Viva Gold Increases Gold Resource and Extends Mineralization at its Tonopah Gold Project in Nevada
NR 22-2
Viva Gold Increases Gold Resource and Extends Mineralization at its Tonopah
Gold Project in Nevada
VANCOUVER, BC – January 25, 2022 – Viva Gold Corp. ( TSX-Venture: VAU; OTCQB: VAUCF ) (the
“Company” or “Viva”) is pleased to provide an updated NI43-101 compliant mineral resource estimate
for the Tonopah gold project (“Tonopah”), located near Tonopah, Nevada, on the prolific Walker Lane
gold trend. The new resource estimate is based on the addition of 19 new dri llholes completed in 2020
and 2021, updated geologic modelling and statistical analysis.
“We are very pleased with these results. Total pit constrained measured and indicated gold resource
increased 21% over prior estimates to 394,000 ounces with an ad ditional inferred resource of 206,000
ounces, a 1 4% increase. Our 2020 and 2021 drill programs added 68,000 ounces of measured and
indicated and 25,000 ounces of inferred resource at a cost of US$12.25/ounce. This demonstrates our
ability to add ounces of new gold resource at Tonopah at a very low cost. More importantly, this recent
drilling increased our understanding of the geometry of the currently defined Tonopah gold deposit and
indicates that the mineralization remains strongly open, at relatively sha llow depths, in at least two
directions. Our near-term future focus will be to drill test these newly identified areas for further resource
expansion,” states James Hesketh, President & CEO.
The updated pit-constrained mineral resource estimate for the Tonopah Project follows:
Donald E. Hulse, P.E., SME -RM, Senior Mining Consultant for WSP USA of Lakewood, Colorado, is the
independent Qualified Person responsible for the preparation of the resource estimate. Resources are
not reserves, and do not include modifying factors which need to be considered to determine whether
they are economically viable.
Mineral resources are tabulated at a cutoff grade of 0. 15 g/t gold for argillite and 0.2 0 g/t for volcanic
hosted mineralization, which constitutes a reasonable prospect for eventual economic extraction based
on a comparison with similar gold deposits in Nevada, and constrained within a US$1,650 gold price pit
shell using a 45-degree average pit slope in all rock types and a 35-degree pit slope for gravels overburden.
The new model uses three modelled domains; lower Palmetto argillite zon e (OP), a weathered argillite
zone of 10 meters thickness at the argillite/volcanic contact (OP -W), and a lower tertiary volcanic (TVL)
zone. Estimates were interpolated using ordinary kriging and a 20 g/t grade cap.
Tonnes Gold Grade Contained
(x1,000) Grams/Tonne Ounces
Measured 4,764 0.830 127,000
Indicated 11,440 0.727 267,000
Measured and Indicated 16,204 0.782 394,000
Inferred 7,352 0.872 206,000
Following is a sensitivity table showing the impact of changing cutoff grade on resource by category:
With additional drilling in 2020, it became apparent that the mineral continuity at Tonopah is controlled
by multiple factors, which are different in the TVL than in the underlaying OP. The OP exhibits local north-
north-west continuity, along a regional east-south-east trend, while mineralization in the lower volcanics
exhibit the dominant east -south-east trend with limited expression on the north -north-west trend.
Previously, all mineralization had been modelled along the north-north-west trend. Based on drill results,
it can also be observed that the primary mineralized trend follows the OP/TVL contact in a zone ranging
between 30- and 60-meters width. A zone of +/ - 10 meters around the OP/TVL contact was treated as a
separate domain in the model. These modifications to the mineral trends and the addition of lithologic
domains developed clean variography and resulted in a well-supported resource model.
Step-out holes were drilled in 2021 to test these observations and were highly successful in intercepting
high-grade mineralization. These holes contributed to an increase in inferred mineralization and helped
to extend the pit shell to the east -south-east along the principal (110 azimuth) trend of the deposit. The
pit also extended to the west along trend based on new drill intercepts from the 2020 drill program. The
new model also developed a small pit in the Midway Hills area of the project, located approximately 1.0
kilometers west from the main pit on trend, indicating that the revised geologic model is doing a better
job of correlating and connecting existing assay intercepts in that area. In addition, the new model also
Classification Cutoff Grade Tonnes Gold Grade Contained
Grams/Tonne (x 1,000) Grams/Tonne Ounces
1.00 951 2.214 67,700
Measured 0.70 1,608 1.645 85,000
0.40 3,194 1.082 111,000
0.20 4,764 0.83 127,000
0.15 4,895 0.813 128,000
1.00 2,157 1.521 105,000
Indicated 0.70 4,339 1.171 163,000
0.40 8,773 0.853 241,000
0.20 11,397 0.729 267,000
0.15 11,655 0.717 269,000
1.00 2,483 1.461 117,000
Inferred 0.70 3,929 1.235 156,000
0.40 6,034 0.995 193,000
0.20 7,322 0.875 206,000
0.15 7,479 0.86 207,000
indicates the possibility of two additional parallel trends t o the south of this main zone. The previously
modelled south zone currently develops three small interconnected pit bottoms along the east -south-
east trend and the third most southerly zone is potentially identified by three drillholes.
We anticipate that the 12 June 2020 NI43-101 Technical Report Preliminary Economic Assessment for the
Tonopah Project will be incorporated by reference in a new NI43 -101 detailing this updated resource
estimate.
James Hesketh, MMSA -QP, has approved the scientific and tech nical disclosure contained in this press
release. Mr. Hesketh is not independent of the Company; he is an Officer and Director.
About Viva Gold Corp:
Viva Gold Corp holds 100% of the Tonopah Gold Project, a large land position consisting of
approximately 10,500 acres on the prolific Walker Lane Trend in western Nevada, 30 kilometers
south-east of the World class Round Mountain mine. The project has a me asured and indicated
contained mineral gold resource of 394,000 ounces at a gold grade of 0.7 8 grams/tonne and
206,000 ounces of Inferred resource at 0.87 grams/tonne. Viva is advancing the project towards
feasibility and permitting.
Viva is committed to Environmental, Social and Responsible Governance (“ESG”) of its business.
We realize these issues are also important to investors. We strive to operate in a manner that
supports environmental and social initiatives and responsible corporate governance. Viva made
significant progress in 2021 in working with its regulators to advance the environmental and social
baseline study efforts required to support future Mining Plan of Operations review under the National
Environmental Policy Act for the Project, and other Nevada State environmental permitting requirements.
These efforts demonstrate our focus and commitment to de -risk and add value as detailed in our
December 7, 2021 press release.
Viva Gold trades on the TSX Venture exchange “VAU”, on the OTCQB "VA UCF" and on the
Frankfurt exchange "7PB". Viva has a tight capital structure with 55.6 million shares outstanding
and a strong management team and board with both gold exploration and production
experience. Viva is building market awareness as the Company advances the high -grade
Tonopah Gold Project. For additional information on Viva Gold and the Tonopah Gold Project, please
visit our website: www.vivagoldcorp.com.
For further information please contact:
James Hesketh, President & CEO
(720) 291-1775
Valerie Kimball, Director Investor Relations
(720) 933-1150
Renmark Financial Communications Inc.
Daniel Gordon: [email protected]
Tel: (416) 644-2020 or (212) 812-7680
www.renmarkfinancial.com
Forward-Looking Information:
This news release contains certain information that may constitute forward -looking information or forward-looking
statements under applicable Canadian securities legislation (collectively, “forward -looking information”), including
but not limited to drilling operations and estimates of gold mineral resource at the Tonopah Gold Project. This
forward-looking information entails various risks and uncertainties that are based on current expectations, and
actual results may differ materially from those contained in such information. These uncertainties and risks include,
but are not limited to, the strength of the global economy, inflationary pressures, pandemics, and permitting issues
related to ESG initiatives; the price of gold; operational, funding and liquidity risks; the potential for achieving
targeted drill results, the degree to which mineral resource estimates are reflective of actual mineral resources; the
degree to which factors which would make a mineral deposit commercially viable are present; the risks and hazards
associated with drilling and mining operations; and the ability of Viva to fund its capital requirements. Risks and
uncertainties about the Company’s business are more fully discussed in the Company’s disclosure materials filed with
the securities regulatory authorities in Canada available at www.sedar.com. Readers are urged to read these
materials. Viva assumes no obligation to update any forward -looking information or to u pdate the reasons why
actual results could differ from such information unless required by law.
Cautionary Note to U.S. Investors --- The United States Securities and Exchange Commission permits U.S. mining
companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and
legally extract or produce. We use certain terms in this rep ort, such as "measured," "indicated," "inferred," and
"resources," that the SEC guidelines strictly prohibit U.S. registered companies from including in their filings with the
SEC.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.