Drill Results

Wesdome Announces Exploration Drilling at Eagle River Continues to Expand

311 And 7 Zones and the Recently Discovered Falcon Zones

TORONTO, June 13, 2019 -- Wesdome Gold Mines Ltd. (TSX: WDO) (“Wesdome” or the “Company”) today announces results

from the ongoing surface and underground exploration drilling program at the Company’s wholly-owned Eagle River Mine in

Wawa, Ontario.

Mr. Duncan Middlemiss, President and CEO commented, "We are pleased with our ongoing exploration efforts at the Eagle

River Mine, in particular the continued expansion of the 7 East and 311 West zones that are proximal to existing development

and infrastructure.  We have repositioned the underground drills to continue drilling the extensions of these zones and expect

to include the results into the existing resource base at year end. We are also pleased with the ongoing surface drilling results

at the recently discovered Falcon zones, where there exists good potential to define higher grade and wider zones of gold

mineralization that would be near mine infrastructure. The objective is to continue our resource definition efforts in this area

that has high probability to be included in future mine production and ultimately augment production rates in the medium

term."

“We remain committed to aggressive exploration utilizing four underground drills and one, increasing to two surface drills in

order to identify additional resources and workplaces for increased future production profiles.”

Underground Exploration Drilling

The 2019 exploration program encompasses 51,000 metres (“m”) of underground exploration drilling and 43,000 m of definition

drilling using 4 drills. These have been focused primarily to extend the 7 and 300 zones, and one underground drill has been

dedicated to exploring new parallel zones of mineralization in the eastern half of the mine diorite, that remains largely under

explored (see Figure 1).

No. 7 East Zone

Capped Assay Highlights from Drilling (Table 1 and Figure 2):

Hole 750-E-59: 13.9 g/t Au cut over 4.9 m true width

Hole 750-E-63: 18.0 g/t Au cut over 2.2 m true width

Hole 750-E-76: 30.8 g/t Au cut over 1.5 m true width

*Assays cut to 125 g/t Au

No. 311 West Zone

Capped Assay Highlights from Drilling (Table 1 and Figure 3):

Hole 844-E-253: 27.0 g/t Au cut over 3.8 m true width

Hole 844-E-259: 8.9 g/t Au cut over 10.1 m true width

Hole 844-E-242: 22.1 g/t Au cut over 1.6 m true width

*Assays cut to 60 g/t Au

New Parallel Zones within eastern portion of mine diorite

Initial limited drilling from the 758 m-level in the eastern half of the mine diorite previously intersected what is interpreted to be

parallel zones north of the past producing 6 and 8 zones and could be the possible extensions of the parallel 7 zone and 300

zone structures being mined along the western portion of the mine diorite. Both of these parallel zones are open up and down

plunge and along strike and remain a focus for 2019 underground drilling.  

Surface Exploration Drilling

Earlier in the year, approximately 7,000 m of surface drilling was completed in the volcanic rocks focussed approximately 200

m west of the mine diorite. Drilling encountered two sub-parallel structures, termed the Falcon Zones, that could be extensions

of the 300 and 7 zones in the mine.  Below are the remaining assays from the initial 2019 drilling (Table 2 and Figures 3 and

4).

Falcon Zones Highlights:

• Hole ERM-2019-10: 42.6 g/t over 1.5 m core length (12.6 g/t Au cut, 1.0 m true width) 

• Hole ERM-2019-42: 13.3 g/t Au over 3.1 m core length (13.0 g/t Au cut, 2.5 m width)

• Hole ERM-2019-47: 53.8 g/t Au over 1.9 m core length (34.7 g/t Au cut, 1.1 m true width)

Assays capped at 60 g/t Au. True widths are estimated.

Surface drilling continued to better define and extend the Falcon zones that remain open down plunge and along strike. 

Additionally, surface mapping and prospecting, with potentially follow-up trenching and drilling, is planned for this summer

proximal to the mine diorite and more regionally along strike as follow-up to numerous historic showings that remain

underexplored.

TECHNICAL DISCLOSURE

The sampling of, and assay data, from surface drill core is monitored through the implementation of a quality assurance -

quality control (QA-QC) program designed to follow industry best practice. Samples are transported in sealed bags to AGAT

Laboratories in Timmins Ontario for preparation. Pulps are transported to Mississauga, Ontario for gold assay by fire assay

with AAS finish. Samples with high grade gold are further assayed with a gravimetric finish and by metallic screen assay

where visible gold is present. Wesdome inserts blanks and certified standards in the sample sequence for quality control.

For underground drilling, the sampling of, and assay data from, underground drill core is monitored through the implementation

of a quality assurance - quality control (QA-QC) program designed to follow industry best practice. Samples are transported in

sealed bags to Eagle River Mine assay office in Wawa, Ontario. Samples are analyzed for gold using standard fire assay

technique with gravimetric finish. Wesdome inserts blanks and certified reference standard in the sample sequence for quality

control.

The technical content of this release has been compiled, reviewed and approved by Michael Michaud, P.Geo., Vice President,

Exploration of the Company and a "Qualified Person" as defined in National Instrument 43-101 -Standards of Disclosure for

Mineral Projects.

ABOUT WESDOME

Wesdome Gold Mines is in its 30 th year of continuous gold mining operations in Canada.  The Company is 100% Canadian

focused with a pipeline of projects in various stages of development.  The Eagle River Complex in Wawa, Ontario is currently

producing gold from two mines, the Eagle River Underground Mine and the Mishi Open pit, from a central mill.  Wesdome is

actively exploring its brownfields asset, the Kiena Complex in Val d’Or, Quebec.  The Kiena Complex is a fully permitted

former mine with a 930 metre shaft and 2,000 tonne per day mill.  The Company has further upside at its Moss Lake gold

deposit, located 100 kilometres west of Thunder Bay, Ontario, which is being explored and evaluated to be developed in the

appropriate gold price environment.  The Company has approximately 135.8 million shares issued and outstanding and trades

on the Toronto Stock Exchange under the symbol “WDO.”

For further information, please contact:

Duncan Middlemiss                                      or                           Lindsay Carpenter Dunlop

President and CEO                                                                    VP Investor Relations

416-360-3743   ext. 2029                                                           416-360-3743   ext. 2025

[email protected]                                                     [email protected]

220 Bay Street, Suite 1200

Toronto, ON, M5J 2W4

Toll Free: 1-866-4-WDO-TSX

Phone: 416-360-3743, Fax: 416-360-7620

Website: www.wesdome.com

This news release contains “forward-looking information” which may include, but is not limited to, statements with respect to

the future financial or operating performance of the Company and its projects. Often, but not always, forward-looking

statements can be identified by the use of words such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “estimates”,

“forecasts”, “intends”, “anticipates”, or “believes” or variations (including negative variations) of such words and phrases, or

state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-

looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results,

performance or achievements of the Company to be materially different from any future results, performance or achievements

expressed or implied by the forward-looking statements. Forward-looking statements contained herein are made as of the date

of this press release and the Company disclaims any obligation to update any forward-looking statements, whether as a result

of new information, future events or results or otherwise. There can be no assurance that forward-looking statements will prove

to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The

Company undertakes no obligation to update forward-looking statements if circumstances, management’s estimates or

opinions should change, except as required by securities legislation. Accordingly, the reader is cautioned not to place undue

reliance on forward-looking statements. The Company has included in this news release certain non-IFRS performance

measures, including, but not limited to, mine operating profit, mining and processing costs and cash costs. Cash costs per

ounce reflect actual mine operating costs incurred during the fiscal period divided by the number of ounces produced.  These

measures are not defined under IFRS and therefore should not be considered in isolation or as an alternative to or more

meaningful than, net income (loss) or cash flow from operating activities as determined in accordance with IFRS as an

indicator of our financial performance or liquidity. The Company believes that, in addition to conventional measures prepared in

accordance with IFRS, certain investors use this information to evaluate the Company's performance and ability to generate

cash flow

Drilling Composites

Table 1

311 West

Hole From

(m)

To

(m)

Width

(m)

True

Width

(m)

Au

(Uncut)

(g/t)

Au (Cut

60)

(g/t)

750-E-57 133.5 135.9 2.35 1.51 18.09 18.09

750-E-58 114.4 116.4 1.95 1.49 2.18 2.18

750-E-59 96.8 102.4 5.60 4.85 13.92 13.92

750-E-60 85.9 87.9 1.95 1.49 0.29 0.29

750-E-61 83.2 84.8 1.60 1.50 5.65 5.65

750-E-62 162.1 163.9 1.85 1.52 1.47 1.47

750-E-63 133.0 135.9 2.85 2.18 17.95 17.95

750-E-64 108.7 110.6 1.85 1.52 2.32 2.32

750-E-66 155.9 158.5 2.60 1.49 7.51 7.51

750-E-67 125.6 127.6 1.95 1.49 1.10 1.10

750-E-68 110.8 112.9 2.15 1.52 1.24 1.24

750-E-69 148.2 150.0 1.75 1.52 14.04 14.04

750-E-70 152.4 154.7 2.35 1.51 18.06 18.06

750-E-71 168.0 169.8 1.85 1.52 8.47 8.47

750-E-73 149.1 157.0 7.90 5.59 7.21 7.21

750-E-74 100.5 102.3 1.85 1.52 5.77 5.77

750-E-75 136.0 138.1 2.15 1.52 15.38 15.38

750-E-76 156.9 159.3 2.35 1.51 30.75 30.75

750-E-77 183.8 185.7 1.95 1.49 1.58 1.58

750-E-79 127.1 129.2 2.15 1.52 2.70 2.70

750-E-80 149.4 151.4 1.95 1.49 1.05 1.05

750-E-81 172.4 174.8 2.40 1.54 15.04 15.04

750-E-82 193.0 195.3 2.35 1.51 25.93 17.87

7 East

Hole From

(m)

To

(m)

Width

(m)

True

Width

(m)

Au

(Uncut)

(g/t)

Au (Cut

125)

(g/t)

844-E-241 191.3 193.7 2.40 2.08 17.16 17.16

844-E-242 223.1 224.9 1.80 1.56 22.10 22.10

844-E-248 224.7 226.7 1.95 1.49 1.38 1.38

844-E-249 274.5 276.5 1.95 1.49 4.60 4.60

844-E-250 270.5 272.7 2.15 1.52 19.72 19.72

844-E-251 257.6 259.4 1.85 1.52 2.31 2.31

844-E-252 242.5 246.1 3.55 2.91 9.17 9.17

844-E-253 205.6 210.2 4.65 3.81 56.63 27.02

844-E-258 228.1 230.0 1.95 1.49 11.65 11.65

844-E-259 256.8 267.6 11.20 7.92 10.12 8.89

844-E-260 261.5 263.8 2.35 1.51 1.87 1.87

844-E-261 317.2 319.5 2.35 1.51 7.68 7.68

844-E-264 278.3 287.4 9.10 6.43 7.33 7.33

Table 2

Hole Zone From

(m) To (m) Width

(m)

True

Width (m)

Au

(Uncut)

(g/t)

Au (Cut

60) (g/t) Comments

ERM-2019-09 Falcon 300 153.8 155.7 1.9 1.46 1.19 1.19  

ERM-2019-09 Falcon 7 218.8 219.5 0.7 0.57 5.61 5.61 VG

ERM-2019-10 Falcon 300 195.5 197.2 1.7 1.08 19.63 11.44  

ERM-2019-10 Falcon 7 264.6 266.1 1.5 1.03 42.64 12.55 VG

ERM-2019-16 Falcon 300 182.0 186.6 4.6 2.97 0.98 0.98  

ERM-2019-16 Falcon 7 248.6 249.2 0.6 0.42 18.65 18.65  

ERM-2019-38 Falcon 7 103.7 104.0 0.35 0.24 5.01 5.01  

ERM-2019-40 Falcon 7 158.6 160.1 1.5 1.03 7.00 7.00 VG

ERM-2019-41 Falcon 300 84.7 85.8 1.1 0.58 1.08 1.08  

ERM-2019-41 Falcon 7 195.7 198.4 2.65 1.57 1.37 1.37 VG

ERM-2019-42 Falcon 300 57.5 58.3 0.85 0.62 2.74 2.74  

ERM-2019-42 Falcon 7 117.4 120.3 2.95 2.33 1.33 1.33  

ERM-2019-42 Falcon 7 126.5 129.6 3.1 2.45 13.25 13.01 VG

ERM-2019-43 Falcon 7 152.2 154.8 2.6 1.83 2.17 2.17  

ERM-2019-44 Falcon 7 185.4 187.5 2.1 1.24 1.05 1.05 VG

ERM-2019-45 Falcon 300 57.7 58.0 0.35 0.24 3.97 3.97  

ERM-2019-45 Falcon 7 131.9 133.5 1.55 1.19 6.42 6.42 VG

ERM-2019-46 Falcon 7 160.0 161.0 1 0.66 7.94 7.94 VG

ERM-2019-47 Falcon 300 101.0 101.5 0.5 0.26 39.00 39.00  

ERM-2019-47 Falcon 7 151.3 153.2 1.9 1.07 53.76 27.39 VG

Images accompanying this announcement are available at

https://www.globenewswire.com/NewsRoom/AttachmentNg/13fb1e04-f12a-4869-bc88-6e991ea9af5b

https://www.globenewswire.com/NewsRoom/AttachmentNg/2b49b3c5-3093-4aeb-83ef-9c51b9319054

https://www.globenewswire.com/NewsRoom/AttachmentNg/5af12f7c-dd9c-43d9-9d39-8891edc7496e

https://www.globenewswire.com/NewsRoom/AttachmentNg/f41d0508-8f3a-4895-a098-8d6b3d74ca94

https://www.globenewswire.com/NewsRoom/AttachmentNg/c870e8fb-5397-4780-b253-8c36f5c5cc6e

PDF available: http://ml.globenewswire.com/Resource/Download/2212ec12-365d-4a50-bfcd-d2212f07c8f6