Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

WEC.V ·

Sprott Resource Holdings Inc. Reports 2019 Third Quarter Results and Updates 2019 Guidance

Financials

Sprott Resource Holdings Inc. Reports 2019 Third Quarter Results and Updates

2019 Guidance

(all amounts expressed in US dollars)

TORONTO, Nov. 11, 2019 -- (TSX: SRHI) - Sprott Resource Holdings Inc. (" SRHI" or the " Company") today announced its

operating and financial results for the three and nine months ended September 30, 2019. The Company's principal operating

business is its 70% equity interest in the Chilean producing copper mine Minera Tres Valles (" MTV"). The Company's financial

statements and management's discussion and analysis (" MD&A") are available at www.sprottresource.com and

www.sedar.com.

“MTV continued to invest in growth projects during the third quarter,” stated Michael Harrison, Interim President and CEO of

SRHI. “MTV’s Don Gabriel open pit mining operation hit target in the third quarter, and MTV is adding the target salt dosage to

the crushed sulphide material. MTV increased ore crushed by 30% to 404,000 tonnes despite some unplanned downtime at

our crusher that resulted in higher average crush size. Mineral production from Don Gabriel has increased from 1,500 tonnes

per day in the first quarter of 2019 to over 2,900 tonnes per day in the third quarter. Total open pit copper grade increased to

0.70% from 0.55% from prior quarter, and we delivered 29% more copper to the heap leach pads compared to the first quarter

of 2019.”

“Our copper production dropped from the prior quarter to 1,646 tonnes, yet MTV increased inventory of recoverable copper in

the heap leach pad by 1,000 tonnes. The majority of this inventory build was caused by the unplanned crusher downtime and

the resulting higher average crush size that then required an increased curing period of salt in the heap leach pad. Unit costs

were higher in Q3, resulting from lower copper production, an increased strip ratio and higher consumable costs, and when

combined with the lower copper price, negatively affecting cash flow. This resulted in weaker financial results including a gross

loss of $4.3 million for the quarter, a net loss of $9.0 million and break-even Adjusted EBITDA. With the pre-payment and

offtake financing taking longer than anticipated to finalize, a lower grade production profile in the first half of the year, and larger

than anticipated inventory build, we are revising our full year 2019 guidance. However, with the year-to-date inventory build

nearing $11 million and full dosing of salt in place, initial results in October are positive including record cathode production of

655 tonnes. The Company expects improved results in the fourth quarter of this year.”

“We have received the detailed engineering report, and we have selected our underground contractor for the Papomono

Massive deposit. We signed a mandate letter with Anglo American Marketing Limited and Kimura in August that will provide

net new financing of $20 million (“ Facility”) and a new offtake arrangement (“Offtake”), and we continue with the drafting of

documentation, with the aim of receiving funding in the fourth quarter.”

“Although our production was not interrupted by the recent nationwide civil unrest in Chile, we were not unaffected; we had a

security incident at the mine on November 3 as presented in our news release of that day which resulted in a security guard

being seriously injured and another individual being fatally shot. We continue to work with our community partners to ensure

we are a good neighbour. We completed another LTI-free quarter, and continue to emphasize safety training and awareness,”

concluded Michael Harrison.

Revised 2019 Guidance

SRHI's updated guidance for copper production, cash cost per pound produced and capital expenditures is set out below

together with the original guidance amounts. The revised guidance reflects several factors both positive and negative, which

collectively resulted in a reduced forecast for the remainder of 2019.

1. For the first half of 2019, at our Don Gabriel mine, 70% of the material delivered to the crushing plant was not in our

reserve mine plan. Blast-hole drill assays determined that the material outside of the reserve mine plan was ore-grade

material, and was mined and processed. The benefit of additional material above cut-off grade reduces reserve

depletion, and is specific to the outer halo of the Don Gabriel deposit, although negatively impacts contained copper

production due to its lower grade, and reduces precision on forecasting production;

2. Mechanical issues, specifically the tertiary and quaternary crusher downtimes resulted in suboptimal crush size for the

application of the Salt Leach (defined below) extending the recovery curve;

3. Operating costs have increased through the year largely due to increasing input costs for diesel and reagents and

elevated consumption of acid in 2019;

4. The delay in securing the Facility negatively impacted the deployment of capital expenditures and advancement of the

current mine plan; and,

5. Lower equipment availability by contractors created compounding operational issues.

Original Guidance

Revised Guidance

November 2019

Provided January

2019

  Cu production (tonnes) 7,000 - 7,400 8,250 - 8,750

  Cu production (millions of pounds) 15.4 - 16.3 18.2 - 19.3

  Cash cost per pound produced 1 $2.50 - $2.80 $2.20 - $2.50

  Capital expenditures ($ millions) $15 - $17 $25-$30

1  See Non-IFRS Performance Measures

2  Guidance is based on certain estimates and assumptions, including but not limited to, mineral reserve estimates, grade and

continuity of interpreted geological formations and metallurgical performance. Please refer to the technical report prepared by

AMEC Foster Wheeler, a Wood company, in respect of the Project filed on December 14, 2018 and the Company’s SEDAR

filings for complete risk factors.

Operational Update

  Three months ended

Nine

months

ended

Eight months

ended

Operating information

Sept. 30,

2019

Sept. 30,

2018

Sept. 30,

2019

Sept. 30,

2018

Copper (MTV Operations)        

Total ore mined (thousands of tonnes) 345  254  897  502 

Total waste mined (thousands of tonnes) 1,442  552  4,518  880 

Ore Processed (thousands of tonnes) 404  313  1,069  670 

Grade (% Cu) 0.73% 0.74% 0.66% 0.73%

Cu Production (tonnes) 1,646  1,462  5,176  3,785 

Cu Production (thousands of pounds) 3,628  3,223  11,412  8,344 

Inventory build ($000s) 2,787  3,036  10,809  4,984 

Cash cost of copper produced 1 (USD per pound) $ 2.77  2.07  $ 2.61  $ 2.35 

Realized copper price (USD per pound) $ 2.51  2.61  $ 2.66  $ 2.96 

1   See Non-IFRS Performance Measures

The Company has previously communicated its focus for MTV; the implementation of the Salt Leach, the expansion of its Don

Gabriel open pit mine and the development and expansion of its Papomono underground mine.

Salt Leach Project Nears Completion - Full Dosage Application in Process

The implementation of chloride leaching (" Salt Leach ") involves adding rock salt (NaCl) in the agglomeration stage of the

crushing plant allowing the mixed sulphide and oxide material to cure in the heap for 15 to 30 days before application of

sulphuric acid. The oxidation of sulphide material in the heaps is expected to improve copper recoveries by approximately 8%,

reduce acid consumption, and decrease the leach time by approximately 40%. These changes are expected to reduce cash

costs and improve MTV’s working capital position. The construction of the salt storage and dosing system to commence the

Salt Leach was completed in June and MTV began adding salt at low levels near the end of the second quarter, nearly three

months ahead of schedule. In mid-October, additional Salt Leach infrastructure was completed and the maximum dosages of

salt have now begun. The total cost of the Salt Leach project is in line with the March 2018 pre-feasibility NI 43-101 technical

report (the "Technical Report ") estimate of $7.1 million. In October, the Company has already seen an increase in production

and expects this to continue with the intention to grow copper production to reach plant capacity of 40 million pounds of

copper cathodes per year.

Quarterly production including continued expansion at Don Gabriel

MTV produced 3.6 million pounds of 99.99% pure copper cathodes at a cash cost of $2.77 per pound of copper produced (see

Non-IFRS Financial Measures) and sold 3.6 million pounds at an average sales price of $2.51 per pound of copper in the

quarter. MTV had approximately $2.0 million of finished goods inventory at September 30, 2019.

Total material crushed in the first three quarters increased to 1.1 million tonnes as a result of increased open pit operations,

primarily from Don Gabriel, Cumbre and the Rajo Norte open pit mines. This compares to 0.7 million tonnes in the prior year's

eight-month period. Tonnes crushed in the third quarter of 2019 of 404 thousand tonnes set a new quarterly record for MTV.

Don Gabriel is the largest contributor of ore to MTV and together with ancillary deposits, ore movement for the first time

increased to more than 100,000 tonnes per month. The Rajo Norte and Cumbre open pit mines are two of the ancillary

deposits that contribute to copper production as shown in the PEA case of the October 2018 Technical Report and

demonstrates the flexibility in MTV’s operations. Open pit ore grade has also increased from 0.67% for the three months

ended September 30, 2018 to 0.70% for the three months ended September 30, 2019.

Ore production from the Papomono underground mine remained stable at approximately 500 tonnes per day, extracting ore

from resource blocks adjacent to the Papomono Massive deposit in advance of future block caving operations. A large

component of ore production growth in 2020 will come from the higher-grade Papomono Massive deposit. MTV plans to extract

ore using the incline block caving method, which is expected to ultimately increase underground production beyond 2,000

tonnes per day halving unit-mining costs. Detailed engineering is completed and construction will begin upon closing of the

Facility.

Cost per pound produced increased to $2.77 for the three months ended September 30, 2019 compared to $2.07 for the

comparable period of last year. The increase in cost per pound is driven by an increase in the strip ratio (2.5:1 in the third

quarter of 2019 compared to 0.8:1 in the third quarter of 2018) as well as the cost and consumption of peroxide, salt and

sulphuric acid. Over the past year, sulphuric acid production in Chile was significantly lower with the major smelters in Chile

undergoing retrofit to meet new emission standards. At the end of 2018, MTV entered into a one year contract to ensure

delivery from suppliers. MTV understands the smelters are back on line, and spot prices are trending downwards. Throughout

the implementation of the Salt Leach, new costs have also been incurred for higher peroxide on initial implementation as well

as the added cost of salt over the quarter. However, we expect the consumption of sulphuric acid to decrease as the Salt

Leach reaches its full potential. For the nine months ended September 30, 2019, cost per pound produced increased to $2.61

from $2.35 from the comparable period of last year for the same reasons as discussed above.

During the quarter, MTV completed additional Salt Leach infrastructure that allowed for an increased dosage of salt to its

sulfide ore. Although a positive event, MTV also encountered mechanical issues during its most recent quarter that negatively

affected both the processing and curing, and recovery time of copper. In separate instances, both the tertiary and quaternary

crushers were off-line resulting in periods of downtime and suboptimal crush size for the Salt Leach process that have now

been addressed to significantly reduce the likelihood of recurrence. These third quarter events contributed to the Company's

revised guidance for the remainder of 2019.

Capital cost, financing and Papomono underground development and expansion

The Company continued funding the expansion projects at MTV including $3.8 million of capital expenditures primarily for

waste stripping at Don Gabriel and costs for the Salt Leach project. During the quarter, 1.4 million tonnes of waste and pre-

strip were moved compared to 0.6 million tonnes moved in the prior year’s quarter illustrating MTV’s execution of its mine

expansion.

Capital expenditures year-to-date of $10.6 million represent front-caving development costs, capitalized stripping costs, Salt

Leach project costs and purchases of equipment.

With the Facility expected to close in the fourth quarter of this year, MTV’s capital expenditure program will accelerate in 2020

when the Papomono underground development and expansion is scheduled to begin.

SRHI and MTV previously announced that it had entered into an investment committee approved mandate letter with Anglo

American Marketing Limited (" Anglo American ") and a fund under the investment management of Kimura Capital LLP

("Kimura") to provide a US$45 million secured prepayment facility and offtake agreement to be utilized for the expansion of

the MTV copper project. The Facility will be used to replace the existing revolving credit facility managed by Kimura and to

repay a portion of debt financing previously provided by the Company to MTV resulting in net new debt financing of

approximately $20 million to MTV. The Facility and Offtake remains subject to satisfaction of customary conditions and

completion of documentation and is expected in the fourth quarter of 2019.

Health and safety

MTV completed another quarter without a Lost-Time Incident (“ LTI”). In January 2019, an employee did suffer an LTI, and is

expected to fully recover. The Company and MTV devote considerable time and effort to ensure that our workers and

contractors return safely to their families after each shift. Our safety statistics are below country and peer averages, and MTV

pro-actively engages in education and assessment to achieve a goal of zero lost-time incidents. MTV’s Injury Frequency rate

was 1.5 per million hours worked at the end of the third quarter.

Community and environment

MTV works with the local communities, and the MTV Foundation continued the funding of projects agreed by the MTV

Foundation board, which is largely composed of community representatives to help MTV understand the true needs of its

neighbors, such as starting an eco-friendly cooperative at a local school.  MTV’s ore purchase program ensures support from

local miners, buying ore from over 26 providers and supporting the development of over 300 small-scale miners through local

mining unions. Furthermore, MTV promotes strong ties with authorities by offering site visits and frequently attending events.

Financial Results

  Three months ended Nine months ended

Financial information (in thousands)

Sept. 30,

2019

Sept. 30,

2018

Sept. 30,

2019

Sept. 30,

2018

Revenue 1 $ 9,650 $ 6,039 $ 26,336 $ 21,812 

Gross loss 1 $ (4,259) $ (1,449) $ (8,922) $ (1,191)

Net loss from continuing operations $ (8,619) $ (1,149) $ (23,949) $ (16,085)

Net loss from discontinued operations 1 $ (374) $ (496) $ (2,428) $ (2,419)

Net loss for the period $ (8,993) $ (1,645) $ (26,377) $ (18,504)

Adjusted EBITDA from continuing operations 2 $ 51 $ (1,712) $ (4,683) $ (2,454)

Gain (loss) on portfolio investments $ (3,419) $ 2,597 $ (8,578) $ (9,972)

Cash provided by (used in) operating activities before working capital

changes $ 109

$ (1,665) $ (4,497) $ (2,161)

1   Comparative figures in the nine months ended column are for the period February 1, 2018 to September 30, 2018

2   See Non-IFRS Financial Measures

Financial results summary

Revenues of $9.7 million were generated predominantly from the sale of copper cathodes and tolling charges for mineralized

material supplied by ENAMI with approximately $2.0 million of finished goods inventory at September 30, 2019. This is largely

driven by an increase in copper cathodes sold during the three months ended September 30, 2019 of 1,653 tonnes compared

to 1,004 tonnes in the same period of 2018. This was partially offset by a lower realized copper price.

The Company reported a quarterly net loss of $9.0 million or $(0.26) per share. This result includes a net loss from

discontinued operations of $0.4 million and a loss on portfolio investments of $3.4 million. Adjusted EBITDA (see Non-IFRS

Financial Measures) from continuing operations for the quarter was $51 thousand or $0.00 per share. In the third quarter of

2018, the Company reported a net loss of $1.6 million or $(0.05) per share and Adjusted EBITDA from continuing operations of

negative $1.7 million or $(0.05) per share.

In the first three quarters of 2019, the Company reported a net loss of $26.4 million or $(0.77) per share. This result includes a

net loss from discontinued operations of $2.4 million and a loss on portfolio investments of $8.6 million. Adjusted EBITDA (see

Non-IFRS Financial Measures) from continuing operations for the nine months ended September 30, 2019 was negative $4.7

million or $(0.14) per share. In the first three quarters of 2018, the Company reported a net loss of $18.5 million or $(0.55) per

share and Adjusted EBITDA from continuing operations of negative $2.5 million or $(0.07) per share.

In the third quarter of 2019, cash provided by operating activities was $2.5 million (cash provided of $109 thousand before

changes in non-cash components of working capital), as compared with the third quarter of 2018 when cash used by operating

activities was $1.5 million (cash used of $1.7 million before changes in non-cash components of working capital).

In the first three quarters of 2019, cash used by operating activities was $3.4 million (cash used of $4.5 million before changes

in non-cash components of working capital), as compared with the first three quarters of 2018 when cash used by operating

activities was $11.9 million (cash used of $2.2 million before changes in non-cash components of working capital).

As the operations at MTV continue to grow and expand, significant costs are incurred approximately one year before the

leaching process for the copper cathodes to be sold is completed. With the Salt Leach now implemented, this period is

expected to decrease by almost 50%. The Company has invested significant working capital in the past year to expand its

operations, including a significant build in inventory that is expected to slowly and steadily increase copper cathode production

in the future. Inventory as at September 30, 2019 was $31.4 million compared to $20.6 million as at December 31, 2018. With

the mining operation continuing to expand and currently operating at less than 50% capacity, the Company's gross profit is

expected to improve as the operation ramps up in 2020 and is brought to full capacity in early 2021.

The gross loss for the three months ended September 30, 2019 was $4.3 million. This is largely generated by depreciation

expense of $3.0 million and an inventory write-down of $1.2 million which are both non-cash items. For the three months ended

September 30, 2019, the Company continued to be in an expansion phase of operations with a high cost environment and,

coupled with a decreasing copper price environment, resulted in a gross loss for the period. In addition to the increase in costs

in 2019 previously mentioned, the expansion of the project resulted in increased depreciation expense primarily from the pre-

strip investment at Don Gabriel.

Cash position

Cash and cash equivalents decreased to $10.7 million at September 30, 2019 from $13.5 million at December 31, 2018 as the

Company continues to support the operations at MTV that have resulted in an inventory build of $10.8 million and capital

expenditures of $10.6 million during the nine months ended September 30, 2019.

In late September 2019, Kimura extended a further $5 million in short-term financing to MTV in anticipation of closing the

Facility. MTV's revolving credit facility with Kimura is now $20 million and is expected to be rolled into the Facility upon closing

as Kimura will continue as one of two lenders for the Facility.

The net additional debt financing is expected to be approximately $20 million to support MTV's planned mine expansion. The

majority of this Facility will be long-term in nature providing the necessary capital flexibility to MTV.

Investment portfolio divestment

The Company continues to work on its divestment strategies for the non-core assets. During the quarter, the Company

completed selling its holdings in InPlay Oil Corp. and Virgina Energy Resources Inc. Management expects that further non-

core investments or businesses could be divested during the remainder of 2019 but now believes the majority of its remaining

non-core investments or businesses will be divested in 2020.

Outlook and Growth Initiatives

The Company is focused on executing the three expansion projects identified in the Technical Report.

The expansion of Don Gabriel began in the second half of 2018 and has been supported by the Company's working capital and

MTV's operational cash flows. This expansion has progressed well with $1.9 million of capital expenditures incurred in 2018 for

pre-stripping of phases 2, 3 and 5 (7 mining phases in total). In 2019, a further $4.5 million of expenditures were incurred year-

to-date in phases 4, 5, 6 and 7. Starting in the first half of 2018, ore movement at Don Gabriel has more than tripled to over

90,000 tonnes per month. Ore production at Don Gabriel for the three months ended September 30, 2019 was 25% higher than

the three months ended June 30, 2019 and 45% higher than the three months ended September 30, 2018.

The Salt Leach project development and construction commenced in mid-2018, following the recommendations outlined in a

Preliminary Feasibility Study filed in March 2018. Capital expenditures of approximately $7.1 million were defined for the Salt

Leach and this project was implemented ahead of schedule and is in line with the March 2018 pre-feasibility Technical Report

estimate utilizing the Company's working capital and MTV's operational cash flows to date. Preliminary results are supportive

of the expected increase in recoverable copper, reduced leaching time and reduced acid consumption. Mechanical issues

during the third quarter interrupted the initial leach cycle on the first ore under Salt Leach. Production for October has already

started to demonstrate positive results with production of 655 tonnes which is a monthly production record for MTV.

As outlined in the Technical Report, the development and construction of Papomono Massive and ancillary deposits provides

for $21 million in capital expenditures over 18 months. Although some of this amount has been incurred, the majority of these

capital expenditures is to be funded by the Facility. The Facility and Offtake are expected to be in place in the fourth quarter of

this year and remain subject to satisfaction of customary conditions and completion of documentation.

Upon MTV completing the aforementioned capital projects, cash flows generated from this expansion should provide MTV the

ability to exploit the exploration upside of its significant land package of over 44,334 hectares of mineral rights and more than

100 copper occurrences identified that require more exploration effort.

MTV commenced an exploration drill program in the quarter. Initial results were encouraging in new areas, however deeper drill

holes under Papomono Massive failed to explain the geophysical anomalies encountered. Further exploration at this area will

be pursued at a later time as we focus our efforts on near to medium term exploration targets.

In October 2019, unrest in Chile gained international attention and was country-wide. Vandalism and looting were reported

throughout the country, including in mining jurisdictions. MTV reported one incident of minor damage that resulted in no harm

to its employees and no impact to its operations.

On February 11, 2019, the Board of Directors of the Company formed a Special Committee of the Board comprised solely of

the Company's four Independent Directors chaired by Terry Lyons, the current Chairman of the Board. The Special Committee

continues to review and evaluate potential measures to address the Company's market valuation. This review is comprehensive

and is evaluating all measures to maximize shareholder value. The Special Committee has engaged financial and legal

advisors to assist in its evaluation.

Conference Call and Webcast Details

SRHI will hold a conference call and webcast to review its results for the three and nine months ended September 30, 2019 on

Monday, November 11, 2019 at 4:00pm Toronto time. To listen to the call, please dial (855) 458.4215 ten minutes prior to the

scheduled start of the call and provide conference ID:7089107. A taped replay of the conference call will be available

until Monday, November 18, 2019 by calling (855) 859.2056. The conference call will be webcast at  www.sprottresource.com

and https://edge.media-server.com/mmc/p/h4r5qcsm

Qualified Persons

Scientific or technical information in this press release relating to MTV is based on information prepared by Dr Antonio

Luraschi, RM CMC, Manager of Metallurgic Development and Senior Financial Analyst, Wood; Mr Sergio Navarrete, RM CMC,

Mining Engineer, Wood; Mr Alfonso Ovalle, RM CMC, Mining Engineer, Wood; Mr Michael G. Hester, FAusIMM, Vice

President and Principal Mining Engineer, Independent Mining Consultants, Inc.; Mr Enrique Quiroga, RM CMC, Mining

Engineer, Q&Q Ltda; Mr Gabriel Vera, RM CMC, Metallurgical Process Consultant, GVMetallurgy; and Mr Sergio Alvarado,

RM CMC, Consultant Geologist, General Manager and Partner, Geoinvestment Sergio Alvarado Casas E.I.R.L., all of whom

are independent “Qualified Persons” as such term is defined in National Instrument 43-101 – Standards of Disclosure for

Mineral Projects. The Technical Report was filed by SRHI on SEDAR on December 14, 2018. Readers are encouraged to read

the Technical Report in its entirety.

Notes on Preliminary Economic Assessments

Please note that the PEA Case is preliminary in nature, that it includes inferred mineral resources that are considered too

speculative geologically to have the economic considerations applied to them that would enable them to be categorized as

mineral reserves, and there is no certainty that the PEA Case will be realized. Mineral resources that are not mineral reserves

do not have demonstrated economic viability.

About MTV

MTV is an operating mining complex located 300 kilometers northeast of Santiago, Chile in Region IV near the town of

Salamanca. MTV comprises two main deposits: Papomono (underground) and Don Gabriel (open pit). The mine is currently

operating and producing high-grade copper cathode. The mine has significant infrastructure in place with a crushing and

processing plant with nameplate capacity of 7,000 and 6,000 tonnes per day, respectively. The plant is designed to produce

up to 18,500 tonnes per annum of LME Grade 99.999% copper cathodes. For more information about MTV, please

visit http://www.mineratresvalles.com.

About Sprott Resource Holdings Inc.

SRHI acquires and grows a portfolio of cash-flowing businesses and businesses expected to cash flow in the natural resource

sector. Based in Toronto, SRHI is part of the Sprott Group of Companies and seeks to deploy capital to provide our investors

with exposure to attractive commodities. For more information about SRHI, please visit www.sprottresource.com.

Non-IFRS Financial Measures

"Cash costs", "Adjusted EBITDA" and "Working Capital" are non-IFRS financial performance measures. Further details on non

-IFRS measures are provided in the MD&A accompanying SRHI financial statements filed from time-to-time on SEDAR at

www.sedar.com.

Cautionary Statement Regarding Forward-Looking Information

Certain statements in this news release, contain forward-looking information (collectively referred to herein as the " Forward-

Looking Statements ") within the meaning of applicable Canadian securities laws. The use of any of the words "expect",

"anticipate", "continue", "estimate", "may", "will", "project", "should", "believe", "plans", "intends" and similar expressions are

intended to identify Forward-Looking Statements. In particular, but without limiting the foregoing, this news release contains

Forward-Looking Statements pertaining to: expectations regarding production growth; expectations regarding the MTV mine

expansion, including the anticipated expansion methods, costs, timing and the benefits derived from the expansion;

expectations regarding the costs, timing and benefits of the Salt Leach; activity in zones with lower strip ratios which will help

boost production and reduce unit costs; maintaining and increasing levels of production to grow copper production to reach

plant capacity of 40 million pounds of copper cathodes per year; continued ramp up of waste mining activity; material reduction

in operating costs; growth initiatives; future block caving efforts and the expected benefits therefrom; expectations regarding

the timing of permit approvals; securing long-term debt and offtake financing from Anglo American and Kimura to fund growth

initiatives on the terms and conditions provided above; expectations regarding the investment portfolio divestment; the

Company's outlook, including its 2019 guidance for MTV and expected improved results for the fourth quarter of 2019; the

capital expenditure program for MTV; mineral resource and mineral reserve estimates; the Technical Report; continued unrest

in Chile; and general business and economic conditions.

Although SRHI believes that the Forward-Looking Statements are reasonable, they are not guarantees of future results,

performance or achievements. A number of factors or assumptions have been used to develop the Forward-Looking

Statements, including: there being no significant disruptions affecting the development and operation of MTV; the availability of

certain consumables and services and the prices for power and other key supplies being approximately consistent with

assumptions in the Technical Studies; labour and materials costs being approximately consistent with assumptions in the

Technical Studies; fixed operating costs being approximately consistent with assumptions in the Technical Studies; permitting

and arrangements with stakeholders being consistent with current expectations as outlined in the Technical Studies; certain

tax rates, including the allocation of certain tax attributes, being applicable to MTV; the availability of financing for MTV’s

planned development activities; assumptions made in mineral resource and mineral reserve estimates and the financial

analysis based on the mineral reserve estimate and in the case of the PEA, the mineral resource estimate, including (as

applicable), but not limited to, geological interpretation, grades, commodity price assumptions, metallurgical performance,

extraction and mining recovery rates, hydrological and hydrogeological assumptions, capital and operating cost estimates,

and general marketing, political, business and economic conditions. Actual results, performance or achievements could vary

materially from those expressed or implied by the Forward-Looking Statements should assumptions underlying the Forward-

Looking Statements prove incorrect or should one or more risks or other factors materialize, including: (i) possible variations in

grade or recovery rates; (ii) copper price fluctuations and uncertainties; (iii) delays in obtaining governmental approvals or

financing; (iv) risks associated with the mining industry in general (e.g., operational risks in development, exploration and

production; delays or changes in plans with respect to exploration or development projects or capital expenditures; the

uncertainty of estimates and projections relating to mineral reserves, production, costs and expenses; and labour, health,

safety and environmental risks) and risks associated with the other portfolio companies' industries; (v) performance of the

counterparty to the ENAMI Tolling Contract; (vi) risks associated with investments in emerging markets; (vii) general

economic, market and business conditions; (viii) market volatility that would affect the ability to enter or exit investments; (ix)

failure to secure financing in the future on terms acceptable to the Company, if at all; (x) commodity price fluctuations and

uncertainties; (xi) those risks disclosed under the heading "Risk Management" in SRHI’s Management’s Discussion and

Analysis for the three-months ended June 30, 2019; and (xii) those risks disclosed under the heading "Risk Factors" or

incorporated by reference into SRHI’s Annual Information Form dated March 6, 2019.  See also the cautionary language under

“Notes on Preliminary Economic Assessments” above. The Forward-Looking Statements speak only as of the date hereof,

unless otherwise specifically noted, and SRHI does not assume any obligation to publicly update any Forward-Looking

Statements, whether as a result of new information, future events or otherwise, except as may be expressly required by

applicable Canadian securities laws.

Cautionary Note to United States Investors Concerning Estimates of measured, indicated and inferred mineral

resources

This news release may use the terms "measured", "indicated" and "inferred" mineral resources. United States investors are

advised that while such terms are recognized and required by Canadian regulations, the United States Securities and

Exchange Commission does not recognize them. "Inferred mineral resources" have a great amount of uncertainty as to their

existence, and as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral

resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not

form the basis of feasibility or other economic studies. United States investors are cautioned not to assume that all or any part

of measured or indicated mineral resources will ever be converted into mineral reserves. United States investors are also

cautioned not to assume that all or any part of an inferred mineral resource exists or is economically or legally mineable.

For further information:

Michael Harrison

President and CEO

T: (416) 943-4995

E: [email protected]

Source: Sprott Resource Holdings Inc.