WESTERN ALASKA MINERALS INTERSECTS FIRST GOLD INTERCEPT AT WARM SPRINGS 4.68 meters of 1.29 g/t Au including 0.18 meters of 12.5 g/t Au

Drill Results Mine Development & Operations

NEWS RELEASE

WESTERN ALASKA MINERALS INTERSECTS FIRST GOLD INTERCEPT

AT WARM SPRINGS

4.68 meters of 1.29 g/t Au including 0.18 meters of 12.5 g/t Au

TUCSON, ARIZONA, US – August 29, 2024 - Western Alaska Minerals (the "Company" or "WAM")

(TSXV: “WAM”) is pleased to announce initial gold assay results from their first ever drilling at the

Warm Springs target on the Illinois Creek project in western Alaska.

Highlights:

• Two gold zones intercepted in drill hole IC24-0004:

o 1.29 g/t Au over 4.68 meters within massive pyrite, including:

▪ 12.5 g/t Au and 0.9% Cu over 0.18 meters

o 2.13 g/t Au over 2.96 meters, including:

▪ 5.57 g/t Au over 1.01 meters

• Discovery of a new and separate mineralized structure parallel to the Illinois Creek

Fault, opening the potential of a new “spoke” to the system.

• First significant copper and gold mineralization intercepted since WAM initiated

exploration in 2021.

• The gold bearing zone is located approximately 1.4 km southeast of the Illinois Creek

gold-silver resource (Figure 1).

“Finding gold at Warm Springs opens up a whole new gold target zone within the eight-kilometer-long

trend between the Illinois Creek and Waterpump Creek resources,” said Kit Marrs, founder and CEO

of Western Alaska Minerals.

Mr. Marrs continues, “This is an exciting complement to our high-grade silver-zinc-lead resource at

Waterpump Creek.”

Figure 1. Top: Google Earth view looking down and to the northwest of the Illinois Creek CRD system,

encompassing Illinois Creek resource - Warm Springs - LH - Waterpump Creek resource. Bottom:

LeapFrog 3D model of the mineralized areas.

Warm Springs Target

Dr. Peter Megaw, Technical Advisor and world -renowned silver and CRD geologist stated, “ The

appearance of gold and copper in the multiply brecciated alteration and mineralization zones cut in

these latest holes at Warm Springs clearly indicates we’re zeroing in on a repeatedly reactivated

structure that acted as a major pathway for proximal/near -source mineralizing fluids. The CRD

continuum model suggests the next steps are to link this to the distal silver -lead-zinc resource at

Waterpump Creek and the more proximal gold-copper resource adjoining the historical Illinois Creek

mine. The possibility that this is a separate structure parallel to the Illinois Creek Fault is especially

intriguing as it may indicate a whole new “spoke” to the system.”

Western Alaska Minerals has completed nine drill holes at Warm Springs. Extensive alteration and

oxide mineralization along with local base -metal sulfide mineralization has been intercepted in

seven of the nine drill holes.

Table 1. Table of highlight intercepts from drill hole IC24-0004

Hole

From

(m)

To

(m)

Length

(m)

Au

(g/t)

Ag

(g/t)

Pb

%

Zn

%

Cu

%

Sulfide/

Oxide

IC24-0004 84.17 88.85 4.68 1.29 11.6 0.26 0.05 0.04 Sulfide

Including 84.17 84.35 0.18 12.50 167 2.44 0.03 0.91

IC24-0004 244.40 247.36 2.96 2.13 7.0 0.35 0.30 .03 Oxide

Including 246.35 247.36 1.01 5.57 12.8 0.38 0.26 .05

All intercepts are core length and are close to true width. Core recovery averaged 90.1% for

reported intercepts.

Table 2. Coordinate locations and angles for drill holes IC24-0004

Hole Easting Northing Plunge Azimuth TD (m)

IC24-0004 555150 7101350 -60 000 451.41

Significance of Warm Springs Drill Results – Technical Discussion

The Warm Springs mineralization is a major extension to the Illinois Creek CRD system and shows

significant complexly overprinted mineralization stages. Exploration this year followed up on the

Warm Springs siliceous breccia outcrop and two Anaconda drill holes from 1982 *. The target was

thought to be either an extension of the East IC Manto down -dip to the south or possibly a new

mineralizing structure parallel to that of the Illinois Creek Mine mineralization. The drill results show

numerous stages of mineralization incl uding early -stage recrystallized ankerite with trace base -

metal sulfides and cross-cutting late-stage silica and oxide mineralization. The first hole, IC24-0004,

was a 310m step-off south of Anaconda drill holes 11 and 12*, and 1.2 km west of the WAM 2022 drill

holes.

IC24-0004 intercepted four mineralization zones consisting of numerous mineralization stages

(Figure 4) including 1) pyrite + hydrothermal quartz breccia with elevated Au, As and Cu values as

shown in Table 1, 2) recrystallized ankerite with trace galena 3) pervasive silica + oxide breccia

including limonite-dominant and hematite -dominant sub-zones and 4) o xidized elevated Pb + Mn

(assay results not shown) manto gossans. These elevated metal zones ranged from 18.7 to 53.65

meters thick with a combined total mineralization thickness of 100 meters.

Figure 2. Massive pyrite with breccia texture for the intercept reported in Table 1.

Figure 3. Breccias in various stages of mineralization

LH Target Zone Update

The 2024 drill program also included drill testing of the LH target zone, located on the west side of

the airstrip. The LH Target has generated significant interest as a potential high -grade extension of

the Waterpump Creek zone. It was first drilled by NovaGold in 2005/2006*. WAM drilled four holes in

2024 which cut a few gossans, but no significant sulfide manto mineralization. In addition, four

surface trenches were cut to better understand the LH target. Assays for the drilling and trenching

are pending. The drill holes this year plus the trenching have refined our exploration model and target

for the LH zone. It is now interpreted to be a vertically oriented feature and likely higher in the CRD

system than Waterpump Creek and mineralization is thought to be deeper than originally

anticipated.

The LH target remains a priority target.

Drilling Statistics

• Drill program was completed on August 24th, totalling 4,230 meters

• LH Zone: four drill holes totalling 1,347 meters

• Warm Springs Zone: nine drill holes totalling 2,883 meters

• Assay results pending for all holes except IC24-0004

Quality Assurance and Quality Control

Quality Assurance/Quality Control of drill sample assay results are monitored by WAM staff through

a quality assurance/quality control (“QA/QC”) protocol which includes the insertion of blind

standard reference materials, blanks, and duplicates samples at regular intervals.

Core logging and sampling is completed at the Illinois Creek mine camp in Alaska. Drill core is logged

under an established procedure using GeoSpark commercial logging software. Core intervals

selected for assay are sawn lengthwise in half. One half of the core interval is bagged and labeled for

assay. The remainder is stored on site for reference.

The bagged core samples are transported to the ALS Minerals laboratory in Fairbanks, Alaska, USA,

for sample submission. ALS Minerals Fairbanks is a satellite sample preparation facility accredited

under ALS Minerals. The ALS Minerals Fairbanks laboratory then shipped the samples to ALS

Minerals in North Vancouver, B.C., Canada, for sample preparation and analysis. ALS Minerals North

Vancouver is an independent laboratory certified under ISO 9001:2008 and accredited under

ISO/IEC 7025:2005 by the Standards Council of Canada. ALS Minerals includes its own internal

quality control samples comprising certified reference materials, blanks, and pulp duplicates.

At ALS the half -core samples were weighed (WEI -21), dried if excessively wet (DRY -21), coarse jaw

crushed to 70% passing 6 mm (CRU-21), fine jaw crushed to 70% passing 2 mm (CRU-31), riffle split

to 250 g subsamples (SPL -21) and pulverized to 85% passing 7 5 μm (PUL-31). Crushed duplicates

were created by riffle splitting crushed samples into two parts.

The gold content is determined by fire assay of a 30-gram charge with an AA finish (Au-AA23). Silver,

lead, copper, and zinc along with other elements are analyzed by ICP utilizing a four -acid digestion

(ME-ICP61). Over-limit samples for silver, lead, copp er, and zinc are determined by using either an

ore grade four-acid digestion and ICP-ES finish (ME-OG62) or ore-grade titration analysis (VOL50 or

VOL70) for very high -grade samples. Au from the high -grade interval from 84.17 to 84.35 was

analyzed a 30 gram fire assay charge and gravimetric finish.

ALS Minerals’ laboratory also performs its own internal QA/QC procedures to assure the accuracy

and integrity of results. Parameters for ALS’ internal and WAM’ external blind quality control samples

are acceptable for the elements analyzed. WAM is unaware of any drilling, sampling, recovery, or

other factors that could materially affect the accuracy or reliability of the data referred to herein.

Qualified Person

The Qualified Person who reviewed and approved the technical disclosure in this release is Andrew

West, Certified Professional Geologist, a Qualified Person as defined under National Instrument 43-

101. Mr. West is the Vice President for Western Alaska Minerals with a MS in Geology and 30 years of

experience in mineral resources, mine, and exploration. He is a Certified Professional Geologist with

the American Institute of Professional Geologists (AIPG CP-11759).

His review verified the technical data disclosed, including geology, sampling, analytical and QA/QC

data underlying this news release, including reviewing the reports of ALS, methodologies, results,

and all procedures undertaken for quality assurance and quality control in a manner consistent with

industry practice.

About WAM

Our mission is to advance a mineable and scalable CRD, ultimately reshaping the mineral landscape

of western Alaska and establishing a new CRD district.

WAM’s CRD system encompasses a 373K oz AuEq NI 43-101-compliant indicated and 152K oz AuEq

Inferred resource* at the past producing Illinois Creek gold-silver mine*, and the Waterpump Creek

high-grade silver-lead-zinc deposit with an inferred resource estimate of 74.9Moz at 980 G/T AgEq*,

open to the north. Within the same CRD system sits the Honker gold vein prospect. Twenty -five

kilometers northeast of the Illinois Creek CRD lies the Round Top copper and the TG North CRD

prospects. All prospects were originally discovered by Anaconda Minerals Co. in the early 1980’s *.

WAM’s 100% owned claims and uplands mining lease cover 73,120 acres (114.25 square miles or

29,591 hectares), approximately 45 km east of an ocean barge -compatible section of the Yukon

River. Since 2010, WAM, along with its precursor company, Western Alas ka Copper & Gold,

reassembled the Anaconda land package and has been engaged in exploring the district.

Headquartered in both Alaska and Arizona, WAM brings together a team of seasoned professionals

with a shared vision of pioneering new frontiers in mineral exploration. Our strategic approach is

underpinned by cutting -edge technology, innovative techniques, and a deep understanding of the

geological intricacies of the region.

*Information on our historical gold and Waterpump Creek resources, as well as historical work

performed by Anaconda Minerals Co. and NovaGold (2005/2006) can be found on our NI 43 -101

report, dated April 2, 2024, authored by Bruce Davis, PhD, FAusIMM, titled “Western Alaska Minerals

Corp. ILLINOIS CREEK PROJECT UPDATE Illinois Creek Mining District, Western Alaska, USA” on our

website: https://www.westernalaskaminerals.com/_resources/pdfs/Illinois -Creek-NI43101-Technical-

Report.pdf?v=0.317

On behalf of the Company

“Kit Marrs”

Kit Marrs

President & CEO

Phone: 520-200-1667

For further information please contact:

Vanessa Bogaert, Director of Corporate Communications/IR at

[email protected]

Or visit our website at: www.westernalaskaminerals.com

Forward Looking Information

This news release contains “forward -looking information” within the meaning of applicable

Canadian securities legislation. “Forward -looking information” includes, but is not limited to,

statements with respect to the activities, events or developments that the Company expects or

anticipates will or may occur in the future. Generally, but not always, forward -looking information

and statements can be identified by the use of words such as “plans”, “expects”, “is expected”,

“budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the

negative connotation thereof or variations of such words and phrases or state that certain actions,

events or results “may”, “could”, “would”, “might” or “will be taken”, “occur” or “be achieved” or

the negative connation thereof.

Such forward-looking information and statements are based on numerous assumptions, including

among others, Although the assumptions made by the Company in providing forward -looking

information or making forward-looking statements are considered reasonable by management at the

time, there can be no assurance that such assumptions will prove to be accurate and actual results

and future events could differ materially from those anticipated in such statements.

Important factors that could cause actual results to differ materially from the Company’s plans or

expectations include risks relating to market conditions, metal prices, and risks relating to general

economic, market or business conditions, uninsured risk s, regulatory changes, defects in title,

availability of personnel, materials, and equipment on a timely basis, accidents or equipment

breakdowns, unanticipated environmental impacts on operations and costs to remedy same, and

other exploration or other ri sks detailed herein and from time to time in the filings made by the

Company with securities regulators. Although the Company has attempted to identify important

factors that could cause actual results to differ materially from those contained in the forwa rd-

looking information or implied by forward-looking information, there may be other factors that cause

results not to be as anticipated, estimated or intended. There can be no assurance that forward -

looking information and statements will prove to be accurate, as actual results and future events

could differ materially from those anticipated, estimated or intended. Accordingly, readers should

not place undue reliance on forward-looking statements or information.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.