Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

WRLG.V ·

West Red Lake Gold Reports Third Quarter Operations Update for Madsen Mine Ramp-Up

Mine Development & Operations

October 7, 2025

Vancouver, BC

West Red Lake Gold Reports Third Quarter Operations

Update for Madsen Mine Ramp-Up

West Red Lake Gold Mines Ltd. (“West Red Lake Gold” or “WRLG” or the “Company”)

(TSXV: WRLG) (OTCQB: WRLGF) is pleased to provide a third quarter (“Q3”) update on the

ramp-up of the Madsen Mine located in the Red Lake Gold District of Northwestern Ontario,

Canada.

“Ramp up at the Madsen mine is progressing well, ” said Shane Williams, President and

CEO. “It is exciting to see tonnages rise, efficiencies increase, and gold production grow

quarter by quarter, as planned. ”

“It takes a methodical approach to step a mine towards steady state operations, ramping

up daily mining while completing final infrastructure projects and underground

development needs, and at Madsen we are now seeing the benefits of such an approach.

Operational performance at the mine in Q3 continued within the expected range.

Importantly, key parameters remained consistent, including ongoing strong reconciliation

between planned and actual gold grades in modeled tonnes, and certain capital projects

are starting to have notable positive impacts. I am excited to see the final pieces of this

operation come into place over the fourth quarter, positioning Madsen for commercial

production in early 2026.”

In Q3 the Madsen Mine produced 35,700 tonnes of ore at an average grade of 5.4 grams per

tonne gold. The mill poured 7,055 ounces of gold. Note that mined and poured ounces do

not align because of factors including month end timings and gold in circuit. Those ounces

were sold at an average price of US$3,456 per ounce for gross proceeds of CAD$33 million.

This compares to 5,260 ounces of gold poured in Q2 for gross proceeds of CAD$24 million

and 496 ounces of gold in Q1 for gross proceeds of CAD$2.1 million. Q3 gold production

represented a 34% increase over Q2 gold production, a rate that positions Madsen to reach

targeted output levels early in 2026.

Mined ore tonnage is increasing month over month, within the variability of mine ramp up.

Increasing daily mined tonnage is the primary ramp-up factor at Madsen, so the Company

is pleased to report ore tonnage rising consistently.

2

Figure 1. Ore tonnes mined at Madsen on a monthly basis from December 2024

through September 2025.

Mined waste development is also progressing as planned, as crews drive access to new

areas for drilling and mining. Importantly, as of mid-September mined waste is now being

stored largely underground.

The underground waste rock storage program is a key de-bottlenecking effort recently in

effect and is directly supporting the mine’s ability to move ore tonnes. In the second half of

September the mine moved over 1,000 tonnes of ore per day on several days, including a

record day moving 1,400 tonnes. This new ability to store all waste rock underground,

which has shifted trucking capacity away from waste haulage to ore haulage, bodes well

for production.

In terms of processed tonnes, variability was part of the ramp-up plan. To test the mill’s

ability to run at higher throughputs, in June and July the mill was fed a combination of

mined and stockpiled tonnes. Since the start of August, the mill has only processed direct

mined tonnes. Madsen’s gold output is now a clear representation of what the mine is

producing as the operation progresses towards operational stability.

Focus during Q3 was on balancing the competing priorities of ramp-up projects and regular

mining operations. For instance, the need to develop a secondary egress from a key mining

complex impacted ore production in August while work on underground power distribution

impacted mining optionality in September. The Company also managed labour force

availability impacts stemming from the June mine site incident.

3

Reconciliation between modeled and actual mined grades remains strong. Figure 2 below

shows a comparison of modeled versus actual longhole stope grades. Note that sill

development contributed 25 to 30% of milled tonnage over the quarter; Figure 2 does not

consider sill tonnes and grade. See Figure 3 for sill grade data.

Figure 2: Comparison of modeled versus actual gold grade in mined longhole stopes.

Note this chart does not include sill tonnes and grade.

Sill development tonnes continue to outperform on grade. In Q3, mined sill tonnes

averaged 8.8 g/t gold.

0

1

2

3

4

5

6

July August September

Gold Grade (g/t Au)

Mined Stope Grade Reconciliation

Stope Model Grade (weighted average)

4

Figure 3. Sill development gold grade and ounce production at the Madsen Mine.

Equipment availability has improved over the quarter as maintenance systems ramped up.

The maintenance team is keeping availabilities for haul trucks, scoops, jumbo drills, and

other equipment at target levels.

Pathway to Commercial Production

During the quarter West Red Lake Gold defined the operational components the Company

aims to implement before declaring commercial production. With the mine seeing good

progress on staffing, the geology-engineering workflow producing good reconciliation and

grounding an achievable detailed mine plan, the mill returning strong and consistent

recoveries, and other components from maintenance to water treatment also ramping up

as expected, focus with respect to commercial production went to operational

components, including:

• Storage of waste rock in historic underground voids. The Madsen Mine produced

approximately 2 million ounces of gold from 1936 to 1972. Many mined-out stopes

were backfilled, but several large historic stopes were left void. As West Red Lake

Gold advances deeper into the mine, such stopes are verified and measured. It was

determined that the 1136 void, which is proximal to the 1155 mining complex that is

providing 40% of mine’s produced ounces in H2 2025, is significantly larger than

expected (65,000 tonnes versus an initial expectation of 34,000 tonnes). It is also a

competent void. As a result, this area is now being utilised to store waste rock

utilising a combination of cemented rock fill (“CRF”) and dumped waste rock, at

rates up to 2,000 tonnes per day.

5

Since getting this waste storage process operational in mid-September, ore

production from the mine has increased because of increased truck availability and

ventilation capacity.

• Skipping 350 tonnes per day up the shaft. The Madsen Shaft was developed in the

1950s; the Company rehabilitated the square timbered shaft in H2 2024. In 2025

management decided to use the shaft to move material. West Red Lake Gold

ordered the needed hoist components; the rope was delivered in August while the

skip and scrolls are expected in October.

Once these components are installed, the Company expects to start moving 350

tonnes of ore out of the mine each day through the shaft. This is expected to provide

notable benefit over trucking these tonnes in terms of cost savings and ventilation

capacity.

• Final equipment deliveries. The mine expects to take delivery of another 42-tonne

haul truck and two 4-yard Komatsu scoops over the next two months, which will

complete the planned fleet of mining equipment.

The first of these requirements – underground waste storage – is now operational. The shaft

is expected to start operating in November and the equipment should be delivered and

operational at approximately the same time.

These achievements will create operational stability at the Madsen mine. The 2026 detailed

mine plan is also expected before the end of the year, which will enable confident guidance

as part of a declaration of commercial production.

“The Madsen Mine remains on track towards commercial production, ” states Williams.

“We are staying focused on a methodical approach to this ramp up because developing a

strong sustainable mine gives us the potential to create more value in Red Lake. Such

potential is very apparent in our Rowan project, which we are advancing quickly so that its

anticipated production rate of 35,000 ounces adds to our Red Lake production profile

within a few years, and we see significant additional value potential at Madsen as we test

high-grade targets in and around the deposit and unlock the deeper opportunity of this gold

system. ”

Additional Information on Recent Financing

In connection with the Company’s bought deal public offering previously disclosed on

September 23, 2025, the Company raised an aggregate of C$40,651,260 and the Company

paid Raymond James Ltd., as lead underwriter, a cash commission of $2,270,469.60.

The technical information presented in this news release has been reviewed and approved

by Will Robinson, P .Geo., Vice President of Exploration for West Red Lake Gold and the

Qualified Person for exploration at the West Red Lake Project, and by Hayley Halsall-Whitney,

P .Eng., Vice President of Operations for West Red Lake Gold and the Qualified Person for

6

technical services at the West Red Lake Project, as defined by National Instrument 43-101 -

Standards of Disclosure for Mineral Projects.

ABOUT WEST RED LAKE GOLD MINES

West Red Lake Gold Mines Ltd. is a gold mining company that is publicly traded and focused

on its flagship high-grade Madsen Gold Mine and the associated 47 km 2 highly prospective

land package in the Red Lake district of Ontario. The highly productive Red Lake Gold District

of Northwest Ontario, Canada has yielded over 30 million ounces of gold from high -grade

zones and hosts some of the world's richest gold depo sits. WRLG also owns the Rowan

Property in Red Lake, which hosts a small, high -grade deposit that West Red Lake Gold is

looking to advance towards production.

ON BEHALF OF WEST RED LAKE GOLD MINES LTD.

“Shane Williams”

Shane Williams

President & Chief Executive Officer

FOR FURTHER INFORMATION, PLEASE CONTACT:

Gwen Preston

7

Vice President Communications

Tel: (604) 609-6132

Email: [email protected] or visit the Company’s website

at https://www.westredlakegold.com

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is

defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy

or accuracy of this release.

CAUTIONARY STATEMENT AND FORWARD-LOOKING INFORMATION

Certain statements contained in this news release may constitute “forward -looking

information” within the meaning of applicable securities laws. Forward-looking information

generally can be identified by words such as “anticipate” , “expect” , “estimate” , “forecast” ,

“planned” , and similar expressions suggesting future outcomes or events. Forward -looking

information is based on current expectations of management; however, it is subject to known

and unknown risks, uncertainties and other factors that may cause actual results to differ

materially from the forward-looking information in this news release.

Forward-looking information involves numerous risks and uncertainties and actual results

might differ materially from results suggested in any forward-looking information. These risks

and uncertainties include, among other things, market volatility; the st ate of the financial

markets for the Company’s securities; fluctuations in commodity prices; and changes in the

Company’s business plans. Forward -looking information is based on a number of key

expectations and assumptions, including without limitation, that the Company will continue

with its stated business objectives and its ability to raise additional capital to proceed.

Although management of the Company has attempted to identify important factors that

could cause actual results to differ materially fro m those contained in forward -looking

information, there may be other factors that cause results not to be as anticipated, estimated

or intended. There can be no assurance that such forward -looking information will prove to

be accurate, as actual results an d future events could differ materially from those

anticipated in such forward -looking information. Accordingly, readers should not place

undue reliance on forward-looking information. Readers are cautioned that reliance on such

information may not be appr opriate for other purposes. Additional information about risks

and uncertainties is contained in the Company’s management’s discussion and analysis for

the year ended December 31, 2024, and the Company’s annual information form for the year

ended December 31, 2024, copies of which are available on SEDAR+ at www.sedarplus.ca.

The forward-looking information contained herein is expressly qualified in its entirety by this

cautionary statement. Forward -looking information reflects management’s current beliefs

and is based on information currently available to the Company. The forw ard-looking

information is made as of the date of this news release and the Company assumes no

8

obligation to update or revise such information to reflect new events or circumstances,

except as may be required by applicable law.

For more information on the Company, investors should review the Company’s continuous

disclosure filings that are available on SEDAR+ at www.sedarplus.ca.