallurgist for Ausenco Engineering Canada ULC for metallurgy
and process plant design.
Jean-François St-Laurent, ing. PEng (ON), M.Sc, Principal Consultant for SRK Consulting
(Canada) inc. for the Tailings Management Facility.
Charles Veilleux, ing, Senior Consultant for SRK Consulting (Canada) inc. for the Hydrology, Site
Wide Water balancing and mine site surface water management facilities.
Maude Lévesque Michaud, ing., from Geodoz conseil for environmental and social considerations.
Stephen Coates, P. Eng. for Evomine Consulting for mining methods.
Alexandre Burelle, P. Eng. for Evomine Consulting for cost estimation and financial analysis.
Non-IFRS Financial Measures
XXIX has included certain non-IFRS financial measures in this news release, such as Initial Capital Cost,
Sustaining Capital, Closure Costs, C1 Cash Cost, C3 Cash Cost, NPV to Initial Capital, and Profitability
Index, which are not measures recognized under IFRS and do not have a standardized meaning
prescribed by IFRS. As a result, these measures may not be comparable to similar measures reported
by other corporations. Each of these measures used are intended to provide additional information to
the user and should not be considered in isolation or as a substitute for measures prepared in
accordance with IFRS.
For further information, please contact:
Guy Le Bel, Chief Executive Officer