Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

WRLG.V ·

Madsen Mine Site Update: Connection Drift 50% Complete, Primary Crusher Commissioned, Camp Installation Underway

Mine Development & Operations

December 4, 2024

Vancouver, British Columbia

Madsen Mine Site Update: Connection Drift 50% Complete, Primary Crusher Commissioned,

Camp Installation Underway

West Red Lake Gold Mines Ltd. (“West Red Lake Gold” or the “Company”) (TSXV: WRLG) (OTCQB:

WRLGF) is pleased to provide an operations update on restart readiness activities at its 100%

owned Madsen Mine project in the Red Lake Gold District of Northwestern Ontario, Canada.

“As we push towards our goal of restarting the Madsen Mine next year, the team continues to

make great progress on achieving key operational readiness milestones ,” said Shane Williams,

President and CEO. “Access development for test mining has been underway since late summer,

putting us on the edge of mining. The bulk samples generated through the test mining program

will be stockpiled on surface and then batch processed. Meanwhile the Connection Drift, primary

crusher, and camp projects are being completed on schedule while definition drilling and mine

planning and optimization continue.

“The entire WRLG team has been collectively working towards a successful restart of the Madsen

mine. We are now approaching the finish line on many of the fundamental pieces that support

this goal, including final optimization on the pre-feasibility study, completing key capital projects,

mining our first underground stopes, and starting up the mill. It is a very exciting time for WRLG

as we make the transition from developer to producer.”

Connection Drift 50% Complete

The Connection Drift, the largest of the capital projects supporting restart of the Madsen Mine,

is 50% complete and is on track for completion by the end of March 2025.

The Connection Drift is a 1.2-km haulage way connecting the historic West Portal, which through

extensive underground workings provides access to most parts of the Madsen mine including the

Austin, South Austin, and McVeigh zones, and the East Portal, a modern portal from which

development only extends a modest distance into the North Austin area.

The prior operator developed the East Portal and workings early in its construction effort but soon

shifted to the less capital-intensive approach of using the historic West Portal.

West Red Lake Gold found notable inefficiencies in using the West Portal for moving mined

material, including:

• The portal is relatively small, limiting hauling to 30-tonne trucks.

• The haulage ways descending from the West Portal were developed over many years of

historic operations; an array of steep sections and sharp corners make the route relatively

inefficient for trucking.

• The route from the portal to the mill crosses two public roads and goes past the town of

Madsen. Material must be dumped out of underground haul truck and reloaded into

surface-insured trucks and only hauled during daylight hours (because of noise restrictions)

to use this route.

• Much of the resource at Madsen sits spatially under the mill. Moving it west to bring it up

through the West Portal and then driving it back east to the mill adds kilometres of

trucking distance.

The East Portal, by contrast, is a large portal with modern workings. It can accommodate 60-tonne

trucks, the haulage route within the mine was designed with efficiency in mind, and the East

Portal is beside the primary crusher, which is close to the mill.

The Connection Drift will allow West Red Lake Gold to move all mined material out through the

East Portal, eliminating the inefficiencies of the West Portal (which will remain open for

ventilation and emergency access).

West Red Lake Gold raised $10 million in Canadian Development Expense flow through funds to

finance this major project. Work started in August 2024.

“The Connection Drift is a key project as we prepare to mine , for several reasons,” said Maurice

Mostert, Vice President Technical Services. “It is creating an efficient way to move material, the

effort to develop it is giving our mining teams valuable experience working accurately and

effectively underground at Madsen, and it is unlocking the potential to drill test some prospective

targets.

“Investing in capital projects to create an efficient operation before we restart this mine is one of

the key pillars of our Madsen thesis, which is that an efficient mine tapping a well -drilled and

understood resource in appropriate ways will be very much worth the effort.”

The Connection Drift is on track for its targeted completion date in late March. To date 6 04.8

metres have been completed, of the 1.2 km total length.

Figure 1. A view of the Connection Drift, which is progressing west to east. This 1.2-km haulage

way is now 50% complete.

Primary Crusher Commissioned

The primary crusher was delivered to the Madsen Mine site on November 5 , 2024 . It was

unloaded, assembled, and has now been commissioned.

“A fully functioning and reliable primary crusher is a good example of the kind of capital

investments we are making to support efficient operations when we restart the Madsen Mine,”

said Williams. “It is exciting to see the crusher processing material as we commission this key

piece of infrastructure.”

Figure 2. The CRJ3042 Electric Primary Jaw Crushing Plant being commissioned at the Madsen

Mine site in late November.

Camp Installation

The camp was delivered on November 11, 2024 and is now being installed at the Madsen Mine

site.

The camp is a 114-person facility. It offers individual rooms with ensuite bathrooms for each

worker, a kitchen and dining hall, and recreation space.

Horizon North, an industry leader in providing accommodations and services to meet workforce

requirements within the mining industry in Canada, supplied and will staff the camp facility.

Figure 3. The 114-person workforce accommodations facility for the Madsen Mine project

during the unloading and installation process.

QUALIFIED PERSON

The technical information presented in this news release has been reviewed and approved by

Maurice Mostert, P .Eng., Vice President of Technical Services for West Red Lake Gold and the

Qualified Person for technical services at the West Red Lake Project, as defined by National

Instrument 43-101 Standards of Disclosure for Mineral Projects.

ABOUT WEST RED LAKE GOLD MINES

West Red Lake Gold Mines Ltd. is a mineral exploration company that is publicly traded and

focused on advancing and developing its flagship Madsen Gold Mine and the associated 47

km2 highly prospective land package in the Red Lake district of Ontario. The highly productive Red

Lake Gold District of Northwest Ontario, Canada has yielded over 30 million ounces of gold from

high-grade zones and hosts some of the world’s richest gold deposits. WRLG also holds the wholly

owned Rowan Property in Red Lake, with an expansive property position covering 31

km2 including three past producing gold mines – Rowan, Mount Jamie, and Red Summit.

ON BEHALF OF WEST RED LAKE GOLD MINES LTD.

“Shane Williams”

Shane Williams

President & Chief Executive Officer

FOR FURTHER INFORMATION, PLEASE CONTACT:

Gwen Preston

Vice President Communications

Tel: (604) 609-6132

Email: [email protected] or visit the Company’s website

at https://www.westredlakegold.com

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in

the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of

this release.

CAUTIONARY STATEMENT AND FORWARD-LOOKING INFORMATION

The decision to continue with the advancement of the Madsen Mine restart and the Company’s

operations and plans with respect thereto, as described herein (the “Madsen Mine Restart”), are

based on economic models prepared by the Company in conjunction with management’s

knowledge of the property and the existing estimate of indicated and inferred mineral resources

on the property set out in the report entitled, “Independent NI 43 -101 Technical Report and

Updated Mineral Resource Estimate for the PureGold Mine , Canada”, with an effective date of

July 31, 2022, as amended on April 24, 2024, a copy of which is available on SEDAR+ at

www.sedarplus.ca. The Madsen Mine Restart is not based on a preliminary economic assessment,

a pre -feasibility study or a feasibility study of mineral reserves demonstrating economic and

technical viability. Accordingly, there is increased uncertainty and economic and technical risks of

failure associated with the Madsen Mine Restart, in particular: the risk that mineral grades will

be lower than expected; the risk that additional ongoing mining operations are more difficult or

more expensive than expected; and the risk that production and economic variables may vary

considerably, due to the absence of a detailed economic and technical analysis undertaken in

accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects.

Certain statements contained in this news release may constitute “forward-looking information”

within the meaning of applicable securities laws. Forward -looking information generally can be

identified by words such as “anticipate”, “expect”, “estimate”, “forecast”, “planned”, and similar

expressions suggesting future outcomes or events. Forward -looking information is based on

current expectations of management; however, it is subject to known and unknown risks,

uncertainties and other factors that may cause actual results to differ materially from the forward-

looking information in this news release and include without limitation, statements relating to

plans for the potential restart of minin g operations at the Madsen Mine, the potential of the

Madsen Mine; any untapped growth potential in the Madsen deposit or Rowan deposit; and the

Company’s future objectives and plans. Readers are cautioned not to place undue reliance on

forward-looking information.

Forward-looking information involve numerous risks and uncertainties and actual results might

differ materially from results suggested in any forward -looking information. These risks and

uncertainties include, among other things, market volatility; the state of the financial markets for

the Company’s securities; fluctuations in commodity prices; timing and results of the cleanup and

recovery at the Madsen Mine; and changes in the Company’s business plans. Forward -looking

information is based on a number of key expectations and assumptions, including without

limitation, that the Company will continue with its stated business objectives and its ability to

raise additional capital to proceed. Although management of the Company has attempted to

identify important factors that could cause actual results to differ materially from those contained

in forward -looking information, there may be other factors that cause results not to be as

anticipated, estimated or intended. There can be no assurance that such forward -looking

information will prove to be accurate, as actual results and future events could differ materially

from those anticipated in such forward-looking information. Accordingly, readers should not place

undue reliance on forward -looking information. Reade rs are cautioned that reliance on such

information may not be appropriate for other purposes. Additional information about risks and

uncertainties is contained in the Company’s management’s discussion and analysis for the year

ended November 30, 2023, and the Company’s annual information form for the year ended

November 30, 2023, copies of which are available on SEDAR+ at www.sedarplus.ca.

The forward -looking information contained herein is expressly qualified in its entirety by this

cautionary statement. Forward-looking information reflects management’s current beliefs and is

based on information currently available to the Company. The forw ard-looking information is

made as of the date of this news release and the Company assumes no obligation to update or

revise such information to reflect new events or circumstances, except as may be required by

applicable law.

For more information on the Company, investors should review the Company’s continuous

disclosure filings that are available on SEDAR+ at www.sedarplus.ca.