Currie Rose Announces Updated Mineral Resource Estimate at its North Queensland Vanadium Project
Currie Rose Announces Updated Mineral
Resource Estimate at its North Queensland
Vanadium Project
Toronto, Ontario--(Newsfile Corp. - November 1, 2022) -
Currie Rose Resources Inc. (TSXV: CUI)
("Currie Rose" or the "Company") is pleased to announce an updated independent mineral resource
estimate ("MRE") for its Cambridge Vanadium Deposit that forms part of the North Queensland
Vanadium Project ("NQVP") situated within the "Vanadium Hub" approximately 450 km west of the port
of Townsville, Queensland, Australia.
Highlights:
Indicated Resource of 61.33Mt @ 0.34% V
2
O
5
. The initial 2018 MRE contained no indicated
mineral resources.
Inferred Resource increased by 61Mt to 144.87Mt @ 0.33% V
2
O
5
,
representing a 72% increase
from the initial 2018 resource.
Updated resource estimate based on 65 drill holes, using 30 drill holes not included in the initial
2018 resource.
Estimated Molybdenum (M
O
O
3
) grade of 239.7ppm, up 51.8ppm ~28% increase.
The updated MRE is based on "reasonable prospects for eventual economic extraction" and is
constrained in a Lerchs Grossman (LG) open pit shell that was constructed using $AUD 23,152/tonne
($USD 7.5/lb) for V
2
O
5
.
The MRE has an effective date of October 27, 2022 and is based on historical
drilling from 2008 to 2019.
Details of the MRE are shown in Table 1 below.
Additionally, the North Queensland Vanadium Project has multiple characteristics that are positive for
potential future development. These include:
Existing road access on the western edge of the deposit.
Close to rail and power infrastructure.
Mineralization is flat lying and outcrops at surface in places.
Large property with multiple exploration targets.
Cambridge Deposit covers ~ 2,500Ha (or 2%) of the 124,000Ha package.
Mike Griffiths, CEO, President and Director
, said: "With this update, we have more than doubled the
in-situ metal, improved the overall grade and elevated a substantial amount of resources to Indicated
Resource status. We believe that NQV Project presents a massive opportunity to make our mark in the
ever-evolving battery and energy metals markets. Vanadium redox flow batteries will soon begin to play
an integral role in supporting power grids and bridging the gap of reliable alternative sources of energy.
There are plenty of exploration catalysts to communicate with shareholders over the next several quarters
as we set on our path to de-risk the NQVP."
Table 1 - Mineral Resource Estimate for the NQVP at 0.25 % Vanadium Cut-Off Grade
Cut-Off
V
2
O
5
(%)
Classification
Ore Tonnes
(Mt)
V
2
O
5
(t)
V
2
O
5
(%)
MoO
3
(t)
MoO
3
(ppm)
0.25
Indicated
61.33
210,300
0.34
14,600
234.6
Inferred
144.87
483,400
0.33
35,500
241.9
Notes
:
Indicated and Inferred Mineral Resources are not Mineral Reserves. Mineral resources which are not mineral reserves do not have
demonstrated economic viability. There has been insufficient exploration to define the inferred resources tabulated above as an indicated or
measured mineral resource, however, it is reasonably expected that the majority of the Inferred Mineral Resources could be upgraded to
Indicated Mineral Resources with continued exploration. There is no guarantee that any part of the mineral resources discussed herein will
be converted into a mineral reserve in the future. The estimate of mineral resources may be materially affected by environmental, permitting,
legal, marketing or other relevant issues. The mineral resources have been classified according to the Canadian Institute of Mining (CIM)
Definition Standards for Mineral Resources and Mineral Reserves (May 2014) and CIM Estimation of Mineral Resources & Mineral Reserves
Best Practices Guidelines (2019).
The Mineral Resource Estimate is constrained in an LG pit optimization utilizing V
2
O
5
at $USD 7.5/lb, Mining at $AUD 2.86/tonne, Processing
and G&A at $AUD 7.86/tonne, pit slopes at 35
o
.
Differences may occur in totals due to rounding.
Tonnage estimates are based on a bulk density of 1.8 g/cm
3
.
Mr. Mike Dufresne, P.Geol., P.Geo. and Mr. Steven Nicholls, M.AIG of APEX Geoscience Ltd. ("APEX"), who are deemed a qualified person
as defined by NI 43-101 is responsible for the completion of the updated mineral resource estimation.
Figure 1 - North Queensland Vanadium Project Location
To view an enhanced version of Figure 1, please visit:
https://images.newsfilecorp.com/files/2005/142564_0bb8e9d7e4d87a56_002full.jpg
The NQVP is the merger of the Toolebuc and Flinders River Vanadium Projects and is situated
approximately 450km west of the port of Townsville (Figure 1). The NQVP covers an area of
approximately 124,000 Ha and is close to rail, road and power infrastructure.
The Cambridge vanadium pentoxide (V
2
O
5
)
mineralisation is located within marine sediments of the
Early Cretaceous Toolebuc Formation, a stratigraphic unit that occurs throughout the Eromanga Basin in
Central Northern Queensland. The Toolebuc Formation is a flat-lying, early Cretaceous (Albian ~100 Ma)
sedimentary package that consists predominantly of black carbonaceous and bituminous shale and
minor siltstone, with limestone lenses and coquinites (mixed limestone and clays). The Cambridge MRE
is situated within the flat lying Toolebuc Formation.
65 aircore drill holes totalling 1,577 m were completed to delineate the Cambridge Deposit between
2008 and 2019 by Horizon Minerals/Intermin Resources in 2008 ("Horizon/Intermin") and Liontown
Resources Ltd in 2019 ("Liontown"). The drilling defined one flat lying horizon of V
2
O
5
and MoO
3
mineralization ranging in thickness from 2 m to around 15 m covering a lateral area of 5.8 x 4.3 km.
Photo 1 - Surface View of the Cambridge V
2
O
5
Deposit - Looking South
To view an enhanced version of Photo 1, please visit:
https://images.newsfilecorp.com/files/2005/142564_0bb8e9d7e4d87a56_003full.jpg
About the Mineral Resource Estimate
Modelling was conducted in the Map Grid of Australia (MGA) coordinate space relative to the
Geocentric Datum of Australia (GDA) 2020, and MGA zone 54 (EPSG:7854). The mineral resource
block model utilized a block size of 100 m (X) x 50 m (Y) x 2 m (Z) to honour the mineralization
wireframes. The percentage of the volume of each block below the bare earth surface and within the
mineralization domain was calculated using the 3D geological models and a 3D surface model.
The Cambridge Deposit drill hole database consists of 58 drill holes that intersect the interpreted
mineralization wireframe. The V
2
O
5
and MoO
3
assays were composited to 1m composite lengths, and
the estimation utilized 575 composited samples. All intervals within the interpreted wireframe were
visually checked to ensure the flagging process was completed correctly.
The MRE is based on the combination of geological modelling, geostatistics and conventional block
modelling using the Ordinary Kriging ("OK") method of grade interpolation with locally varying anisotropy
variogram models.
For grade estimation, 1m composites were used to create the interpreted mineralization boundaries. A
lower cut-off grade of 0.12% V
2
O
5
was used to define the domain outline.
This lower cut-off was chosen
as a natural inflection in the V
2
O
5
assay population.
A single mineralized domain was defined. Block
tonnes were estimated using 1.8 g/cm
3
for mineralized material.
The V
2
O
5
and MoO
3
grade estimations were completed independently of each other and were
completed using OK. The search ellipsoid size used to estimate the V
2
O
5
and MoO
3
grades was
informed by the modelled variograms for each variable. Block grade estimation employed locally varying
anisotropy, which uses different rotation angles to define the principal directions of the variogram model
and search ellipsoid on a per-block basis.
Blocks within estimation domains are assigned rotation angles using a modelled 3D mineralization trend
surface wireframe. The estimation was performed using three estimation passes whereby each
successive pass utilized a less restrictive sample search strategy for block estimation.
The search radii for the first estimation pass equals half of the variogram ranges. The second pass
increases the search distance to the variogram range. The third pass further expanded the search
distances up to twice the variogram range. Over 95% of the blocks were estimated within the first two
estimation passes.
The resource is classified according to the CIM "Estimation of Mineral Resources and Mineral Reserves
Best Practice Guidelines" dated November 29th, 2019, and CIM "Definition Standards for Mineral
Resources and Mineral Reserves" dated May 10th, 2014. Mr. Dufresne believes the North Queensland
Vanadium Project - Cambridge Deposit has the potential for future economic extraction.
The unconstrained resource block model was subjected to several open pit optimization scenarios and
surface mining parameters. The following criteria, Table 2, were considered reasonable.
Table 2
-
Assumptions Used for the LG Pit Shell and Reasonable Prospects of Eventual
Economic Extraction
Item
Unit
Value
Vanadium Price
USD/lb
7.50
Molybdenum Price
-
-
Mining Cost
AUD/tonne
2.86
Processing + G&A
AUD/tonne
7.86
AUD - USD Exchange Rate
0.70
Assumed V205 Recovery
%
85
Assumed Molybdenum Recovery
-
-
*Molybdenum was treated as a by-product of Vanadium and as such not used in the economic
parameters of reasonable prospects of eventual economic extraction (LG Pit design).
Table 3 - Sensitivity Analysis of the Mineral Resource Estimate for the NQVP at Various
Vanadium Cut-Off Grades
Classification
Cutoff
V
2
O
5
(%)
Ore
Tonnes
(Mt)
V
2
O
5
(t)
V
2
O
5
(%)
MoO
3
(t)
MoO
3
(ppm)
Indicated
0.2
87.63
269,700
0.301
19,200
214.6
0.25
61.33
210,300
0.339
14,600
234.6
0.3
38.32
147,400
0.383
10,100
263.3
0.35
22.15
95,200
0.429
6,300
283.5
0.4
12.59
59,500
0.473
3,900
306.8
Inferred
0.2
217.59
648,300
0.294
48,800
220.6
0.25
144.87
483,400
0.33
35,500
241.9
0.3
80.83
308,700
0.38
21,600
264.5
0.35
46.81
199,600
0.426
13,500
287.7
0.4
23.97
114,900
0.478
6,900
288.8
A National Instrument 43-101 Technical Report will be filed under the Company's SEDAR profile at
www.sedar.com
within 45 days.
Data Verification
Currie Rose has not yet conducted any drilling on the North Queensland Vanadium Property. In 2018,
Optiro Pty Ltd. completed an independent MRE report of the Cambridge Deposit, which is now
superseded and is considered a historical estimate.
The QPs reviewed recent reports and other documents including a recent independent mineral resource
estimate report ("Cambridge Resource") authored by Optiro Pty Ltd. (2018), a summary report by Mike
Griffiths of Currie Rose (2021), and a number of ASX news releases (by Liontown Resources Ltd.). The
Optiro Report documents a historical MRE that the QPs consider to having been compliant with recent
CIM guidelines (2014) at the time it was constructed.
The Optiro Cambridge MRE was calculated based on 35 aircore holes completed in 2008 by Intermin.
Mr. Dufresne and Mr. Steven Nicholls of APEX, both QP's reviewed the MRE and the underlying data.
Liontown completed a total of 30 aircore holes in 2019 that are not included in the historical Optiro MRE
but are available, well
documented
and were utilized in the current MRE.
The 2019 Liontown drill holes were drilled after the completion of the Optiro MRE and hence the MRE is
now considered historical. The QPs have reviewed all the reports, the data that backs up the reports and
the recent MRE data including drillhole data, wireframes and block models and confirm that the work and
data are of a good standard and suitable for use for the calculation of a current MRE.
The drilling by Liontown in 2019 on the Cambridge Exploration License 26494 has confirmed the
presence of vanadium mineralization in twin holes in the Cambridge Resource area identified in the
Optiro (2018) Report and has likely extended the mineralization envelope.
Mr. Nicholls of APEX has performed a property visit and has reviewed the assay data for the seven twin
drill holes in comparison with the historical Intermin drill holes, and the results returned show comparable
V
2
O
5
% assay results between the two sets of data.
Figure 2 - Plan View of the NQVP - Cambridge Deposit Showing the Drill Hole Locations and
the Interpreted Mineralization Extents
To view an enhanced version of Figure 2, please visit:
https://images.newsfilecorp.com/files/2005/142564_0bb8e9d7e4d87a56_004full.jpg
Figure 3 - Cross-Sectional View 694700E of the NQVP - Cambridge Deposit Showing the V
2
O
5
Estimated Grades, Drill Hole Assays and the Interpreted Mineralization Extents. The Vertical
Exaggeration of This Cross Section is 1:25.
To view an enhanced version of Figure 3, please visit:
https://images.newsfilecorp.com/files/2005/142564_0bb8e9d7e4d87a56_005full.jpg
Figure 4 - Cross-Sectional View 692700E of the NQVP - Cambridge Deposit Showing the V
2
O
5
Estimated Grades, Drill Hole Assays and the Interpreted Mineralization Extents. The Vertical
Exaggeration of This Cross Section is 1:25.
To view an enhanced version of Figure 4, please visit:
https://images.newsfilecorp.com/files/2005/142564_0bb8e9d7e4d87a56_006full.jpg
Qualified Persons and 43-101 Disclosure
The updated Cambridge MRE was reviewed and approved for release by Michael Dufresne, M.Sc.,
P.Geol., P.Geo., President and Principal of APEX in accordance with the requirements of National
Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101").
During 2022, APEX was retained by Currie Rose to complete an updated NI 43-101 report and update
the mineral resource estimate for the Cambridge Deposit. The authors of the report, Mr. Michael
Dufresne and Mr. Steven Nicholls of APEX, both independent qualified persons as defined by the
Canadian Securities Administration (CSA) National Instrument 43-101. Mr. Nicholls conducted the most
recent property visit in November 2021 and compiled the mineralized domains for the mineral resource
estimation of the Cambridge Deposit.
About Currie Rose Resources Inc.
Currie Rose is a publicly traded battery metals explorer and developer focused on identifying high-value
assets in mining-friendly jurisdictions. The Company's immediate focus is the advanced North
Queensland Vanadium Project in Queensland, Australia. Please visit our website at
www.currierose.com
.
For additional information, please contact:
Mike Griffiths, CEO
Office: 905-688-9115 ext. 104
Email:
Iryna Zheliasko, Investor Relations
Office: 905-688-9115 ext. 322
Email:
Forward-Looking Statements
Neither the TSX Venture Exchange nor its regulation services provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this
release.
This news release may contain forward-looking statements that are based on the Company's
expectations, estimates and projections regarding its business and the economic environment in
which it operates. Statements about the closing of the transaction, expected terms of the transaction,
the number of securities of Currie Rose that may be issued in connection with the transaction, and the
parties' ability to satisfy closing conditions and receive necessary approvals are all forward-looking
information. These statements are not guarantees of future performance and involve risks and
uncertainties that are difficult to control or predict. Therefore, actual outcomes and results may differ
materially from those expressed in these forward-looking statements and readers should not place
undue reliance on such statements. Statements speak only as of the date on which they are made,
and the Company undertakes no obligation to update them publicly to reflect new information or the
occurrence of future events or circumstances, unless otherwise required to do so by law.
To view the source version of this press release, please visit
https://www.newsfilecorp.com/release/142564