Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

USA.TO ·

Americas Silver Reports Second Quarter Production Results and Relief Canyon Construction Update

Production Results Mine Development & Operations

1 

AMERICAS SILVER REPORTS SECOND QUARTER PRODUCTION RESULTS AND RELIEF CANYON 

CONSTRUCTION UPDATE 

TORONTO,  ONTARIO—July  30,  2019—Americas  Silver  Corporation  (TSX:  USA)  (NYSE  American:  USAS) 

(“Americas Silver” or the “Compa ny”), a growing North American  precious metals producer, announces 

Q2,  2019  production  and  operating  cost  results  on  a  consolidated  and  individual  basis  for  its  Cosalá 

Operations and Galena Complex and a construction update on the Relief Canyon gold mine.  All figures are 

in U.S. dollars. 

Second Quarter Highlights 

 Consolidated silver production of approximately 1.7 million silver equivalenti ounces and 345,695 silver 

ounces, representing an increase of 15% year‐over‐year to both silver and silver equivalent.  

 Consolidated cash costsii were approximately $8.28 per silver ounce and consolidated all‐in sustaining 

costs (“AISC”) were approximately $16.15 per silver ounce, both  representing an increase year‐over‐

year and from the prior quarter. These increased costs were primarily the result of lower realized prices 

for zinc and lead and lower production at the Galena Complex. 

 For the first half of 2019, consolidated silver production of a pproximately 3.4 million silver equivalent 

ounces and 740,000 silver ounces with consolidated cash costs of approximately $3.60 per silver ounce 

and consolidated AISC of approximately $10.50 per silver ounce. 

 Guidance for 2019 remains unchanged  at 1.6 – 2.0  million silver   ounces and 6.6 – 7.0 million silver 

equivalent ounces at cash costs of $4.00 to $6.00 per silver ou nce and AISC of $10.00 to $12.00 per 

silver ounce. The Company expects to release its second quarter  financial results on or before August 

14, 2019. 

 Construction is proceeding as expected at the Relief Canyon Mine with leach pad activities progressing, 

mobilization of the mining contractor expected later this week and all fabrication work on the crusher 

and conveyors progressing to meet scheduled delivery in the third quarter. First gold pour is expected 

in late Q4, 2019. 

 Milled tonnage at the Cosalá Operations increased by 13% year‐o ver‐year, with the San Rafael mine 

sustaining an average milling rate of approximately 1,750 tonnes per operating day during the quarter, 

resulting in production of approximately 1.3 million silver equ ivalent ounces, including approximately 

145,000 silver ounces. Cash costs were approximately negative ($18.27) per silver ounce and AISC were 

approximately negative ($11.66) per silver ounce, representing increases of 70% and 72%, respectively, 

when  compared  to  prior  year,  largely  due  to  lower  zinc  and  lead  prices  and  higher  treatment  and 

refining charges.  

 The  Galena  Complex  produced  approximately  383,000  silver  equiva lent  ounces,  including 

approximately  200,000  silver  ounces ,  representing  decreases  of  3%  and  9%,  respectively,  when 

compared  to  Q2,  2018.  Cash  costs  were  approximately  $27.55  per  silver  ounce  and  AISC  were 

approximately  $36.35  per  silver  ounce,  representing  increases  of  50%  and  36%,  respectively,  when 

compared  to  the  same  period.  These  increases  were  largely  due  to  a  focus  on  development  over 

production given low metals prices during the quarter.  

“The Company remains on target to achieve its full year production and cost guidance despite the expected 

lower production from the Galena Complex and lower realized metal prices in the quarter,” said Americas 

Silver President and CEO Darren Blasutti. “The second half of 2 019 will be a very exciting period for our 

Company as we expect not only higher silver production, but mos t importantly, first gold pour from the 

Relief Canyon Mine.”   

2 

Consolidated Second Quarter Production Details 

Consolidated silver production for the second quarter of 2019 w as 345,695 ounces and silver equivalent 

production  was  approximately  1.7  million  ounces,  an  increase  of  15%  year‐over‐year  for  both  metrics. 

Consolidated cash costs increased 235% to $8.28 per silver ounce year‐over‐year and AISC increased 199% 

to $16.15 per silver ounce compared year‐over‐year. Consolidated zinc production increased by 27% year‐

over‐year, while consolidated lead production increased by 16% year‐over‐year. 

Table 1 

Consolidated Production Highlights 

   Q2 2019  Q2 2018  Change  Q1 2019  Change 

Processed Ore (tonnes milled)  186,310  164,313  13%  182,029  2% 

Silver Production (ounces)  345,695  301,711  15%  393,824  ‐12% 

Silver Equivalent Production (ounces)  1,683,358  1,462,170  15%  1 ,754,839  ‐4% 

Silver Grade (grams per tonne)  76  77  ‐1%  87  ‐13% 

Cost of Sales ($ per equiv. ounce silver)  $8.75  $8.20  7%  $7.11  23% 

Cash Costs ($ per ounce silver)   $8.28  ($6.15)  >100%  ($0.50)  >100% 

All‐in Sustaining Costs ($ per ounce silver)   $16.15  $5.40  >100%  $5.54  >100% 

Zinc Production (pounds)  11,150,174  8,756,201  27%  11,263,623  ‐1 % 

Lead Production (pounds)  7,237,607  6,216,592  16%  8,211,429  ‐12%  

Cosalá Operations Production Details 

The Cosalá Operations produced 145,410 ounces of silver during the second quarter of 2019 and 1.3 million 

ounces of silver equivalent during the same period at cash cost s of negative ($18.27) per silver ounce and 

AISC  of  negative  ($11.66)  per  silver  ounce.  Silver  production  increased  by  54%  while  silver  equivalent 

production increased by 25% over the prior year, respectively.  Cash costs and AISC increased by 70% and 

72%, respectively, compared to Q2, 2018, despite significant increases in zinc and lead production.  

Table 2 

Cosalá Operations Highlights 

   Q2 2019  Q2 2018  Change  Q1 2019  Change 

Processed Ore (tonnes milled)  156,998  138,708  13%  152,605  3% 

Silver Production (ounces)  145,410  94,231  54%  173,169  ‐16% 

Silver Equivalent Production (ounces)  1,300,009  1,041,246  25%  1 ,322,045  ‐2% 

Silver Grade (grams per tonne)  49  42  17%  57  ‐14% 

Cost of Sales ($ per equiv. ounce silver)   $5.51  $5.36  3%  $4.34  27% 

Cash Costs ($ per ounce silver)   ($18.27)  ($60.13)  ‐70%  ($30.48)  ‐40% 

All‐in Sustaining Costs ($ per ounce silver)   ($11.66)  ($41.66)  ‐72%  ($25.85)  ‐55% 

Zinc Production (pounds)  11,150,174  8,756,201  27%  11,263,623  ‐1 % 

Lead Production (pounds)  4,052,559  2,982,316  36%  4,626,233  ‐12%  

Strong results were driven by sustained improvements in grade,  mill throughput and metal recovery as 

mining and milling operations generally expanded at San Rafael  in Q2, 2019 compared to Q2, 2018.  Ore 

production from the Main Zone benefited from additional working headings providing greater operational 

flexibility.  

3 

Silver  and  lead  head  grades  in  Q2,  2019  were  lower  compared  to Q1,  2019  with  steady  zinc  grades 

consistent  with  the  Mining  Plan  though  expected  to  be  slightly lower  in  the  second  half  of  2019.  Any 

potential reduction in head grades over the remainder of the ye ar are expected to be largely offset by 

further gains in mill throughput and metal recovery as additional flotation capacity was installed during the 

second quarter with increased recoveries. 

The increase in cash costs and AISC were largely the result of  higher treatment and refining charges and 

lower market prices for both zinc and lead during the quarter.  Operating costs and capital expenditures 

remain in line with management expectations. 

Development of the incline ramp toward the Upper Zone continues  to advance with the expectation of 

accessing the area prior to the end of the year. 

 Galena Complex Production Details  

As previously noted in Q1, 2019, two high‐tonnage stopes were i mpacted by separate ground falls in late 

Q1,  2019  with  follow‐on  impact  in  Q2,  2019.  The  remaining  active  stopes  were  unable  to  replace  the 

tonnage  loss  associated  with  the  impacted  areas.   Due  to  these issues,  the  Galena  Complex  produced 

200,285 ounces of silver during Q2 2019 and 383,349 ounces of s ilver equivalent at cash costs of $27.55 

per silver ounce and AISC of $36.35 per silver ounce.  Silver and silver equivalent production decreased by 

9% and 11%, respectively, compared to the prior quarter, and 3%  and 9%, respectively, year‐over‐year. 

Both cash costs and AISC represe nted an increase of 20% due to  the noted lower production and lower 

lead prices during the quarter.  

In order to improve mining flexibility, the Galena team priorit ized underground development and gained 

over 1,600 feet of advance durin g the quarter. New production a reas were established on the 2400 and 

3200 levels.  In addition, ongoing exploration activities conti nue to yield encouraging results which could 

benefit  production in the near term.   Specifically, drilling on  the 4900 level has identified  new zones of 

mineralization (129 and 130 Veins) near existing infrastructure and further extended the strike and vertical 

extent of known resources (137, 146, 167, 168 and 168HW Veins). 

Table 3 

Galena Complex Highlights 

   Q2 2019  Q2 2018  Change  Q1 2019  Change 

Processed Ore (tonnes milled)  29,312  25,605  14%  29,424  0% 

Silver Production (ounces)  200,285  207,480  ‐3%  220,655  ‐9% 

Silver Equivalent Production (ounces)  383,349  420,924  ‐9%  432,7 94  ‐11% 

Silver Grade (grams per tonne)  220  263  ‐16%  242  ‐9% 

Cost of Sales ($ per equiv. ounce silver)  $19.75  $15.24  30%  $15 .55  27% 

Cash Costs ($ per ounce silver)  $27.55  $18.36  50%  $23.03  20% 

All‐in Sustaining Costs ($ per ounce silver)  $36.35  $26.77  36%  $30.17  20% 

Lead Production (pounds)  3,185,048  3,234,276  ‐2%  3,585,196  ‐11%  

Relief Canyon Update 

Construction  is  advancing  well  at  the  fully  funded  Relief  Canyon  Mine.  Preparation  of  the  leach  pad  is 

approximately 80% complete and installation of the liner has started. Mobilization of the mining contractor 

is expected later this week. Work at the existing processing plant has started where upgrades will be made 

to the refinery and emissions controls. 

4 

Further  information  on  the  Relief  Canyon  development  will  be  ma de  available  periodically  on  the 

Company’s website as construction progresses at www.americassilvercorp.com.  

About Americas Silver Corporation  

Americas Silver is a precious metal mining company focused on g rowth from its existing asset base and 

execution of targeted accretive acquisitions. It owns and operates the Cosalá Operations in Sinaloa, Mexico 

and the Galena Complex in Idaho, USA. The Company expects to begin producing gold in the fourth quarter 

of  2019  at  its  fully  funded  Relief  Canyon  Mine  in  Nevada,  USA  which  is  currently  in  construction.  The 

Company also holds an option on the San Felipe development project in Sonora, Mexico.  

Daren  Dell,  Chief  Operating  Officer  and  a  Qualified  Person  under  Canadian  Securities  Administrators 

guidelines, has approved the applicable contents of this news r elease. For further information please see 

SEDAR or americassilvercorp.com. 

Cautionary Statement on Forward‐Looking Information: 

This news release contains “forward‐looking information” within the meaning of applicable securities laws. 

Forward‐looking  information  includes,  but  is  not  limited  to,  Ame r i c a s  S i l v e r ’ s  e x p e c t a t i o n s ,  i n t e n t i o n s ,  

plans, assumptions and beliefs wit h respect to, among other  thi ngs,  Americas  Silver’s  financing  efforts; 

production  and  cost  performance  at  the  Cosalá  Operations  and  th e  Galena  Complex;  construction, 

production, development plans and performance expectations at the Relief Canyon Project and the impact 

o n  A m e r i c a s  S i l v e r ’ s  f i n a n c i a l  p e r f o r m a n c e ;  O f t e n ,  b u t  n o t  a l w ays,  forward‐looking  information  can  be 

identified  by  forward‐looking  words  such  as  “anticipate”,  “believe”,  “expect”,  “goal”,  “plan”,  “intend”, 

“potential’, “estimate”, “may”, “assume” and “will” or similar words suggesting future outcomes, or other 

expectations,  beliefs,  plans,  objectives,  assumptions,  intentions,  or  statements  about  future  events  or 

performance. Forward‐looking information is based on the opinions and estimates of Americas Silver as of 

the date such information is provided and is subject to known and unknown risks, uncertainties, and other 

factors that may cause the actual results, level of activity, performance, or achievements of Americas Silver 

t o  b e  m a t e r i a l l y  d i f f e r e n t  f r o m  t h o s e  e x p r e s s e d  o r  i m p l i e d  b y  such  forward‐looking  information.  With 

respect  to  the  business  of  Americas  Silver,  these  risks  and  unc ertainties  include  interpretations  or 

reinterpretations  of  geologic  information;  unfavorable  exploration  results;  inability  to  obtain  permits 

required for future exploration,  development or production; gen eral economic conditions and conditions 

affecting the industries in which the Company operates; the unc ertainty of regulatory requirements and 

approvals; fluctuating mineral and commodity prices; the abilit y to obtain necessary future financing on 

acceptable terms or at all; the ability to develop, complete co nstruction and operate the Relief Canyon 

P r o j e c t ;  a n d  r i s k s  a s s o c i a t e d  w i t h  t h e  m i n i n g  i n d u s t r y  s u c h  a s  economic  factors  (including  future 

commodity prices, currency fluctuations and energy prices), gro und conditions and other factors limiting 

mine access, failure of plant, equipment, processes and transpo rtation services to operate as anticipated, 

environmental risks, government regulation, actual results of current exploration and production activities, 

possible  variations  in  ore  grade  or  recovery  rates,  permitting  timelines,  capital  and  construction 

expenditures, reclamation activities, labor relations, social a nd political developments and other risks of 

the mining industry. Although the Company has attempted to iden tify important factors that could cause 

actual results to differ materially from those contained in forward‐looking information, there may be other 

factors that cause results not to be as anticipated, estimated,  or intended. Readers are cautioned not to 

place undue  reliance on such information. Additional informatio n regarding the fact ors that may cause 

actual  results  to  differ  materially  from  this  forward‐looking  information  is  available  in  Americas  Silver’s 

filings with the Canadian Securities Administrators on SEDAR an d with the SEC. Americas Silver does not 

undertake any obligation to update publicly or otherwise revise any forward‐looking information whether 

as a result of new information, future events or other such factors which affect this information, except as 

required  by  law.  Americas  Silver  does  not  give  any  assurance  (1)  that  Americas  Silver  will  achieve  its 

expectations,  or  (2)  concerning  the  result  or  timing  thereof.  All  subsequent  written  and  oral  forward‐

5 

looking information concerning Americas Silver are expressly qu alified in their entirety by the cautionary 

statements above. 

For more information: 

Darren Blasutti 

President and CEO 

Americas Silver Corporation 

416‐848‐9503 

i Silver equivalent production thr oughout this press release was  calculated based on silver, zinc, and lead realized prices dur ing 

each respective period. 

ii Cash cost per ounce and all‐in sustaining cost per ounce are non‐IFRS performance measures with no standardized definition. For 

further  information  and  detailed   reconciliations,  please  refer  to  the  Company’s  2018  year‐end  and  quarterly  MD&A.  The 

performance measures for the  quarter ended June 30, 2019 are pr eliminary throughout this press release subject to refinement 

from the Company’s second quarter financial results to be released on or before August 14, 2019.