Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

WRLG.V ·

West Red Lake Gold Intersects 54.19 g/t Au over 4m and 23.73 g/t Au over 3.53m at Austin – Madsen Mine

Drill Results

September 10, 2024

Vancouver, BC

West Red Lake Gold Intersects 54.19 g/t Au over 4m and

23.73 g/t Au over 3.53m at Austin – Madsen Mine

West Red Lake Gold Mines Ltd. (“West Red Lake Gold” or “WRLG” or the “Company”) (TSXV:

WRLG) (OTCQB: WRLGF) is pleased to report drill results from its 100% owned Madsen Mine

located in the Red Lake Gold District of Northwestern Ontario, Canada.

The drill results featured in this news release are focused on the high -grade Austin Zone. The

Austin Zone currently contains an Indicated mineral resource of 914,200 ounces (“oz”) grading

6.9 grams per tonne (“g/t”) gold (“Au”) , with an additional Inferred resource of 104,900 oz

grading 6.5 g/t Au.

The purpose of this drilling was definition within priority areas of Austin to continue building an

inventory of high-confidence ounces to support the restart of production at the Madsen mine ,

which is expected to commence in H2 2025. The Company expects to complete a pre-feasibility

study in support of that restart goal in the coming months.

AUSTIN ZONE HIGHLIGHTS:

• Hole MM24D-12-4791-020 Intersected 4m @ 54.19 g/t Au, from 32m to 36m, Including

1m @ 215.61 g/t Au, from 33m to 34m.

• Hole MM24D-12-4791-026 Intersected 3.53m @ 23.73 g/t Au, from 27.50m to 31.03m,

Including 1m @ 79.81 g/t Au, from 30.03m to 31.03m

• Hole MM24D-12-4791-023 Intersected 3m @ 24.49 g/t Au, from 32m to 35m, Including

1m @ 71.02 g/t Au, from 33m to 34m; AND

• Hole MM24D-12-4791-041 Intersected 6m @ 11.65 g/t Au, from 35m to 41m, Including

1m @ 10.86 g/t Au, from 36m to 37m, Also including 1.05m @ 47.27 g/t Au, from

39.95m to 41.00m.

• Hole MM24D-12-4791-035 Intersected 3.2m @ 15.84 g/t Au, from 38.8m to 42.0m,

Including 2m @ 24.32 g/t Au, from 39.4m to 41.4m.

Page 2 of 19

• Hole MM24D-12-4791-002 Intersected 4.8m @ 9.95 g/t Au, from 26.2m to 31.0m,

Including 0.87m @ 10.47 g/t Au, from 26.20m to 27.07m, Also including 0.52m @ 43.08

g/t Au, from 29.82m to 30.34m.

• Hole MM24D-12-4791-023 also Intersected 3.15m @ 15.06 g/t Au, from 20.35m to

23.50m, Including 0.88m @ 22.62 g/t Au, from 21.12m to 22.00m, Also including 0.98m

@ 20.20 g/t Au, from 22.52m to 23.50m.

Shane Williams, President & CEO, stated, “The deeper portions of the Austin Zone are continuing

to return very positive results as we advance the infill drilling programs and increase our

confidence in these areas of the mine . Due to limited underground development, t he two

previous operators were only able to access portions of the Madsen deposit down to around 9

level. We are very excited to continue accessing deeper portions of the deposit which were

historically mined during a period when gold was only valued at $20-40 per ounce. This resulted

in very selective mining practices targeting just the core of the system that left behind a lot of

mineralization that would be considered high grade by current standards. With gold prices now

in excess of US $2,500/oz we are taking full advantage of that remnant material and see a lot of

upside at depth in Madsen.”

Plan maps and section for the Austin drilling outlined in this release are provided in Figures 1

through 10. To see these drill holes in the context of a 3-dimensional model of the Madsen project

mineral resource, click here. https://vrify.com/decks/16834?auth=fa5e3754-1ad2-440b-b5cc-

fcfee08d8175

TABLE 1. Significant intercepts (>3 g/t Au) from drilling at Austin Zone.

Hole ID Target From (m) To (m) Length (m)* Au (g/t)

MM24D-12-4791-001 Austin No Assays > 3 g/t Au

MM24D-12-4791-002

Austin

26.20 31.00 4.80 9.95

Incl. 26.20 27.07 0.87 10.47

Also Incl. 29.82 30.34 0.52 43.08

AND Austin 37.50 40.00 2.50 3.65

MM24D-12-4791-003 Austin 24.34 29.50 5.16 5.65

Incl. 28.00 28.83 0.83 17.54

AND Austin 35.18 38.00 2.82 4.73

MM24D-12-4791-004 Austin 22.29 23.29 1.00 4.43

AND Austin 24.93 25.71 0.78 3.41

AND Austin 26.50 27.50 1.00 4.82

MM24D-12-4791-005 Austin 26.00 30.00 4.00 4.45

AND Austin 33.00 34.00 1.00 3.06

AND Austin 38.19 39.19 1.00 10.70

MM24D-12-4791-006 Austin 23.58 24.10 0.52 3.28

AND Austin 26.10 26.63 0.53 9.66

Page 3 of 19

Hole ID Target From (m) To (m) Length (m)* Au (g/t)

AND Austin 30.64 31.50 0.86 4.56

MM24D-12-4791-007 Austin 27.70 28.50 0.80 5.37

MM24D-12-4791-008 Austin 43.07 46.00 2.93 8.44

Incl. 44.00 45.00 1.00 18.13

AND Austin 51.00 51.80 0.80 6.74

MM24D-12-4791-009 Austin 20.58 22.06 1.48 3.98

AND Austin 25.00 28.65 3.65 5.74

Incl. 27.25 28.00 0.75 20.02

MM24D-12-4791-010 Austin No Assays > 3 g/t Au

MM24D-12-4791-011 Austin No Assays > 3 g/t Au

MM24D-12-4791-012 Austin 23.82 24.50 0.68 5.48

MM24D-12-4791-013 Austin 44.55 46.50 1.95 4.91

MM24D-12-4791-014 Austin No Assays > 3 g/t Au

MM24D-12-4791-015 Austin 20.68 22.00 1.32 3.72

MM24D-12-4791-016 Austin No Assays > 3 g/t Au

MM24D-12-4791-017 Austin 18.45 22.00 3.55 5.83

MM24D-12-4791-018 Austin 23.10 29.00 5.90 3.62

MM24D-12-4791-019 Austin 21.82 24.00 2.18 9.15

Incl. 21.82 23.00 1.18 15.80

MM24D-12-4791-020 Austin 20.00 22.92 2.92 7.70

Incl. 21.46 21.96 0.50 40.74

AND Austin 32.00 36.00 4.00 54.19

Incl. 33.00 34.00 1.00 215.61

MM24D-12-4791-021 Austin 30.00 33.22 3.22 7.92

Incl. Austin 30.00 30.50 0.50 21.38

AND Austin 35.00 37.50 2.50 3.47

MM24D-12-4791-022 Austin 26.00 28.70 2.70 5.13

Incl. 27.43 28.00 0.57 15.04

MM24D-12-4791-023

Austin

20.35 23.50 3.15 15.06

Incl. 21.12 22.00 0.88 22.62

Also Incl. 22.52 23.50 0.98 20.20

AND Austin 32.00 35.00 3.00 24.49

Incl. 33.00 34.00 1.00 71.02

MM24D-12-4791-024 Austin 48.80 51.00 2.20 8.01

Incl. 49.77 50.50 0.73 20.54

MM24D-12-4791-025 Austin 41.75 45.25 3.50 8.70

Incl. 43.25 44.25 1.00 18.82

AND Austin 48.00 49.00 1.00 3.02

MM24D-12-4791-026 Austin 27.50 31.03 3.53 23.73

Incl. 30.03 31.03 1.00 79.81

MM24D-12-4791-027 Austin 30.50 36.30 5.80 5.51

Incl. 34.30 35.30 1.00 15.58

MM24D-12-4791-028 Austin 36.72 41.98 5.26 5.76

Page 4 of 19

Hole ID Target From (m) To (m) Length (m)* Au (g/t)

Incl. 40.45 41.98 1.53 10.87

AND Austin 45.00 48.00 3.00 4.30

MM24D-12-4791-029 Austin 28.00 30.75 2.75 7.81

Incl. 29.00 30.00 1.00 14.39

AND Austin 33.00 34.30 1.30 6.90

MM24D-12-4791-030 Austin No Assays > 3 g/t Au

MM24D-12-4791-031 Austin 30.18 34.04 3.86 3.99

MM24D-12-4791-032 Austin 41.95 44.00 2.05 3.99

MM24D-12-4791-033 Austin 33.65 34.30 0.65 12.67

MM24D-12-4791-034 Austin 32.00 33.04 1.04 4.24

AND Austin 35.60 38.00 2.40 11.36

Incl. 35.60 36.31 0.71 37.75

MM24D-12-4791-035 Austin 38.80 42.00 3.20 15.84

Incl. 39.40 41.40 2.00 24.32

AND Austin 44.00 46.00 2.00 3.54

MM24D-12-4791-036 Austin 27.00 34.00 7.00 3.76

MM24D-12-4791-037 Austin 30.00 33.47 3.47 3.82

MM24D-12-4791-038 Austin 36.60 38.00 1.40 5.90

MM24D-12-4791-039 Austin 37.15 40.75 3.60 4.68

MM24D-12-4791-040 Austin 36.30 38.50 2.20 5.89

Incl. 36.30 37.00 0.70 14.55

AND Austin 44.70 45.20 0.50 3.58

MM24D-12-4791-041

Austin

35.00 41.00 6.00 11.65

Incl. 36.00 37.00 1.00 10.86

Also Incl. 39.95 41.00 1.05 47.27

*The “From-To” intervals in Table 1 are denoting overall downhole length of the intercept. True thickness has not

been calculated for these intercepts but is expected to be ≥ 70% of downhole thickness based on intercept angles

observed in the drill core. Internal dilution for composite intervals does not exceed 1m for samples grading <0.1 g/t

Au.

TABLE 2: Drill collar summary for holes reported in this News Release.

Hole ID Target Easting Northing Elev

(m)

Length

(m) Azimuth Dip

MM24D-12-4791-001 Austin 435847 5646644 -147 50.6 86 -25

MM24D-12-4791-002 Austin 435847 5646645 -145 83.0 64 27

MM24D-12-4791-003 Austin 435847 5646645 -144 88.8 66 35

MM24D-12-4791-004 Austin 435847 5646645 -145 81.0 73 30

MM24D-12-4791-005 Austin 435847 5646645 -144 95.1 76 40

MM24D-12-4791-006 Austin 435848 5646644 -146 75.2 83 10

MM24D-12-4791-007 Austin 435847 5646643 -146 111.0 93 10

MM24D-12-4791-008 Austin 435847 5646643 -147 100.3 96 -32

Page 5 of 19

Hole ID Target Easting Northing Elev

(m)

Length

(m) Azimuth Dip

MM24D-12-4791-009 Austin 435847 5646643 -144 105.0 98 32

MM24D-12-4791-010 Austin 435847 5646643 -146 102.3 103 10

MM24D-12-4791-011 Austin 435847 5646643 -145 111.0 104 22

MM24D-12-4791-012 Austin 435847 5646643 -144 81.0 105 42

MM24D-12-4791-013 Austin 435847 5646643 -147 90.0 105 -32

MM24D-12-4791-014 Austin 435846 5646643 -147 75.0 113 -32

MM24D-12-4791-015 Austin 435846 5646643 -145 57.0 117 20

MM24D-12-4791-016 Austin 435846 5646643 -144 66.0 120 40

MM24D-12-4791-017 Austin 435846 5646642 -145 60.0 125 29

MM24D-12-4791-018 Austin 435846 5646642 -146 90.0 127 8

MM24D-12-4791-019 Austin 435846 5646642 -145 63.0 130 19

MM24D-12-4791-020 Austin 435846 5646642 -144 72.0 132 37

MM24D-12-4791-021 Austin 435846 5646642 -146 78.0 136 -7

MM24D-12-4791-022 Austin 435846 5646642 -146 84.0 137 7

MM24D-12-4791-023 Austin 435846 5646642 -145 66.0 137 27

MM24D-12-4791-024 Austin 435845 5646642 -147 72.0 140 -28

MM24D-12-4791-025 Austin 435845 5646641 -147 66.0 139 -22

MM24D-12-4791-026 Austin 435845 5646641 -145 63.0 141 17

MM24D-12-4791-027 Austin 435845 5646641 -146 75.0 144 -5

MM24D-12-4791-028 Austin 435845 5646641 -147 66.0 144 -13

MM24D-12-4791-029 Austin 435845 5646641 -146 63.0 146 8

MM24D-12-4791-030 Austin 435845 5646641 -145 75.0 148 25

MM24D-12-4791-031 Austin 435845 5646641 -146 75.0 149 1

MM24D-12-4791-032 Austin 435845 5646641 -147 85.0 150 -15

MM24D-12-4791-033 Austin 435844 5646641 -145 72.0 151 16

MM24D-12-4791-034 Austin 435844 5646641 -146 66.0 153 8

MM24D-12-4791-035 Austin 435844 5646641 -146 69.0 154 -6

MM24D-12-4791-036 Austin 435844 5646641 -145 63.0 155 32

MM24D-12-4791-037 Austin 435844 5646641 -145 72.0 158 23

MM24D-12-4791-038 Austin 435844 5646641 -146 85.0 159 5

MM24D-12-4791-039 Austin 435844 5646640 -145 63.0 166 14

MM24D-12-4791-040 Austin 435844 5646640 -145 75.0 170 19

MM24D-12-4791-041 Austin 435844 5646641 -145 63.0 170 26

DISCUSSION

The Austin zone is accessed through the Madsen Mine West Portal . Like the other mineralized

domains that comprise the Madsen Mine, the Austin structures are hosted within broad,

kilometer-scale planar alteration and deformation corridors that have been repeatedly

reactivated during gold mineralization and subsequent deformation and metamorphism.

Page 6 of 19

At the deposit scale the Austin, South Austin, North Austin, and McVeigh Zones are locally folded

and structurally dismembered by transposition and rotation into the penetrative S2 Foliation. In

addition to this intense deformation overprint, the mineralized veins and alteration have been

subjected to the relatively high temperatures of amphibolite facies metamorphism, which led to

extensive recrystallization and growth of the skarn -like replacement mineral assemblage of

diopside-amphibole-quartz-biotite.

All significant gold mineralization on the mine property is demonstrably early relative to the most

significant, penetrative deformation (D2) and metamorphic events. The North Austin Zone

displays ‘mine-style’ alteration and mineralization and consists of multiple mineralized domains

defined over a strike length of 0.5km. Mineralization remains open at depth and along strike to

the northeast.

In drill core, or at underground face exposures, gold-bearing zones at the Madsen Mine are best

identified visually by fine (sub-millimetre) grains of free gold within strong alteration and veining.

All high-grade intervals generally contain visible gold o n drill core exteriors, although numerous

examples exist of high-grade assays where visible gold was only identified within the interior (cut

surface) of the core samples. Apart from the presence of free gold, pervasive silicification (locally

accompanied by discrete quartz veining) and quartz -carbonate or diopside veining are the best

indicators that a given interval is within a high-grade zone along/within the mineralized structure.

The current underground drilling program at the Madsen Mine is focused on further definition

of near-term mining inventory , as well as growth of the current mineral resource. Drilling has

been focused on the more continuous and higher -grade portions of the Austin, South Austin,

North Austin and McVeigh Zones. This will continue to be the strategy through 2024.

High resolution versions of all the figures contained in this press release can be found at the

following web address: https://westredlakegold.com/september-10th-news-release-maps/

FIGURE 1. Madsen Mine long section showing location of 12-4791 Drill Bay in Austin Zone.[1]

[1] Mineral resources are estimated at a cut-off grade of 3.38 g/t Au and a gold price of US1,800/oz. Please refer to the technical report entitled “Independent NI 43-

101 Technical Report and Updated Mineral Resource Estimate for the PureGold Mine, Canada”, prepared by SRK Consulting (Canada) Inc. and dated June 16, 2023,

and amended April 24, 2024. A full copy of the SRK report is available on the Company’s website and on SEDAR+ at www.sedarplus.ca.

Page 8 of 19

FIGURE 2. Austin plan view drill section showing assay highlights for Holes MM24D-12-4791-001 through -041.[1]

[1] Mineral resources are estimated at a cut-off grade of 3.38 g/t Au and a gold price of US1,800/oz. Please refer to the technical report entitled “Independent NI 43-

101 Technical Report and Updated Mineral Resource Estimate for the PureGold Mine, Canada”, prepared by SRK Consulting (Canada) Inc. and dated June 16, 2023,

and amended April 24, 2024. A full copy of the SRK report is available on the Company’s website and on SEDAR+ at www.sedarplus.ca.