Velocity Announces Positive Drill Results from the Sedefche Gold Project, Southeast Bulgaria Highlights include:
1
Lms
NR-20-07 March 2, 2020
Velocity Announces Positive Drill Results from the
Sedefche Gold Project, Southeast Bulgaria
Highlights include:
Drill hole SDD-019; 25.2m @ 5.45 g/t gold and 57.8 g/t silver;
incl. 13.0m @ 9.38g/t gold and 70.5 g/t silver
Vancouver, British Columbia – Velocity Minerals Ltd. (TSX .V: VLC) (“ Velocity” or the “ Company”)
announces that it has received results for four additional drill holes for the Sedefche Gold Project
(“Sedefche”), Bulgaria. Velocity’s results continue to broadly confirm the grade and tenor of historical
results and have identified a number of higher-grade zones like those for drill hole ODD-019 (Figure 1 and
Table 1). The results support the potential to fast- track development of the Sedefche deposit along the
lines of an existing, permitted Mine Design Plan completed by Bulgarian partner Gorubso -Kardzhali A.D.
(“Gorubso”).
Figure 1: Cross Section at Sedefche Gold Project showing results for drill hole ODD-019 and drill holes for which
results are pending and planned drill holes. Drill hole locations are shown on Figure 2 below.
Velocity’s results have returned better grade and tenor than previous results and continue to define a
number of higher -grade zones within the existing resource envelope, which were not identified by
historical exploration (Figures 1 and 2).
NR-20-07 Continued March 2, 2020
2
Drill hole SDD -019 (Figures 1 and 2) returned a 25.2m intersection grading 6.40 g/t gold (5.45 g/t gold
using a 20g/t top cut) and 57.8 g/t silver , including 13.0m grading 11.22 g/t gold (9.38 g/t gold using a
20g/t) top cut and 70.5 g/t silver. Top cutting is done when samples return analysis in excess of 20 g/t
gold; in this drill hole being three samples, peaking at a grade of 30.9 g/t gold over 1 meter.
Drill hole SDD-018 (Figure 1) returned three significant intersects of 4.0m grading 1.58 g/t gold and 67 g/t
silver, plus 6.1m grading 2.17 g/t gold and 92.5 g/t silver, plus 4.7m grading 1.20 g/t gold and 34.8 g/t
silver to a depth of 69.1m from surface.
Additional drilling and engineering due diligence is planned with the aim of reaching a decision point on
exercise of the Sedefche option in H1, 2020.
Table 1: Significant Drill Results at Sedefche Gold Project
The drill intersections disclosed here have not yet been included in a resource model and true thickness of
mineralization has not yet been determined. Drill holes are designed to intersect mineralization perpendicular or
close to perpendicular. Drill intersections are calculated using a top-cut of 20 g/t gold, a 0.3 g/t gold trigger, a
minimum 0.7 g/t gold composite, and a maximum of 1.5 metres consecutive waste.
Quality Assurance / Quality Control
Velocity have not assessed the Quality Assurance / Quality Control (QAQC) of historical results and as such
historical results are not consistent with the standards of disclosure defined by NI 43 -101 and may not
necessarily be consistent with CIM best practice with respect to reporting.
The work program at Sedefche was designed and is supervised by Stuart A. Mills, CGeol, the Co mpany's
Vice-President Exploration, who is responsible for all aspects of the work, including the quality
control/quality assurance program. On-site personnel at the project rigorously collect and track samples
which are then security sealed and shipped t o ALS Global laboratory in Romania. Samples used for the
results described herein are prepared and analyzed by fire assay using a 30 -gram charge in compliance
with industry standards at ALS’ Romanian laboratory. A sample split of the milled material is shipped to
ALS’ Irish laboratory for multi- element analysis using an inductively coupled Mass Spectrometer. Field
duplicate samples, blanks and independent controlled reference material (standards) are added to every
batch. Drill intersections in this news release are calculated using a 0. 3 g/t gold trigger, a minimum 0. 7
g/t gold composite, and a maximum of 1.5 metres consecutive waste.
NR-20-07 Continued March 2, 2020
3
Figure 2: Map of the Sedefche Gold Project, showing the drill traces of completed and planned drilling as well as
those for which results are pending. The drill hole locations are displayed on a geological map of the deposit
including positions of previous drill collars A section locations is included for Figure 1.
NR-20-07 Continued March 2, 2020
4
Qualified Person
The technical content of this release has been approved for disclosure by Stuart A. Mills, BSc, MSc, CGeol,
a Qualified Person as defined by NI 43-101 and the Company’s Vice President Exploration. Mr. Mills is not
independent of the Company.
About Velocity Minerals Ltd.
Velocity is a gold exploration and development company focused on southeastern Bulgaria. Velocity’s
strategy is to develop a low cost centralized “Hub and Spoke” operation whereby multiple projects within
this emerging gold district produce gold concentra tes for trucking to a central processing plant for
production of doré. The Company envisions staged open pit mining of satellite deposits and processing
in a currently operating carbon-in-leach (CIL) plant. Velocity has a 70% joint venture interest in the Rozino
gold project and has entered into option agreements to earn a 70% interest in the Obichnik, Makedontsi
and Sedefche gold projects, with Gorubso, an established and respected mining company in Bulgaria.
Velocity’s management and board includes mining industry professionals with combined experience
spanning Europe, Asia, and the Americas as employees of major mining comp anies as well as founders
and senior executives of junior to mid-tier public companies. The team's experience includes all aspects
of mineral exploration, resource definition, feasibility, finance, mine construction and mine operation as
well as a track record in managing publicly listed companies.
About Bulgaria
Bulgaria is a member of NATO (2004) and a member of the European Union (2007). The local currency
(BGN) has been tied to the Euro since 1999 (1.956 BGN/EUR). The country is served by modern European
infrastructure including an extensive network of paved roads. Bulgaria boasts an exceptionally low
corporate tax rate of only 10%. The country’s education system is excellent with good availability of
experienced mining professionals in a favourable cost environment. Foreign mining companies are
successfully operating in Bulgaria. The country’s mining law was established in 1999 and updated in
2011. Mining royalties are low and compare favourably with more established mining countries.
On Behalf of the Board of Directors
“Keith Henderson”
President & CEO
For further information, please contact:
Keith Henderson
Phone: +1-604-484-1233
E-mail: [email protected]
Web: www.velocityminerals.com
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION:
NR-20-07 Continued March 2, 2020
5
This news release includes certain “forward -looking statements” under applicable Canadian securities legislation.
Forward-looking statements include, but are not limited to, statements with respect to future exploration, testing
and Initial Drilling and, if applicable, the Additional Drilling carried out at the Project, the exercise of the Option, the
entry into of the Joint Venture and any payments in connection with same and the future business and operations
of Velocity. Often, but not always, forward looking statements can be identified by words such as “pro forma”,
“plans”, “expects”, “may”, “should”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”,
“believes”, “potential” or variations of such words including negative variat ions thereof, and phrases that refer to
certain actions, events or results that may, could, would, might or will occur or be taken or achieved. In making the
forward-looking statements in this news release, the Company has applied several material assumpt ions, including
without limitation, that market fundamentals will result in sustained gold demand and prices, the receipt of any
necessary permits, licenses and regulatory approvals in connection with the future development of the Company’ s
Bulgarian projects, the availability of financing on suitable terms for the development, construction and continued
operation of the Company’s projects, and the Company’s ability to comply with environmental, health and safety
laws. Forward looking information involves known and unknown risks, uncertainties and other factors which may
cause the actual results, performance or achievements of the Company to differ materially from any future results,
performance or achievements expressed or implied by the forward-looking information. Such risks and other factors
include, among others, operating and technical difficulties in connection with mineral exploration and development
and mine development activities for Sedefche and the Company’s projects generally, including the geo logical
mapping, prospecting and sampling programs for the projects, the fact that the Company’s interest in Sedefche is
only an option and there is no guarantee that such interest, if earned, will be certain, actual results of exploration
activities, including the Initial Drilling and, if applicable, the Additional Drilling, estimation or realization of mineral
reserves and mineral resources, the timing and amount of estimated future production, costs of production, capital
expenditures, the costs and timing of the development of new deposits, the ability of the Company to obtain access
to the CIL Plant and to have ore from the Project (and the Company’s other projects) processed at the CIL Plant on
profitable terms, the availability of a sufficient supply of water and other materials, requirements for additional
capital to fund the Company's business plan, future prices of precious metals, changes in general economic
conditions, changes in the financial markets and in the demand and market price for commodi ties, possible
variations in ore grade or recovery rates, possible failures of plants, equipment or processes to operate as
anticipated, accidents, labour disputes and other risks of the mining industry, delays in obtaining governmental and
regulatory appr ovals (including of the TSXV), permits or financing or in the completion of development or
construction activities, changes in laws, regulations and policies affecting mining operations, hedging practices,
currency fluctuations, title disputes or claims limitations on insurance coverage and the timing and possible outcome
of pending litigation, environmental issues and liabilities, risks related to joint venture operations, and risks related
to the integration of acquisitions, as well as those factors discu ssed under the heading. "Risk Factors" in the
Company's annual management's discussion and analysis and other filings of the Company with the Canadian
Securities Authorities, copies of which can be found under the Company's profile on the SEDAR website at
www.sedar.com.
Readers are cautioned not to place undue reliance on forward looking information. The Company undertakes no
obligation to update any of the forward -looking information in this news release or incorporated by reference
herein, except as otherwise required by law.
- 30 -