Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

VGZ.TO ·

Vista Gold Announces Feasibility Study Delivering 7 Million Ounce Gold Reserve Underpinning Large-Scale Production at High Operating Margins over a 16-Year Mine Life

Economic Studies

1

__________________ NEWS _________________

Vista Gold Announces Feasibility Study Delivering 7 Million Ounce Gold Reserve

Underpinning Large-Scale Production at High Operating Margins over a 16-Year Mine Life

Denver, Colorado, February 9, 2022 – Vista Gold Corp. (“Vista” or the “Company”) (NYSE American and TSX:

VGZ) today announced the results of the feasibility study (the “FS”) for its 100% owned Mt Todd gold project (“Mt

Todd” or the “Project”) in the Northern Territory, Australia (“NT”). Gold reserves increased 19% to 6.98 million

ounces resulting in average annual production of 479,000 ounces of gold during the first seven years of commercial

operations. With economics based on Q4 2021 costs, the Project is projected to deliver compelling cashflows over a

16-year mine life.

Highlights of the FS for a 50,000 tonne per day (“tpd”) project include:

 After-tax NPV5% of $999.5 million and IRR of 20.6% at a $1,600 gold price and a $0.71 Fx rate(1);

 After-tax NPV5% of $1.5 billion and IRR of 26.7% at a $1,800 gold price and $0.71 Fx rate;

 After-tax cash flow at a $1,800 gold price of $2.1 billion for years 1-7 of commercial operations;

 19% increase in proven and probable mineral reserves, now estimated to be 6.98 million ounces of gold (280.4

million tonnes at 0.77 grams of gold per tonne (“g Au/t”)) at a cut-off grade of 0.35 g Au/t; life of mine grade

to the grinding circuit after ore sorting of 0.84 grams of gold per tonne;

 Average annual life of mine production of 395,000 ounces, including average annual production of 479,000

ounces of gold during the first seven years of commercial operations;

 Life of mine average gold recovery of 91.6%;

 Average cash costs of $817 per ounce (life of mine), including average cash costs of $752 per ounce during

the first seven years of commercial operations(2);

 Average all-in sustaining cost (“AISC”) of $928 per ounce (life of mine), including average AISC of $860 per

ounce during the first seven years of commercial operations;

 Mine life of 16 years (increase of 3 years); and

 Initial capital requirements of $892 million (8% increase), which reflects the use of a third-party

owner/operator of the power plant.

(1) All dollar amounts stated herein are in U.S. currency and are expressed as $ unless specified otherwise. All foreign exchange (“Fx") rates are in U.S.

dollars per Australian dollar.

(2) Cash costs per ounce and AISC per ounce are non-GAAP financial measures. See “Note Regarding Non-GAAP Financial Measures” below for a

discussion on non-GAAP financial measures and a reconciliation to U.S. GAAP measures.

Vista’s President and CEO, Frederick H. Earnest, commented, “The FS affirms the strength of Mt Todd’s gold

production capacity and ability to deliver solid economic results at a time when inflationary pressures are having

significant impacts on operating mines and development projects alike. Completion of the FS represents another

major step in de-risking Mt Todd and readying the Project for development. The scale, quality of work completed and

location of Mt Todd, together with the FS and the fact that all major authorizations for development have been

obtained, distinguish Mt Todd as a unique development opportunity. We believe the results of the FS will appeal to

many potential partners, investors and lenders and allow us to evaluate a broad range of development alternatives as

we continue to focus on maximizing shareholder value. (CEO Video)

Trading Symbol: VGZ

NYSE American and Toronto Stock Exchanges

7961 Shaffer Parkway

Suite 5

Littleton, CO 80127

Phone: 720-981-1185

2

With Q4 2021 costs, the FS reflects the inflationary pressures being faced currently by all operators in the mining

industry. While we believe this inflationary trend is transitory, the resilience of Mt Todd is amply demonstrated by the

robust project economics reflected in the FS. Mt Todd’s attributes, together with the deep understanding of the various

Project components create valuable optionality in the approach to its development.

Mt Todd’s economic returns benefit from the increase in the gold reserve estimate, favorable results of the power

plant trade-off study and slightly lower energy costs in the NT. In view of the current gold price, we increased the

gold price used in the reserve estimate from $1,000 to $1,125 and changed the cut-off grade from 0.40 g Au/t to 0.35

g Au/t. These changes, while very conservative, significantly increased the reserve estimate from 5.85 million ounces

to 6.98 million ounces. Our power plant trade-off study identified a number of highly-credentialled, well-capitalized

power generating companies. Our decision to use a third-party power provider has resulted in important positive

impacts to our capital costs and insulates the Project from certain construction and operating risks while maintaining

what we believe to be attractive operating costs. While our operating costs have increased as a result of higher labor,

reagent, grinding media and over-the-fence power costs, our core energy costs yield some offsetting savings.

In addition to securing the approval of the Mining Management Plan since our last technical report, we have

modernized our agreement with the Jawoyn Aboriginal Association Corporation (the “Jawoyn”). We continue to

enjoy a close working relationship and their strong support for the Project. The economic returns reflect the increased

royalty to the Jawoyn (in lieu of the previous right to a 10% direct Project ownership) as reported in November

2020.”

Mr. Earnest concluded, “Our attention will now focus more intensely on increasing shareholder value and the

realization of the intrinsic value of Mt Todd. We believe Mt Todd’s location, scale, economics, permitting status,

and extensive technical work represent a unique near-term development opportunity and allow us to evaluate a broad

range of development partners, structures and alternatives as we continue to focus on maximizing shareholder value.”

Sabry Abdel Hafez, Ph.D., P.Eng., Rex Bryan, Ph.D., Amy Hudson, Ph.D, CPG, SME REM, April Hussey, P.E.,

Chris Johns, M.Sc., P.Eng., Max Johnson, P.E., , Vicki Scharnhorst, P.E., and Keith Thompson, CPG, member

AIPG, on behalf of Tetra Tech, Thomas Dyer, P.E., SME REM, on behalf of Respec, Dr. Deepak Malhotra, Ph.D.,

SME REM on behalf of Pro Solv, LLC, Zvonimir Ponos, BE, MIEAust, CPeng, NER on behalf of Tetra Tech

Proteus, are each a Qualified Person as defined under subpart 1300 of Regulation S-K under the United States

Securities Exchange Act of 1934, as amended (“S-K 1300”) and an independent Qualified Person as defined by

Canadian National Instrument 43-101 – Standards of Disclosure of Mineral Projects (“NI 43-101”), and prepared

or supervised the preparation of the information that forms the basis for the scientific and technical information

disclosed herein and have reviewed this press release and consented to its release. Dr. Deepak Malhotra has verified

the metallurgical testing program and data in respect of the process improvements. For additional information

applicable to the FS, including data verification, quality assurance and control, and key assumptions; and for other

matters relating to the Project, see Vista’s most recent Annual Report Form 10-K as filed on EDGAR at

www.sec.gov/edgar.shtml and on SEDAR at www.sedar.com.

Overview

The technical aspects of the FS are underpinned by extensive metallurgical testing and stringent design criteria that

continue to reflect Vista’s rigorous approach to ensuring Mt Todd will meet design and operating specifications. This

includes utilizing modern, proven technologies and oversizing processing equipment to best ensure throughput

capacity. The FS also incorporates provisions of the recently approved Mt Todd Mine Management Plan, which will

subsequently be amended to align with design changes in the FS.

A summary of the FS results is presented in the table below.

3

(1) Economics presented using $1,600/oz gold and a $0.71 Fx rate.

(2) Years 1 - 7 start after the 6 month commissioning and ramp up period.

(3) Life of Mine is from start of commissioning and ramp up through final closure.

(4) Post-sorted grinding circuit feed grade (g Au/t).

(5) Cash costs per ounce and AISC per ounce are non-GAAP financial measures. See “Note Regarding Non-GAAP Financial Measures”

below for a discussion on non-GAAP financial measures and a reconciliation to U.S. GAAP measures.

Sensitivity Analysis

The following table provides additional details of the Project’s after-tax economics at variable gold prices and exchange

rate assumptions. The Project economics are robust at the FS gold price of $1,600 per ounce and an Fx rate of $0.71

and even more compelling at today’s market conditions. Using a gold price of $1,800 per ounce and an Fx rate of

$0.71, the after-tax NPV5% is $1.5 billion and the IRR is 26.7%. For every $100 increase in gold price, the Project

NPV5% increases by approximately $230 million.

Note: NPV5% values in $ millions. Changes in Fx rates are only applied to operating costs and not applied to either initial or

sustaining capital costs.

Capital Costs

Management placed a high priority on managing capital costs while maintaining the operating cost benefits of a large-

scale project. Initial capital costs increased 8% and benefited from savings associated with a favorable trade-off study

that supports using a third-party power provider to build, own and operate the power plant at only modestly higher

power costs to the Project.

Capital expenditures for initial and sustaining capital requirements are summarized in the following table.

Life of Mine (3)

(16 years)

Average Plant Feed Grade (g Au/t)

(4) 1.01 0.84

Average Annual Gold Production (koz) 479 395

Average Recovery (%) 92.2% 91.6%

Total Payable Gold (koz) 3,353 6,313

Cash Costs ($/oz)

(5) $752 $817

AISC ($/oz)

(5) $860 $928

Strip Ratio (waste:ore) 2.77 2.51

Initial Capital (millions) $892

After-tax Payback (months) 47

After-tax NPV5% (millions) $999.5

IRR (after-tax) 20.6%

Years 1-7 (2)50,000 tpd Project (1)

Gold Price $1,300 $1,400 $1,500 $1,600 $1,700 $1,800 $1,900

FX Rate NPV (5) IRR (%) NPV (5) IRR (%) NPV (5) IRR (%) NPV (5) IRR (%) NPV (5) IRR (%) NPV (5) IRR (%) NPV (5) IRR (%)

0.74 $214 8.6 $453 12.4 $674 15.7 $911 19.0 $1,144 22.1 $1,372 25.0 $1,589 27.7

0.71 $304 10.2 $541 14.0 $762 17.3 $999.5 20.6 $1,229 23.7 $1,458 26.7 $1,674 29.4

0.68 $393 11.9 $626 15.6 $851 19.0 $1,085 22.3 $1,313 25.7 $1,543 28.5 $1,758 31.3

4

Note: Components may not add to totals due to rounding.

Operating Costs

Operating costs continue to benefit from the economies of scale associated with a 50,000 tonne per day process plant,

a low 2.5:1 stripping ratio (unchanged from the last technical report), and a locally-based labor force. Operating costs

were impacted by the additional royalty granted to the Jawoyn in exchange for their prior right to a 10% participating

interest in the Project.

Note: Jawoyn royalty and refinery costs calculated at $1,600 per ounce gold and $0.71 exchange rate. May not add to totals due to rounding.

(1) Cash costs per tonne processed and cash costs per ounce are non-GAAP financial measures. See “Note Regarding Non-GAAP Financial

Measures” below for a discussion on non-GAAP financial measures and a reconciliation to U.S. GAAP measures.

Mining and Production

The mine plan contemplates that 280.4 million tonnes of ore, containing an estimated 6.98 million ounces of gold at an

average grade of 0.77 g Au/t, will be processed over the life of the Project. Total recovered gold is expected to be 6.31

million ounces with average annual gold production expected to be 395,000 ounces. Average annual production over

the first seven years of commercial operations is expected to be 479,000 ounces. The Company expects commercial

production to commence after two years of construction and six months of commissioning and ramp-up.

Mining $81 $531

Process Plant $474 $28

Project Services $56 $89

Project Infrastructure $45 $8

Site Establishment & Early Works $24 $0

Management, Engineering, EPCM Services $100 $0

Preproduction Costs $27 $0

Contingency $86 $44

Sub-Total $892 $700

Asset Sale and Salvage $0 ($37)

Total Capital $892 $663

Total Capital Per Payable ounce gold $141 $105

Capital Expenditures 50,000 tpd Project Initial Capital

($ millions)

Sustaining

Capital

($ millions)

50,000 tpd Project

Operating Cost Per tonne

processed Per ounce Per tonne

processed Per ounce Per tonne

processed Per ounce

Mining $8.52 $315.97 $6.14 $323.60 $6.79 $301.55

Processing $9.39 $348.23 $9.38 $494.68 $9.44 $419.35

Site General and Administrative $1.06 $39.19 $0.94 $49.61 $0.99 $44.04

Water Treatment $0.26 $9.81 $0.24 $12.91 $0.29 $13.10

Tailings Management $0.08 $3.10 $0.08 $4.41 $0.08 $3.74

Refining $0.09 $3.45 $0.07 $3.50 $0.08 $3.48

Jawoyn Royalty $0.86 $32.00 $0.61 $32.00 $0.72 $32.00

Total Cash Costs (1)

$20.28 $751.75 $17.47 $920.71 $18.40 $817.25

Life of Mine CostYears 1-7 Years 8-14

5

The table below highlights the FS production schedule. The shaded portion of the table demonstrates the benefit of

sorting that reduces the tonnage processed by 10%, increases the processed grade by a similar percentage, and results

in cost savings for grinding, leaching and tailings handling.

(*) Six months commissioning and ramp-up period ahead of full production.

(1) Years 16 and 17 process Heap Leach ore after the pit ore is exhausted.

(2) Components may not add to totals due to rounding.

As demonstrated in the chart below, the 19% increase in gold reserves sustains a strong production profile over the first

seven years with an average of 479,000 ounces of gold per year. The Project also benefits from three additional years

of mine life. This reserve growth successfully offsets much of the inflationary pressure on capital and operating costs

currently affecting the entire mining sector. The Company believes resource conversion and exploration during the

early years of the Project will contribute to improved gold production in years 9 through 11 and further extend the life

of the Project.

Years Pit Ore

Mined

(kt)

Waste

Mined

(kt)

Ore

Crushed

(kt)

Crushed

Grade

(g/t)

Contained

Ounces

(kozs)

Ore to CIP

(Post Sorting)

(kt)

CIP Grade

(g/t)

Contained

Ounces

(kozs)

Gold

Produced

(kozs)

Recovery

(%)

-1 7,188 14,066 0 0 0 0 0.00 0 0 0

1(*) 18,216 25,904 12,334 1.10 436 11,100 1.21 431 399 92.6%

2 30,578 38,623 17,750 0.88 503 15,975 0.97 497 458 92.1%

3 19,696 63,199 17,750 1.04 594 15,975 1.14 587 542 92.5%

4 15,218 69,774 17,799 0.66 378 16,019 0.73 373 341 91.3%

5 27,591 66,264 17,750 0.79 451 15,975 0.87 445 408 91.7%

6 25,499 74,510 17,823 1.03 591 16,041 1.13 583 539 92.4%

7 13,229 77,291 17,750 0.97 554 15,975 1.06 546 504 92.3%

8 7,779 71,277 17,774 0.69 392 15,997 0.75 386 352 91.2%

9 13,866 59,499 17,774 0.52 295 15,997 0.57 291 261 89.8%

10 14,523 50,082 17,750 0.55 312 15,975 0.60 308 277 90.1%

11 20,830 40,490 17,750 0.61 347 15,975 0.67 343 311 90.7%

12 18,523 13,685 17,774 0.72 410 15,997 0.79 404 370 91.4%

13 11,307 4,388 17,774 0.76 433 15,997 0.83 428 391 91.6%

14 13,829 1,866 17,750 0.79 448 15,975 0.86 442 406 91.7%

15 9,149 412 17,750 0.78 446 16,120 0.85 440 403 91.6%

16 (1) 0 0 16,710 0.64 344 15,968 0.66 341 310 90.7%

17 (1)

0 0 2,612 0.54 45 2,612 0.54 45 41 89.8%

Total (2)

267,021 671,331 280,375 0.77 6,979 253,673 0.84 6,891 6,313 91.6%

6

Operating Margin Summary

Note: Cash operating costs is a non-GAAP financial measure. See “Note Regarding Non-GAAP Financial Measures” below for a discussion

on non-GAAP financial measures and a reconciliation to U.S. GAAP measures.

7

Mineral Resources and Mineral Reserves

The tables below present the estimated mineral resources and mineral reserves for the Project. The effective date of the

mineral resources and mineral reserves estimates is December 31, 2021. The following mineral resources and mineral

reserves were prepared in accordance with both S-K 1300 standards and Canadian Institute of Mining, Metallurgical

and Petroleum definition standards.

Notes:

1) Measured & Indicated Mineral Resources include Proven and Probable Reserves.

2) Batman and Quigleys mineral resources are quoted at a 0.40g-Au/t cut-off grade. Heap Leach resources are the average grade of the heap, no cut-off

applied.

3) Batman: Mineral resources constrained within a $1,300/oz gold Whittle TM pit shell. Pit parameters: Mining Cost $1.50/tonne, Milling Cost $7.80/tonne

processed, G&A Cost $0.46/tonne processed, G&A/Year 8,201 K US4, Au Recovery, Sulfide 85%, Transition 80%, Oxide 80%, 0.2g-Au/t minimum for

resource shell.

4) Quigleys: Resources constrained within a $1,300/oz gold Whittle TM pit shell. Pit parameters: Mining cost $1.90/tonne, Processing Cost $9.779/tonne

processed, Royalty 1% GPR, Gold Recovery Sulfide, 82.0% and Ox/Trans 78.0%, water treatment $0.09/tonne, Tailings $0.985/tonne.

5) Differences in the table due to rounding are not considered material. Differences between Batman and Quigleys mining and metallurgical parameters are

due to their individual geologic and engineering characteristics.

6) Rex Bryan of Tetra Tech is the QP responsible for the Statement of Mineral Resources for the Batman, Heap Leach Pad and Quigleys deposits.

7) Thomas Dyer of RESPEC is the QP responsible for developing the resource WhittleTM pit shell for the Batman Deposit.

8) The effective date of the Heap Leach, Batman and Quigleys resource estimate is December 31, 2021.

9) Mineral resources that are not mineral reserves have no demonstrated economic viability and do not meet all relevant modifying factors.

Notes:

1) Thomas L. Dyer, P.E., is the QP responsible for reporting the Batman Deposit Proven and Probable Mineral Reserves.

2) Batman deposit mineral reserves are reported using a 0.35 g Au/t cutoff grade.

3) Deepak Malhotra is the QP responsible for reporting the heap-leach pad mineral reserves.

4) Because all the heap-leach pad reserves are to be fed through the mill, these mineral reserves are reported without a cutoff grade applied.

5) The mineral reserves point of reference is the point where material is fed into the mill.

6) The effective date of the mineral reserve estimates is December 31, 2021.

Project Description

Gold mineralization in the Batman Deposit occurs in sheeted veins within silicified greywackes/shales/siltstones. The

Batman deposit strikes north-northeast and dips steeply to the east. Higher grade zones of the deposit plunge to the

south. The core zone is approximately 200-250 meters wide and 1.5 kilometers long, with several hanging wall

structures providing additional width to the deposit. Mineralization is open at depth as well as along strike, although

the intensity of mineralization weakens to the north and south along strike.

Tonnes Grade Tonnes Grade Tonnes Grade Tonnes Grade

(000s) (g/t) (000s) (g/t) (000s) (g/t) (000s) (g/t)

Measured (M) 77,725 0.88 2,191 - - - 594 1.15 22 78,319 0.88 2,213

Indicated (I) 200,112 0.80 5,169 13,354 0.54 232 7,301 1.11 260 220,767 0.80 5,661

Measured &

Indicated 277,837 0.82 7,360 13,354 0.54 232 7,895 1.11 282 299,086 0.82 7,874

Inferred (F) 61,323 0.72 1,421 - - - 3,981 1.46 187 65,304 0.77 1,608

Mt Todd Gold Project - Mineral Resources

Contained

Ounces

(000s)

Contained

Ounces

(000s)

Contained

Ounces

(000s)

Total

Contained

Ounces

(000s)

Batman Deposit Heap Leach Pad Quigleys Deposit

Tonnes

(000)

Grade

(g/t)

Contained

Ounces

(000)

Tonnes

(000)

Grade

(g/t)

Contained

Ounces

(000)

Tonnes

(000)

Grade

(g/t)

Contained

Ounces

(000)

Proven 81,277 0.84 2,192 - - - 81,277 0.84 2,192

Probable 185,744 0.76 4,555 13,354 0.54 232 199,098 0.75 4,787

Mt Todd Gold Project - Mineral Reserves - 50,000 tpd, 0.35g Au/t cutoff and US$1,125 per ounce LG Pit

0.77 6,979Proven & Probable

Batman Deposit Heap Leach Pad Total P&P

267,021 0.79 6,747 13,354 0.54 232 280,375

8

The Project is designed to be a conventional, owner-operated, open-pit mining operation that will utilize large-scale

mining equipment in a drill/blast/load/haul operation. The Company continues to evaluate the potential use of contract

mining and/or autonomous truck haulage. Ore is planned to be processed in a comminution circuit consisting of a

gyratory crusher, two cone crushers, two high pressure grinding roll crushers with primary grinding by two ball mills

and secondary grinding by 10 FLSmidth VXP mills. Vista plans to recover gold in a conventional carbon-in-pulp

recovery circuit.

Opportunities for Adding Value

Additional resources are predominantly at depth and lateral along strike. A portion of the Inferred Mineral Resources

are contained within the existing pit design and are currently included in the mine plan as waste material. Potential to

convert part of the mineral resources to mineral reserves represents an opportunity to improve existing LOM economics

and extend mine life.

The Company also has known mineral resources at the Quigleys Deposit, which is close to the planned processing

plant. The estimated grade of the Quigleys Deposit is higher than the estimated average grade of the Batman Deposit

and could provide a source of higher-grade feed in the mid years of the Project when the average grade of feed to the

plant is expected to decrease. Additional drilling and metallurgical testing are required to develop mine plans and

ultimately establish proven and probable mineral reserves at the Quigleys deposit.

Growth through exploration represents additional opportunity to add value at Mt Todd. Both the Batman Deposit and

Quigleys Deposit remain open. Recent drilling demonstrates the continuity of mineralization between these two

deposits. In addition, Vista controls over 1,500 sq. km of contiguous exploration licenses at the southeast end of the

Pine Creek Mining District. Various gold targets have been identified through early-stage, grass roots exploration

programs along the Cullen-Australis and Batman-Driffield structural corridors, the latter of which is the host to the

Batman Deposit. To-date, Vista’s exploration efforts have primarily focused on the Batman Deposit.

The FS uses a natural gas price comparable to other facilities that self-generate power in the NT. Due to the location of

the Project and its close proximity to the main NT natural gas transmission line, the Company believes that there is

significant opportunity to achieve a lower natural gas price upon commitment to a long-term gas delivery contract. This

belief is in part based on local expectations of significantly increased gas reserves in the Beetaloo Basin south of Mt

Todd.

Conference Call Details

A conference call and webcast to discuss highlights of the FS will be held Wednesday, February 9, 2022 at 4:00 p.m.

EDT (2:00 p.m. MDT).

Toll-free in North America: 844-898-8648

International: 647-689-4225

Confirmation Code: 5074108

To participate in the webcast and view the slide presentation, please follow the steps below at least 15 minutes prior

to the start time:

Step 1 – Registration Page:

https://onlinexperiences.com/Launch/QReg/ShowUUID=803ED6AB-ABDC-4C7F-B282-A98D4DCB25D7

Step 2 – Login Page:

https://onlinexperiences.com/Launch/Event/ShowKey=187237