Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

VGZ.TO ·

Vista Gold Announces Updated Preliminary Feasibility Study for the Mt Todd Gold Project with Increased After-Tax NPV5% of $823 Million and IRR of 23.4%

Economic Studies

1

__________________ NEWS _________________

Vista Gold Announces Updated Preliminary Feasibility Study for the Mt Todd Gold Project

with Increased After-Tax NPV5% of $823 Million and IRR of 23.4%

Denver, Colorado, September 10, 2019 - Vista Gold Corp. (“Vista” or the “Company”) (NYSE American and TSX:

VGZ) today announced the positive results of an updated preliminary feasibility study (the “PFS”) for its Mt Todd gold

project (“Mt Todd” or the “Project”) in Northern Territory, Australia. The PFS is based on the results of metallurgical

optimization test work, a redesign of the fine grinding circuit, construction and ramp-up schedule changes and a

comprehensive review of all aspects of the Project, including an independent benchmarking study of key PFS

parameters. The process improvements have resulted in improved projected gold recovery and increased estimated

gold production at Mt Todd. All dollar amounts stated herein are in United States currency and are expressed as $

unless specified otherwise. References to A$ are to Australian dollars.

Highlights of the PFS for a 50,000 tonne per day (“tpd”) project include:

 After-tax NPV5% of $823 million and IRR of 23.4% at a $1,350 per ounce gold price and a $0.70=A$1.00

exchange rate (the “Base Case”);

 After-tax NPV5% of $1.15 billion and IRR of 30.3% at current prices and exchange rates ($1,500 per ounce

gold and $0.685=A$1.00 exchange rate);

 Unchanged proven and probable mineral reserves estimated to be 5.85 million ounces of gold (221.0 million

tonnes at 0.82 grams of gold per tonne (“g Au/t”)) at a cut-off grade of 0.40 g Au/t(1);

 Improved estimated annual production of 413,400 ounces of gold per year over the life of the Project, including

estimated average annual production of 495,100 ounces of gold per year during the first five years of

commercial operations;

 Life of mine projected average cash costs of $645 per ounce, including projected average cash costs of $575

per ounce during the first five years of commercial operations (life of mine average all-in sustaining cost

(“AISC”) of $746 per ounce, including average AISC of $688 per ounce during the first five years of

commercial operations);

 A projected 13-year mine life; and

 Estimated initial capital requirements of $826 million.

(1) See “Cautionary Note to United States Investors” below.

Vista’s President and CEO, Frederick H. Earnest, commented, “We believe the PFS has substantially de-risked Mt

Todd. The metallurgical programs and process area design changes completed by Vista over the past months have

confirmed our belief that Mt Todd can achieve excellent anticipated gold recoveries within an attractive operating

cost profile. This work, combined with an independent review of capital and operating costs and development

schedules, underpin our confidence that Mt Todd will become a major Australian gold producing project and provide

a solid foundation to further advance the Project.”

Trading Symbol: VGZ

NYSE American and Toronto Stock Exchanges

7961 Shaffer Parkway

Suite 5

Littleton, CO 80127

Phone: 720-981-1185

2

Mr. Earnest continued, “Vista’s management believes the PFS reflects significant value creation through Vista’s

optimization and development work. We believe project economics are strong at assumed long-term gold prices and

quite compelling at today’s market conditions. However, we do not believe Vista should develop Mt Todd on its own.

The PFS gives us a solid basis for conversations with prospective development partners who we believe will recognize

the value of Mt Todd and provide appropriate reward for Vista shareholders. To preserve the value of Mt Todd, we are

prepared to hold the project until a time when the value of the Project appropriately rewards shareholders.”

The PFS was authored by Tetra Tech Inc. (“Tetra Tech”) with Mine Development Associates, Resource Development

Inc., Proteus EPCM Engineers (a Tetra Tech Company, “Tetra Tech Proteus”), JDS Energy & Mining, Inc., and

POWER Engineers, Inc.

Vista’s senior management team is attendingthe Precious Metals Summit from September 10 to 13, 2019 in Beaver

Creek, CO and the Denver Gold Forum from September 16 to18, 2019 in Denver, CO, and will be available to discuss

these results at both conferences. A conference call and webcast to discuss highlights of the PFS will be held Thursday,

September 19, 2019 at 2:00 p.m. MDT.Call-in details are located at the end of this release.

Rex Bryan, Ph.D., Amy Hudson, Ph.D., April Hussey, P.E., Chris Johns, P.Eng., Guy Roemer, P.E., Vicki

Scharnhorst, P.E., Erik Spiller and Keith Thompson on behalf of Tetra Tech, Thomas Dyer on behalf of Mine

Development Associates, Dr. Deepak Malhotra on behalf of Resource Development Inc., Zvon Ponos on behalf of

Tetra Tech Proteus, Jessica Monasterio, P.E. on behalf of JDS Energy & Mining, Inc., each an independent Qualified

Person as defined by Canadian National Instrument 43-101 – Standards of Disclosure of Mineral Projects (“NI 43-

101”), prepared or supervised the preparation of the information that forms the basis for the scientific and technical

information disclosed herein and have reviewed this press release and consented to its release. Dr. Deepak Malhotra

has verified the metallurgical testing program and data in respect of the process improvements. For additional

information on data verification, quality assurance and control, key assumptions and other matters relating to the

Project, see Vista’s Annual Report Form 10-K as filed on SEDAR at www.sedar.com and on EDGAR at

www.sec.gov/edgar.shtml on February 25, 2019.

Overview

An overview of the PFS is presented in the table below.

50,000 tpd Base Case Years 1-5 Life of Mine

(13 years)

Annual

Average Total Annual

Average Total

Average Plant Feed Grade (g Au/t) 0.96 0.82

Payable Gold (000’s ozs) 495 2,476 413 5,305

Gold Recovery 92.3% 91.9%

Cash Costs ($/oz) $575 $645

AISC ($/oz) $688 $746

Strip Ratio (waste:ore) 2.65 2.52

Initial Capital (millions) $826

After-tax Payback (production years) 2.9

After-tax NPV5% (millions) $823

IRR (after-tax) 23.4%

Note: Economics presented using $1,350/oz gold and a flat $0.70 : A$1.00 exchange rate and assumes deferral of certain territory tax

obligations as well as realization of equipment salvage values at the end of the mine life.

3

Sensitivity Analysis

The following table provides additional details of the Project’s after-tax economics at variable gold prices and exchange

rate assumptions.

Foreign

Exchange

($/A$)

Gold Price

$1,200 $1,300 $1,350 $1,400 $1,500

IRR NPV5% IRR NPV5% IRR NPV5% IRR NPV5% IRR NPV5%

0.60 21.7% $686 26.4% $895 28.6% $994 30.8% $1,093 35.0% $1,297

0.65 19.2% $603 23.7% $807 25.9% $911 28.0% $1,011 32.2% $1,209

0.70 16.8% $521 21.2% $718 23.4% $823 25.5% $927 29.6% $1,126

0.75 14.6% $436 18.9% $634 20.9% $733 23.1% $839 27.1% $1,043

0.80 12.5% $351 16.7% $553 18.7% $650 20.7% $749 24.7% $954

Note: Changes in foreign exchange rates are only applied to operating costs and not applied to either initial or sustaining capital costs.

Capital Costs

Key capital expenditures for initial and sustaining capital requirements are identified in the following table.

Capital Expenditures (000s)

50,000 tpd Base Case Initial Capital Sustaining Capital

Mining $121,239 $406,347

Process Plant $366,693 $17,027

Project Services $109,204 $72,448

Project Infrastructure $26,220 $0

Site Establishment & Early Works $17,537 $0

Management, Engineering, EPCM Services $82,058 $0

Preproduction Costs $16,121 $0

Contingency $86,641 $40,354

Sub-Total $825,712 $536,176

Asset Sale and Salvage $0 ($139,631)

Total Capital $825,712 $396,545(1)

Total Capital Per Payable ounce gold $156 $75(1)

Notes: may not add due to rounding.

(1) Net of asset sales.

Operating Costs

Operating Cost

50,000 tpd Base Case

First 5 Years Life of Mine Cost

Per tonne

processed Per ounce Per tonne

processed Per ounce

Mining $6.51 $233.60 $6.02 $250.90

Processing $7.82 $280.78 $7.88 $328.48

Site General and Administrative $1.07 $38.57 $1.11 $46.43

Jawoyn Royalty $0.38 $13.50 $0.32 $13.50

Water Treatment $0.07 $2.35 $0.08 $3.53

Tailings Management $0.08 $2.71 $0.07 $3.07

Refining Costs $0.09 $3.20 $0.08 $3.22

Power Credit $0.00 $0.00 $-0.10 $-3.99

Total Cash Costs $16.01 $574.71 $15.48 $645.14

Note: Jawoyn Royalty and refinery costs calculated at $1,350 per ounce gold. May not add due to rounding.

4

Mining and Production

The mine plan contemplates that 221.0 million tonnes of ore containing an estimated 5.85 million ounces of gold at an

average grade of 0.82 g Au/t to be processed over the 13-year operating life of the Project. Total recovered gold is

expected to be 5.3 million ounces. Average annual gold production over the life of the Project is expected to be 413,400

ounces, averaging 495,100 ounces during the first five years of commercial operations, with 608,600 ounces produced

in the first year of commercial operation. Commercial production is anticipated to begin after two years of construction

and six months of commissioning and ramp-up.

The table below highlights the PFS production schedule.

Years Ore Mined

(kt)

Waste Mined

(kt)

Strip

Ratio

(W:O)

Milled Ore

(kt)

Milled

Grade

(g/t)

Contained

Ounces

(kozs)

Mill

Production

(kozs)

-1 2,859 8,802 3.08 - - - -

1 16,138 10,498 0.65 12,461 1.17 469 430

2 15,613 47,536 3.04 17,750 0.85 482 438

3 24,495 32,880 1.34 17,799 1.04 593 541

4 15,586 76,531 4.91 17,750 0.70 399 360

5 29,852 58,085 1.95 17,750 1.10 629 574

6 8,984 87,011 9.69 17,750 0.78 446 404

7 7,178 68,218 9.50 17,799 0.52 298 264

8 13,482 56,598 4.20 17,750 0.61 297 266

9 18,750 42,935 2.29 17,750 0.70 397 358

10 28,653 29,747 1.04 17,750 0.93 528 481

11 25,970 4,148 0.16 17,799 1.18 674 618

12 127 0 0 17,750 0.65 371 334

13 - - - 15,805 0.52 265 237

Total 207,687 522,990 2.52 221,041 0.82 5,848 5,305

Note: May not add due to rounding. Total milled ore includes material from the heap leach pad that is planned to be processed at the end of the mine life.

Project Mineral Resources and Reserves

The table below presents the estimated mineral resources and reserves for the Project. The effective date of the Batman

and Quigleys deposits mineral resource estimates is January 24, 2018. The effective date of the heap leach mineral

resource estimate is July 9, 2014.

Mt. Todd Gold Project Mineral Reserves – 50,000 tpd, 0.40 g Au/t cut-off and $1,250 per ounce gold

Batman Deposit Heap Leach Pad Quigleys Deposit Total

Tonnes

(000s)

Grade

(g/t)

Contained

Ounces

(000s)

Tonnes

(000s)

Grade

(g/t)

Contained

Ounces

(000s)

Tonnes

(000s)

Grade

(g/t)

Contained

Ounces

(000s)

Tonnes

(000s)

Grade

(g/t)

Contained

Ounces

(000s)

Proven 72,672 0.88 2,057 - - - - - - 72,672 0.88 2,057

Probable 135,015 0.82 3,559 13,354 0.54 232 - - - 148,369 0.79 3,791

Proven & Probable 207,687 0.84 5,616 13,354 0.54 232 - - - 221,041 0.82 5,848

5

Mt. Todd Gold Project Mineral Resources

Batman Deposit Heap Leach Pad Quigleys Deposit Total

Tonnes

(000s)

Grade

(g/t)

Contained

Ounces

(000s)

Tonnes

(000s)

Grade

(g/t)

Contained

Ounces

(000s)

Tonnes

(000s)

Grade

(g/t)

Contained

Ounces

(000s)

Tonnes

(000s)

Grade

(g/t)

Contained

Ounces

(000s)

Measured 77,725 0.88 2,191 - - - 457 1.27 19 78,182 0.88 2,210

Indicated 200,112 0.80 5,169 13,354 0.54 232 5,743 1.12 207 219,209 0.80 5,608

Measured &

Indicated 277,837 0.82 7,360 13,354 0.54 232 6,200 1.13 225 297,391 0.82 7,818

Inferred 61,323 0.72 1,421 - - - 1,600 0.84 43 62,923 0.72 1,464

Note: Measured & indicated mineral resources include proven and probable mineral reserves. Batman and Quigleys mineral resources are quoted at a 0.40g Au/t

cut-off grade. Heap Leach mineral resources are the average grade of the heap, no cut-off grade applied. Economic analysis conducted only on proven and

probable mineral reserves. Rex Bryan of Tetra Tech is the Qualified Person responsible for the geologic mineral resource estimates. Thomas Dyer of Mine

Development Associates is the Qualified Person responsible for developing mineral reserves for the Batman deposit. Dr. Deepak Malhotra of Resource Development

Inc. is the Qualified Person responsible for the metallurgical data and program, and for developing mineral reserves for the heap leach. See “Cautionary Note to

United States Investors” below.

Project Description

Gold mineralization in the Batman Deposit at the Project occurs in sheeted veins within silicified

greywackes/shales/siltstones. The Batman deposit strikes north-northeast and dips steeply to the east. Higher grade

zones of the deposit plunge to the south. The core zone is approximately 200-250 meters wide and 1.5 kilometers long,

with several hanging wall structures providing additional width to the deposit. Mineralization is open at depth as well

as along strike, although the intensity of mineralization weakens to the north and south along strike.

The Project is designed to be a conventional, owner-operated, open-pit mining operation that will utilize large-scale

mining equipment in a drill/blast/load/haul operation. Ore is planned to be processed in a comminution circuit

consisting of a gyratory crusher, two cone crushers, two high pressure grinding roll crushers, and primary grinding by

two ball mills and secondary grinding by 10 FLSmidth VXP mills. Vista plans to recover gold in a conventional

carbon-in-pulp recovery circuit.

Metallurgy, Processing and Infrastructure

Vista has completed extensive metallurgic test work that was announced in press releases dated August 2, 2018, January

9, 2019, April 8, 2019, May 29, 2019, and August 13, 2019.

Vista’s recent metallurgic test programs confirmed: (1) the efficiency of ore sorting across a broad range of head grades

and the natural concentration of gold in the screen undersize material prior to sorting; (2) the efficiency of fine grinding

and improved gold leach recoveries at an 80% passing grind size of 40 microns; and (3) the selection of FLSmidth

VXP mill as the preferred fine-grinding mill.

Benchmarking

Vista retained GR Engineering Services of Perth, Australia to undertake a benchmarking study to assess the

appropriateness of capital and operating cost estimates, construction and ramp-up schedules, owner’s costs and key

components of the Project, such as power supply. Vista has given thorough consideration to this study, resulting in

important changes to the costs and schedule of the Project.

6

Opportunities for Adding Value

In addition to the mineral reserves at the Batman Deposit, we estimate measured and indicated resources of 1.7 million

ounces gold (70.2 million tonnes at 0.77 g Au/t) and inferred resources of 1.4 million ounces gold (61.3 million tonnes

at 0.72 g Au/t). A portion of the inferred resources are contained within the existing pit design and are currently included

in the mine plan as waste material. Additional resources are predominantly at depth and lateral along strike. Potential

to convert part of the mineral resources to reserves represents an opportunity to improve existing LOM economics and

extend mine life.

The Company also has known mineral resources at the Quigleys Deposit, which is close to the planned processing

plant. The estimated grade of the Quigleys Deposit is higher than the estimated average grade of the Batman Deposit

and could provide a source of higher-grade feed in the mid years of the Project when higher stripping is encountered

and the average grade of feed to the plant is expected to decrease. Additional drilling and metallurgical testing are

required to develop mine plans and ultimately convert part of the Quigleys resource to proven or probable reserves.

Growth through exploration represents additional opportunity to add value at Mt Todd. Both the Batman Deposit and

Quigleys Deposit remain open. In addition, Vista controls over 1,100 sq. km of contiguous exploration licenses at the

southeast end of the Pine Creek Mining District. Various gold targets have been identified through early-stage, grass

roots exploration programs along the Cullen-Australis and Batman-Driffield structural corridors, the latter of which is

the host to the Batman Deposit. To-date, Vista’s exploration efforts have primarily focused on the Batman Deposit.

The PFS uses a natural gas price derived from east coast gas pricing. The Company believes that there would be a

significant opportunity to achieve a lower gas price upon commitment to a long-term gas delivery contract. This belief

is in part based on local expectations of significantly increased gas reserves in the Beetaloo Basin south of the Mt Todd

project. The Company is also considering additional optimization of the power plant.

Conference Call Details

A conference call and webcast to discuss highlights of the PFS will be held Thursday, September 19, 2019 at 2:00 p.m.

MDT.

Toll-free in North America: 844-898-8648

International: 647-689-4225

Confirmation Code: 2416449

This call will also be web-cast and can be accessed at the following web location:

Error! Hyperlink reference not

valid.http://event.on24.com/r.htm?e=2087023&s=1&k=D1D1D87054C6B0E6EBDA948F2FB3BC32

This call will be archived and available at www.vistagold.com after September 19, 2019. Audio replay will

be available for 14 days by calling toll-free in North America: 855-859-2056.

Detailed Report

An NI 43-101 compliant technical report will be filed on SEDAR and EDGAR within 45 days of the date hereof and

will be available on our website at that time. As part of the sensitivity analysis of the Project, Vista intends to complete

and present the results of an alternate 33,000 tpd project as part of the technical report.

7

About Vista Gold Corp.

The Company is a well-funded gold project developer. Our principal asset is our flagship Mt Todd gold project in

Northern Territory, Australia. Mt Todd is the largest known undeveloped gold project in Australia.

For further information, please contact Pamela Solly, Vice President of Investor Relations, at (720) 981-1185.

For more information about our projects, including technical studies and mineral resource estimates, please visit our

website at www.vistagold.com.

Forward Looking Statements

This press release contains forward-looking statements within the meaning of the U.S. Securities Act of 1933, as amended, and U.S. Securities

Exchange Act of 1934, as amended, and forward-looking information within the meaning of Canadian securities laws. All statements, other

than statements of historical facts, included in this press release that address activities, events or developments that Vista expects or anticipates

will or may occur in the future, including such things as, the Company’s continued work on the Mt Todd gold project; that process

improvements will result in lower operating costs, reduced power consumption, increased gold recovery and higher gold production; estimates

of mineral reserves and resources; projected project economics, including anticipated production, average cash costs, before and after-tax

NPV, IRR, capital requirements and expenditures, gold recovery after-tax payback, operating costs, average tonne per day milling, mining

methods procedures, estimated gold recovery, project design, and life of mine; that the Project is an advanced stage development project;

average annual production overtime; commencement of commercial production; timing for construction and commissioning; exploration of

new deposits at Mt Todd and the surrounding exploration areas; size of final product through the high pressure grinding roll crusher; potential

costs or savings related to gas price; ability to convert Quigleys estimated mineral resources to proven or probable mineral reserves; grade of

minerals at the Quigleys deposit; ability to add higher grade feed from the Quigleys deposit to the Project in its mid years; timing for and

completion of the NI 43-101 technical report for the PFS; and other such matters are forward-looking statements and forward-looking

information. The material factors and assumptions used to develop the forward-looking statements and forward-looking information contained

in this press release include the following: the accuracy of the results of the PFS, mineral resource and reserve estimates, and exploration and

assay results; the terms and conditions of our agreements with contractors and our approved business plan; the anticipated timing and

completion of a feasibility study on the Project; the anticipated receipt of required permits; no change in laws that materially impact mining

development or operations of a mining business; the potential occurrence and timing of a production decision; the anticipated gold production

at the Project; the life of any mine at the Project; all economic projections relating to the Project, including estimated cash cost, NPV, IRR,

and initial capital requirements; and Vista’s goal of becoming a gold producer. When used in this press release, the words “optimistic,”

“potential,” “indicate,” “expect,” “intend,” “plans,” “hopes,” “believe,” “may,” “will,” “if,” “anticipate,” and similar expressions are intended

to identify forward-looking statements and forward-looking information. These statements involve known and unknown risks, uncertainties

and other factors which may cause the actual results, performance or achievements of Vista to be materially different from any future results,

performance or achievements expressed or implied by such statements. Such factors include, among others, uncertainty of mineral resource

estimates, estimates of results based on such mineral resource estimates; risks relating to cost increases for capital and operating costs; risks

related to the timing and the ability to obtain the necessary permits, risks of shortages and fluctuating costs of equipment or supplies; risks

relating to fluctuations in the price of gold; the inherently hazardous nature of mining-related activities; potential effects on Vista’s operations

of environmental regulations in the countries in which it operates; risks due to legal proceedings; risks relating to political and economic

instability in certain countries in which it operates; as well as those factors discussed under the headings “Note Regarding Forward-Looking

Statements” and “Risk Factors” in Vista’s Annual Report Form 10-K as filed in February 2019 and other documents filed with the U.S.

Securities and Exchange Commission and Canadian securities regulatory authorities. Although Vista has attempted to identify important

factors that could cause actual results to differ materially from those described in forward-looking statements and forward-looking information,

there may be other factors that cause results not to be as anticipated, estimated or intended. Except as required by law, Vista assumes no

obligation to publicly update any forward-looking statements or forward-looking information; whether as a result of new information, future

events or otherwise.

Cautionary Note to United States Investors

The United States Securities and Exchange Commission (“SEC”) limits disclosure for U.S. reporting purposes to mineral deposits that a

company can economically and legally extract or produce. This press release uses the terms “Proven reserves” and “Probable reserves”.

Reserve estimates contained in this press release are made pursuant to NI 43-101 standards in Canada and do not represent reserves under the

standards of the SEC’s Industry Guide 7 and may not constitute reserves under the SEC’s newly adopted disclosure rules to modernize mineral

property disclosure requirements, which became effective February 25, 2019 and will be applicable to the Company in its annual report for

the fiscal year ending December 31, 2021. Under the currently applicable SEC Industry Guide 7 standards, a “final” or “bankable” feasibility

study is required to report reserves, the three-year historical average price is used in any reserve or cash flow analysis to designate reserves

and all necessary permits and government approvals must be filed with the appropriate governmental authority. Additionally, this press release

uses the terms “Measured resources”, “Indicated resources”, and “Measured & Indicated resources”. We advise U.S. investors that while

these terms are Canadian mining terms as defined in accordance with NI 43-101, such terms are not recognized under SEC Industry Guide 7

and normally are not permitted to be used in reports and registration statements filed with the SEC. Mineral resources described in this press

release have a great amount of uncertainty as to their economic and legal feasibility. The SEC normally only permits issuers to report

mineralization that does not constitute SEC Industry Guide 7 compliant “reserves” as in-place tonnage and grade, without reference to unit

8

measures. The term “contained gold ounces” used in this press release is not permitted under the rules of the SEC. “Inferred resources” have

a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that

any or all part of an Inferred resource will ever be upgraded to a higher category. U.S. Investors are cautioned not to assume that any part

or all of mineral deposits in these categories will ever be converted into SEC Industry Guide 7 reserves.