Vancouver, British Columbia – October 24th, 2025 - Xali Gold Corp. (TSXV:XGC) ("Xali Gold” or the

“Company”) is pleased to announce that it has entered into a Share Purchase Agreement (“SPA”) on

October 23 rd to acquire the company Minera Calipuy S.A.C (“Calipuy”), which wholly owns the Pico

Machay Gold Project (“Pico Machay” or the “Pro ject”) in Central Peru , from Pan American Silver Corp.

(TSX:PAAS) (NYSE:PAAS) (“Pan American”) and its subsidiary, Aquiline Resources Inc. (“Aquiline”).

Pico Machay is a high-sulphidation gold deposit that lies within the northern extent of the Southern Peru

Epithermal Gold-Silver Belt and has a Historic Measured and Indicated Resource of 264,600 ounces (“oz”)

of gold (10.6 million (“M”) tonnes grading 0.78 grams per tonne (“gpt”) gold) and an additional Historic

Inferred Resource of 446,000 oz of gold (23.9 M tonnes grading 0. 58 gpt gold) (see Table 1 below for

resource details).

“The Pico Machay acquisition represents a pivotal step for Xali Gold as we expand our presence in one of

the world's most prolific epithermal gold-silver countries,” said Joanne Freeze, President and CEO of Xali

Gold. “With a historic resource already in place and various engineering studies con ducted since

discovery through 2010, the Project offers both immediate value and excellent upside potential. Pico

Machay is especially compelling given that the original resource was calculated using a long-term gold

price of US$700/oz. The current stronger gold price environment provides us with many opportunities to

upgrade the project and evaluate additional production alternatives that may not have been supported by

lower gold price s. With three decades of experience in Peru’s mining sector, we are confident that our

team of South American and gold experts combined with the strengths of local partnerships and the

country’s exceptional mineral potential, uniquely positions us to unlock the full value of this opportunity.

Our focus will be to up date the resource estimate and previous engineering studies with a near-term

production goal, while also testing exploration targets for potential resource expansion. In addition, there

are several other known high -sulphidation prospects in the area which we will evaluate for potential

acquisition and exploration to enhance/expand production at Pico Machay.”

About Pico Machay

Pico Machay was discovered in 1997 and explored by several juniors including Aquiline through 2009.

Aquiline completed various engineering studies including resource estimations and metallurgical

testwork. These studies targeted an open pit heap-leach operation, which was expected to be low-cost

and with a low strip ratio. Given that Aquiline’s engineering work prior to that company’s acquisition by

Pan American was based on a long -term gold price of $700/oz and several exploration targets remain

untested, Xali Gold believes there is excellent upside potential.

Geologically, Pico Machay occurs within the northern extent of the Southern Peru Epithermal Gold-Silver

Belt, which is one of three epithermal gold-silver belts in Peru that are host to world-class gold deposits,

including the Yanacocha and Pierina mines . Minera IRL Ltd.'s Corihuarmi Mine operates 63 km north of

Pico Machay.

NEWS RELEASE

Logistically, the Project lies in the eastern part of Western Cordillera Andes within the District of Santa

Ana, Province of Castrovirreyna and Department of Huancavelica which is a well-established mining

area/district. The Santa Barbara Mine and Julcani Mine have been operating since 1953 by Compañia de

Minas Buenaventura S.A. There are also c urrently several mines within a 45km radius of Pico Machay

including: Lalira, San Genoro, Astohuaraca, El Paloma, Cauduloso, Reliquias and Recuperada.

Pico Machay is 35 km southwest of the city of Huancavelica via road, 457 km from Lima or 270 km from

Pisco. Huancavelica is also connected to Callao, the port of Lima by a 650-kilometre intermontane rail

line. Santa Ana is the nearest town from the Project and is 13 km away.

Historic Resource

Resource Category Tonnes (M) Gold Grade (gpt) Contained Gold (oz)

Measured 4.7 0.91 137,500

Indicated 5.9 0.67 127,100

M & I 10.6 0.78 264,600

Inferred 23.9 0.58 446,000

Table 1: Historical Measured, Indicated and Inferred Gold Resources at Pico Machay

Notes to accompany the Historical Resource table:

1. Information regarding the historical resource at Pico Machay were obtained f rom the report titled: “Independent

Technical Report and Resource Estimate Pico Machay Gold Deposit” prepared by Caracle Creek International

Consulting Inc. for Aquiline Resources Inc (purchased by Pan American Silver) on November 25 th, 2009. The resource

numbers are highlighted in the Pan American News Release dated September 11, 2024 and found on both the Pan

American website and on www.sedarplus.ca. All resource estimates have used the same categories in accordance with

CIM Standards on Mineral Resources and Reserves.

2. The Qualified Person for the Pico Machay Project is David Thomas of DKT Geosolutions Inc.

3. All resource estimates for Pico Machay are considered historical in nature and are based on prior data and reports

prepared by previous property owners.

4. A qualified person has not done sufficient work yet to classify the historical estimates as current resources in

accordance with current CIM categories and the Company is not treating the historical estimates as current resources.

Significant data compilation, redrilling, resampling and data verification may be required by a qualified person before

the historical estimates on the project can be classified as a current resource.

5. There can be no assurance that any of the historical mineral resources, in whole or in part, will ever become

economically viable. In addition, mineral resources are not mineral reserves and do not have demonstrated economic

viability. Even if classified as a current resource, there is no certainty as to whether further exploration will result in any

inferred mineral resources being upgraded to an indicated or measured resource category.

Technical Information

All scientific and technical information in this news release has been prepared by, or approved by David

G. Thomas, P.Geo. and Joanne C. Freeze, P.Geo. Qualified Persons as defined by National Instrument 43-

101 for the Pico Machay Project. Ms. Freeze is the President and CEO of Xali Gold and Mr. Thomas is

Independent.

Resources were estimated using historical drilling (up to 2004) and current drilling (drilled between 2004

and 2008). The resource estimate includes holes up to Hole ABS-246, drilled in 2008. Micromine software

(Version 11.0.4) was used to facilitate the resource estimating process and the estimate was prepared in

accordance with CIM Standards on Mineral Resources and Reserves.

Mineralized zones were outlined to enforce geological control during block modelling. The geological

continuity of the broader mineralized zones, especially for the main zone, was quite good and could be

readily followed from hole-to-hole and section-to-section. An average specific gravity (rock density) value,

based on eleven samples, of 2.31 was used.

A block model was created, constrained by the zone wireframes. Blocks in the In ferred category were

defined based on search ellipse parameters with a range of 40m. Blocks in the Indicated and Measured

categories were identified manually, based on drill intercepts spacing values of 27 and 20m, respectively.

Ordinary block kriging was used to estimate block grades.

Share Purchase Agreement Terms

The terms of the SPA with Pan American and Aquiline to acquire 100% of their collective interest in

Calipuy, which owns all rights, title and interest in the Pico Machay Gold Project , include the following

cash payments (all dollar values are United States dollars):

Time Period Cash Payments

Closing of Transaction $0.5M

1st Year Anniversary $1.5M

2nd Year Anniversary $1.5M

3rd Year Anniversary $4.0M

4th Year Anniversary $3.0M

5th Year Anniversary $4.5M

On delineating a minimum of 1.25M oz Au $2.5M

Total $17.5M

Closing of the transactions under the SPA are subject to customary closing conditions for transactions of

this nature, as set out in the SPA, including TSX Venture Exchange approval for Xali Gold. Pan American

will retain certain security interests over Calipuy, subject to Xali Gold’s completion of the deferred

payments under the SPA.

Xali Gold is dedicated to being a responsible community partner.

Both David G. Thomas, P.Geo. and Joanne C. Freeze, P.Geo . Qualified Persons as defined by National

Instrument 43-101 have reviewed and approved the contents of this release.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

On behalf of the Board of Xali Gold Corp.

“Joanne Freeze” P.Geo.

President, CEO and Director

For further information please contact:

Joanne Freeze, President & CEO

Tel: + 1 604-512-3359

[email protected]

Forward-looking Disclaimer

This press release contains forward-looking information within the meaning of Canadian securities laws (“forward-looking

statements”). Forward -looking statements are typically identified by words such as: believe, expect, anticipate, intend,

estimate, plans, postulate and similar expressions, or are those, which, by their nature, refer to future events. All

statements that are not statements of historical fact are forward-looking statements.

Forward-looking statements in this press release include, without limitation: the timing to close the SPA and meet closing

conditions; potential upside and production from and viability of the Pico Machay Project; the potential tonnage, grades

and content of deposits; the steps and timing to convert historical mineral resource estimates to current estimates for the

Company. These forward-looking statements are made as of the date of this press release. Although the Company believes

the forward-looking statements in this press release are reasonable, it can give no assurance that the expectations and

assumptions in such stat ements will prove to be correct. The Company ca utions investors that any forward -looking

statements by the Company are not guarantees of future results or performance, and are subject to risks, uncertainties,

assumptions and other factors which could cause events or outcomes to differ materially from those expressed or implied

by such forward-looking statements.

Known risk factors and assumptions include risks associated with exploration and project development; accessing further

funding and related dilution: continuing its projected growth, or being fully able to implement its business strategies ; the

calculation of mineral resources and additional work required to convert historical resources to current mineral resources;

the nature, quality and quantity of any mineral deposits that may be located on the project ; operational risks associated

with mining and mineral processing; fluctuations in metal price s and assumption s including cos ts; title matters;

government regulation; obtaining and renewing necessary consents, authorizations, licenses and permits; environmental

liability and insurance; reliance on key personnel; local community opposition; currency fluctuations; labour disputes;

competition; variations in market conditions, and the volatility of our common share price and volume; future sales of

shares by existing shareholders; and other risk factors described in Xali Gold’s MD&A and other filings with Canadian

securities regulators, which may be viewed at www.sedar plus.ca. Although we have attempted to identify important

factors that could cause actual actions, events or results to differ materially from those described in forward -looking

statements, there may be other factors that cause actio ns, events or results not to be as anticipated, estimated or

intended.

There can be no assurance that forward -looking statements will prove to be accurate, as actual results and future events

could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance

on forward-looking statements. Xali Gold expressly disclaims any intention or obligation to update or revise any forward -

looking information, whether as a result of new information, future events or otherwise, except in accordance with

applicable securities laws.

CAUTIONARY NOTE TO U.S. INVESTORS

We advise U.S. investors that this news release uses terms defined in the 2014 edition of the Canadian Institute of Mining,

Metallurgy and Petroleum (CIM) “CIM Definition Standards on Mineral Resources and Mineral Reserves”, as incorporated

by reference in Canadian National Instrument 43 -101 “Standards of Disclosure for Mineral Projects”, for reporting of

mineral resource estimates. These Canadian standards, including NI 43 -101, differ from the requirements of the United

States Securities and Exchange Comm ission (SEC) as set forth in the mining disclosure rules under Regulation S -K

1300. Regulation S-K 1300 uses the same terminology for mineral resources, but the definitions are not identical to NI 43 -

101 and CIM Definition Standards. Regulation S-K 1300 uses the term “initial assessment” for an evaluation of potential

project economics based on mineral resources. This study type has some similarities to a Preliminary Economic

Assessment, but the definition and content requirements of an initial assessmen t are not identical to the definition and

content requirements for a PEA under NI 43-101.