Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

WHN.V ·

Westhaven Announces Updated Preliminary Economic Assessment FOR the Shovelnose GOLD Project, British Columbia After-Tax NPV Doubled to $454 Million After-Tax IRR of 43.2% Payback of Initial Capital Costs of 2.1 Years

Economic Studies

WESTHAVEN ANNOUNCES UPDATED PRELIMINARY ECONOMIC ASSESSMENT

FOR THE SHOVELNOSE GOLD PROJECT, BRITISH COLUMBIA

AFTER-TAX NPV DOUBLED TO $454 MILLION

AFTER-TAX IRR OF 43.2%

PAYBACK OF INITIAL CAPITAL COSTS OF 2.1 YEARS

All amounts are in Canadian Dollars unless otherwise noted

Vancouver, B.C. – March 3 rd, 2025 – Westhaven Gold Corp. (TSX-V:WHN) is pleased to report the

completion of an Updated Preliminary Economic Assessment (“PEA”) at its 100% owned 41,634-hectare

Shovelnose Gold Property (the “Property”) located within the prospective Spences Bridge Gold Belt

(“SBGB”), which borders the Coquihalla Highway 30 kilometres south of Merritt, British Columbia. The

PEA outlines a robust, low-cost, rapid pay-back, high margin, 11.1 year underground gold mining

opportunity and is based on updated mineral resources that include contributions from the South, Franz

and FMN zones.

At a gold price of US$2,400/oz and an exchange rate of C$1.00 to US$0.72, the Shovelnose base case

estimate (the "Base Case") generates an after-tax net present value (NPV) at a 6% discount rate of $454

million and an internal rate of return (IRR) of 43.2%. The proposed mine will operate over an initial 11.1

year mine-life with average annual life-of-mine gold production of 56,000 ounces. Initial capital

expenditure to fund construction and commissioning is estimated at $184 million, with a life-of-mine

capital cost of $379 million and a payback period of 2.1 years. The all-in sustaining costs (as defined per

World Gold Council guidelines, less corporate G&A) are estimated to be US$836 per ounce of gold

produced.

Summary Table - Economic Sensitivity to Long Term Gold Price

Long Term Metal Price

Variability

Corresponding

Gold Price

After Tax NPV

(at 6%)

After Tax

IRR

(percentage change) US$/ounce CDN $ millions (%)

- 20% 1,920 284.3 30.4

- 10% 2,160 369.1 36.9

base case 2,400 453.7 43.2

+ 10% 2,640 538.3 49.5

+ 20% 2,880 622.8 55.7

TSX-V:WHN

Gareth Thomas, President & CEO, comments: “Westhaven’s flagship Shovelnose Gold Property is ideally

situated, in close proximity to roads, power and infrastructure in a tier 1 mining jurisdiction. Production

contribution from both Franz and FMN provide valuable ounces that bring gold production forward in the

schedule resulting in payback of initial capital costs in just 2.1 years. Our intention is to continue to

advance this cornerstone project in parallel with our ongoing exploration efforts to further expand the

gold-silver mineral inventory on this highly prospective land package. The next steps towards rapidly

advancing development include further de-risking initiatives such as continued environmental baseline

studies, permitting requirements, along with other cost and technical requirements.”

The Company cautions that the results of the PEA are preliminary in nature and include Inferred Mineral

Resources that are considered too speculative geologically to have economic consideration applied to

them to be classified as Mineral Reserves. There is no certainty that the results of the PEA will be

realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

Preliminary Economic Assessment Highlights:

*Base case parameters of US$2,400 per ounce gold, US$28 per ounce silver and CDN$/US$ exchange rate of $0.72.

*All costs are in Canadian dollars unless otherwise specified.

 Robust financial metrics.

o Pre-tax Internal Rate of Return (“IRR”) of 56.3%; After-tax IRR of 43.2%.

o Low All-In Sustaining Cost (“AISC”) of $1,161/ounce (“oz”) (US$836/oz) gold equivalent

(“AuEq”).

o Low Cash Cost of $872 oz/AuEq (US$ 628/oz AuEq).

o Pre-tax Net Present Value (“NPV”6%) of $730 million (M) and After-tax NPV of $454M.

o Payback period from start of production year at 1.7 years pre-tax and 2.1 years after-tax.

o After-tax (NPV 6%) increases to $634M and After-tax IRR increases to 56.6% using spot

prices of US$2,900 gold and US$30 silver.

 Low capital-intensive development and operating costs.

o Total Preproduction Capital of $184M.

o Total Life of Mine (“LOM”) Capital Costs of $379M.

o Average operating cost of $142/ tonne processed.

o 92% of total stope mining is cost effective longitudinal and traverse longhole stoping, with

only 8% of total mining requiring cut and fill stoping.

 11.1-year mine life and ability to expand processing to accommodate satellite discoveries.

o 718,600 total Indicated ounces gold equivalent (“AuEq”) underground Mineral Resource

Estimate.

292,000 total Inferred ounces AuEq underground Mineral Resource Estimate.

o Production rate of 1,000 tonnes per day (“tpd”).

o Total payable metals of 637,000 oz gold (“Au”) and 3,562,000 oz silver (“Ag”).

o Average annual production of 56,000 oz Au peaking in year 7 at 68,000 oz Au.

Total mineralized rock production of 4,159,000 tonnes at 5.26 g/t Au and 32 g/t Ag.

o Metallurgical recoveries of 91.5% Au and 92.9% Ag.

 Community/stakeholder benefits.

o Total projected income taxes paid of $284M.

o Total projected British Columbia mineral taxes paid of $163M.

o More than 130 well-paying local full time jobs created during life of mine.

o Additional employment during construction phase.

o Indirect spin-off benefits during both construction and mine operations.

Mineral Resources, Updated PEA Preparation and Results

The previous public Mineral Resource Estimate (“MRE”) for the South Zone was carried out by P&E

Mining Consultants Inc. (“P&E”) with an effective date July 18, 2023. The current underground MRE is

reported herein. All drilling and assay data were provided by Westhaven, in the form of Excel data files.

The GEOVIA GEMS™ V6.8.4 database compiled by P&E for the February 28, 2025 MRE consisted of 355

surface drill holes, totalling 121,971 metres. A total of 145 drill holes (50,714 metres) were intersected

by the Mineral Resource wireframes used in this PEA.

P&E validated the Mineral Resource database in GEMS™ by checking for inconsistencies in analytical

units, duplicate entries, interval, length or distance values less than or equal to zero, blank or zero-value

assay results, out-of-sequence intervals, intervals or distances greater than the reported drill hole length,

inappropriate collar locations, survey and missing interval and coordinate fields. Some minor errors were

identified and corrected in the database. The QPs are of the opinion that the supplied database is

suitable for Mineral Resource estimation.

Block models were constructed using GEOVIA GEMS™ V6.8.4 modelling software and consist of separate

model attributes for estimated Au, Ag and AuEq grade, rock type (mineralization domains), volume

percent, bulk density, and classification. The Mineral Resource was classified as Indicated and Inferred

based on the geological interpretation, variogram performance and drill hole spacing. The QPs also

consider mineralization at the South, Franz and FMN Zones to be potentially amenable to underground

mining methods. The revised MRE used for this Updated PEA is reported with an effective date of

February 28, 2025 and is tabulated in Table 1.

Table 1

Shovelnose Underground Mineral Resource Estimate @ 1.3 g/t AuEq Cut-off (1-7)

Classification Zone Tonnes Au Contained

Au Ag Contained Ag AuEq Contained AuEq

(k) (g/t) (k oz) (g/t) (k oz) (g/t) (k oz)

Indicated

South 3,107 6.18 616.8 33.1 3,302.8 6.56 655.2

Franz 89 7.44 21.2 30.9 88.0 7.80 22.2

FMN 241 5.07 39.2 22.5 173.7 5.33 41.2

Total 3,437 6.13 677.2 32.3 3,564.5 6.50 718.6

Inferred

South 1,386 3.79 168.6 16.5 736.8 3.98 177.2

Franz 63 3.48 7.1 51.9 105.4 4.09 8.3

FMN 843 3.49 94.6 37.5 1,017.3 3.93 106.5

Total 2,292 3.67 270.3 25.2 1,859.5 3.96 292.0

1. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

2. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing,

or other relevant issues.

3. The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and must

not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could potentially be

upgraded to an Indicated Mineral Resource with continued exploration.

4. The Mineral Resources were estimated in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards

on Mineral Resources and Reserves, Definitions (2014) and Best Practices Guidelines (2019) prepared by the CIM Standing Committee on

Reserve Definitions and adopted by the CIM Council.

5. PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic

considerations applied to them that would enable them to be classified as Mineral Reserves, and there is no certainty that the PEA will be

realized.

6. The AuEq cut-off of 1.3 g/t was derived from costs of C$82/t mining, C$42/t processing and $18/t G&A. A USD:CDN exchange

rate of 0.72 along with US$2,400/oz Au and US$28/oz Ag with respective process recoveries of 91.5% and 92.9%.

7. The Au/Ag ratio used was 86:1.

A financial model was developed to estimate the Life of Mine (“LOM”) plan and considered only

underground mining of Mineral Resources at the South, Franz and FMN Zones. Other known gold-silver

mineralization at the Shovelnose Gold Property, currently being evaluated by Westhaven, are not

included.

The LOM plan covers a 13.1-year period (2 years pre-production and 11.1 years of production). Currency

is in Q1 2025 Canadian dollars unless otherwise stated. Inflation has not been considered in the

financial analysis.

The Updated PEA outlines a production mine life of 11.1 years with average annual production of 56,000

ounces gold and 312,000 ounces silver at average respective cash costs and all-in sustaining costs

("AISC") per ounce gold equivalent of $1,161(US$836). The PEA considers the payable recovery of

637,000 oz gold and 3,562,000 oz silver from an underground operation, at average respective mine

production grades of 5.26 g/t and 32 g/t.

Revenue

The commercially saleable product generated by the Project is a gold/silver doré. Westhaven would be

paid once the doré has been delivered to a smelter and refinery, off-site.

The NSR payables were based on the following parameters:

Dore Payable (Includes refining and smelting)

Au 99%

Ag 90%

The CDN$/US$ exchange rate used in the PEA is 0.72.

Subtotal Revenue

Au (US$) $1,529M

Ag (US$) $100M

Net revenue

CDN$ $2,201M

The revenue generation by the Shovelnose Project, on a yearly basis, is presented in Table 2.

Table 2

Summary of Base Case Total Revenue Generation

Item / Year Yr -1 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Total

Tonnes (k) 133.7 330.4 367.5 365.3 365.3 365.3 365.3 365.3 365.3 365.3 365.3 365.3 40.0 4,158.8

Grade (g/t) - Au 3.98 5.43 4.94 5.52 5.16 5.55 5.59 6.35 5.24 5.05 5.42 4.26 3.93 5.26

- Ag 27 26 73 32 25 29 36 32 23 25 29 23 25 32

Au koz Payable 15.5 52.2 52.8 58.7 54.8 59.0 59.4 67.6 55.8 53.8 57.6 45.3 4.6 637.2

Ag koz Payable 98.1 232.9 722.4 310.0 242.0 282.3 352.4 316.4 222.8 244.8 287.4 223.6 26.6 3,561.8

Subtotal Rev.-Au (US$)M 37.2 125.4 126.8 140.8 131.6 141.7 142.6 162.2 133.9 129.0 138.3 108.8 11.0 1,529.3

-Ag (US$)M 2.7 6.5 20.2 8.7 6.8 7.9 9.9 8.9 6.2 6.9 8.0 6.3 0.7 99.7

Subtotal Rev. (Cdn$) M 55.4 183.2 204.3 207.6 192.2 207.8 211.8 237.6 194.6 188.8 203.2 159.8 16.3 2,262.5

Net Royalty (Cdn$) M 5.9 4.6 5.1 5.2 4.8 5.2 5.3 5.9 4.9 4.7 5.1 4.0 0.4 61.1

Net Revenue (Cdn$) M 49.5 178.6 199.1 202.4 187.4 202.6 206.5 231.7 189.7 184.0 198.2 155.8 15.9 2,201.4

Note Yr = Year

The QPs have estimated the net revenues assuming Westhaven has taken advantage of available royalty

buy-outs. There is a 2% Net Smelter Return (“NSR”) royalty on the Shovelnose Gold Property held by

Franco-Nevada Corp. which Westhaven has the option to buy down to a 1.5% NSR for US$3M. There is a

2% NSR held by Osisko Gold Royalties Ltd. which Westhaven has the option to buy down to a 1% NSR for

$500,000.

Costs

Operating costs:

Total average cost $142/t processed

Cash Cost / AuEq oz (Cdn$/oz AuEq) $872/oz AuEq (US$628/oz)

All-in sustaining cost (“AISC”)(Cdn$/oz AuEq) $1,161/oz AuEq (US$836/oz)

Capital costs:

LOM $379M

Sustaining CAPEX $195M

LOM capital costs include the cost of all mine development; process plant, mine equipment; surface

infrastructure; underground infrastructure; a closure cost; a salvage credit; and a 20% contingency.

Stoping methods utilized are transverse longhole, longitudinal longhole and cut & fill. The average vein

widths to be mined are 16.2m, 6.6m and 3.0m respectively.

Mining unit costs by method are $143.81/t for transverse, $144.94 for longitudinal long hole, and

$142.82/t for cut & fill stoping.

The proportion of mining method during the life of mine is 65% longitudinal longhole, 27% for

transverse longhole mining and 8% cut and fill.

Table 3

Base Case Cash Flow Summary

ITEM DESCRIPTION / YEAR UNITS YR

- 2

YR

- 1

YR

1

YR

2

YR

3

YR

4

YR

5

YR

6

YR

7

YR

8

YR

9

YR

10

YR

11

YR

12 TTL

Production

kt 134 330 368 365 365 365 365 365 365 365 365 365 40 4,159

Au

(g/t) 3.9 5.4 4.9 5.5 5.2 5.6 5.6 6.4 5.2 5.1 5.4 4.3 3.9 5.3

Ag

(g/t) 27 26 73 32 25 29 36 32 23 25 29 23 25 32

Revenue M$ 50 179 199 202 187 203 206 232 190 18

4 198 156 16 2,201

Opex

Expensed Stope

Development (Contractor) M$ 11 6 11 13 9 2 6 2 9 3 9 5 1 88

Longitudinal LH Stoping M$ 1 3 3 2 3 3 2 2 2 3 3 4 0.4 30

Transverse LH Stoping M$ 1 2 1 1 2 2 2 1 12

Cut and Fill Stoping M$ 1 2 0.2 1 0.1 1 1 1 1 0.1 7

Mine G&A M$ 3 5 5 5 5 5 5 5 5 5 5 5 1 62

Paste Backfill M$ 1 1 2 3 3 3 3 3 3 3 3 3 1 34

Process Plant M$ 6 14 15 15 15 15 15 15 15 15 15 15 2 173

Transport and Place

Tailings M$ 1 12 2 1 1 1 1 1 1 1 1 1 0.1 12

U/G Ore Haulage M$ 1 4 6 8 8 8 8 9 8 7 8 8 1 84

Surface Ore Haulage M$ 1 1 1 3

Backhaul Paste Backfilll to

FMN M$ 0.1 0.4 0.2 1

Stopckpile Rehandling M$ 1 1 1 1 1 1 1 1 1 1 1 1 0.1 14

G&A M$ 6 6 6 6 6 6 6 6 6 6 6 1 71

Total Opex with

Contingency M$ 25 45 55 58 53 47 50 47 4 47 53 50 6 589

Capex

Mine Development

(Contractor) Waste M$ 19 21 38 16 9 6 1 6 1 8 3 126

Process Plant M$ 50 25 4 4 4 4 3 94

Owner's Cost M$ 3 5 8

Mining Equipment M$ 11 7 7 2 2 12 1 5 2 3 4 54

U/G Infrastructure M$ 1 2 1 1 1 1 1 1 1 1 1 13

Surface Infrastructure M$ 48 5 2 2 5 2 5 2 72

EPCM M$ 9 10 19

Closure & Salvage M$ 5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 -16 -6

Total Capex with

Contingency M$ 62 122 35 52 18 15 4 28 4 18 4 21 10 -16 379

Table 3

Base Case Cash Flow Summary

ITEM DESCRIPTION / YEAR UNITS YR

- 2

YR

- 1

YR

1

YR

2

YR

3

YR

4

YR

5

YR

6

YR

7

YR

8

YR

9

YR

10

YR

11

YR

12 TTL

Taxes

Income Tax M$ 11 25 24 23 30 31 38 27 28 30 21 -4 284

Mineral Tax M$ 0 3 3 12 16 20 17 24 16 18 17 13 3 163

Total Taxes M$ 0 14 28 37 39 50 48 62 43 46 47 34 0 447

After-Tax Cash Flow M$ -62 -97 85 63 90 80 102 80 118 75 87 77 62 26 785

After-Tax Cumulative Cash Flow M$ -62 -160 -75 -11 78 158 260 340 458 533 62

0 697 759 785

After-tax IRR % 43.2

After-tax NPV @ 6% M$ 454

Cash Flow Sensitivity Analysis

The following after-tax cash flow analysis was completed:

Net Present Value (“NPV”) (at 5%, 6%, 7%, 8%, 9% and 10% discount rates).

Internal Rate of Return (“IRR”).

Payback period.

The summary of the results of the cash flow sensitivity analysis is presented in Table 4

TABLE 4

BASE CASE CASH FLOW SENSITIVITY ANALYSIS

Description Discount Rate Units Value

Undiscounted After-Tax CF 0% (M$) 785

Internal Rate of Return % 43.2

After-Tax NPV at

5% (M$) 496

Base Case 6% (M$) 454

7% (M$) 415

8% (M$) 380

9% (M$) 348

10% (M$) 319

After-Tax Total Project Payback (including pre-production) Years 4.1

The Project was evaluated on an after-tax cash flow basis which generates a net undiscounted cash flow

estimated at $785M. This results in an after-tax IRR of 43.2% and an after-tax NPV of $454 M when

using a 6% discount rate. In the base case scenario, the Project has a payback period of 4.1 years from

the start of the Project. The average life-of-mine cash cost is $872/oz AuEq (US$628/oz AuEq), at an

average operating cost of $142/t processed. The average life-of-mine all-in sustaining cost (“AISC”) is

estimated at $1,161/oz AuEq (US$836/oz AuEq).

Sensitivity Analysis

Project risks can be identified in both economic and non-economic terms. Key economic risks were

examined by running cash flow sensitivities to: gold metal price; silver metal price; gold process plant

head grade; gold metallurgical recovery; operating costs; and capital costs.

Each of the sensitivity items were varied up and down by 10% and 20% to assess the effect they would

have on the NPV at a 6% discount rate. The value of each parameter, at 80%, 90%, 100% base case,

110% and 120%, is presented in Table 5.

Table 5

NPV Sensitivity Parameter Values

Parameter 80% 90% 100% 110% 120%

Au Metal Price US$/oz 1,920 2,160 2,400 2,640 2,880

Ag Metal Price US$/oz 22.40 25.20 28.00 30.80 33.60

Au Head Grade g/t 4.21 4.73 5.26 5.79 6.31

Au Met Recovery % N/A 82.4% 91.5% N/A N/A

Capex $M 304 342 379 417 455

Opex $M 471 530 589 648 707

The resultant after-tax NPV @ 6% values of each of the sensitivity parameters at 80% to 120% are

presented in Table 6.

Table 6

After-Tax NPV Sensitivity to Base Case at 6% Discount Rate (M$)

Parameter 80% 90% 100% 110% 120%

Au Metal Price 284 369 454 538 623

Ag Metal Price 442 448 454 459 465

Au Head Grade 284 369 454 538 623

Au Met Recovery N/A 369 454 N/A N/A

Capex 515 484 454 423 392

Opex 502 478 454 429 405