Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

USA.TO ·

Americas Silver Corporation Reports Fourth Quarter and Year‐end 2016 Financial Results

Financials

1 

AMERICAS SILVER CORPORATION REPORTS FOURTH QUARTER AND YEAR‐END 2016 FINANCIAL 

RESULTS  

TORONTO,  ONTARIO—March   30,  2017—   Americas  Silver  Corporation  (TSX:  USA)  (NYSE  “MKT”:  USAS) 

(“Americas  Silver”  or  the  “Company”)  today  reported  fourth  quarter  and  year‐end  financial  and 

operational results for 2016 and an update on the San Rafael Project (“San Rafael”). 

This earnings release should be read in conjunction with the Company’s MD&A, Financial Statements and 

Notes  to  Financial  Statements  for  the  corresponding  period,  which  have  been  posted  on  SEDAR  at 

www.sedar.com  and  are  also  available  on  the  Company’s  website  at  www.americassilvercorp.com.  All 

figures are in U.S. dollars unless otherwise noted. 

Year‐end and Fourth Quarter Highlights  

 Consolidated results met 2016 guidance for cash costs1 and all‐in sustaining costs1 with approximately 

2.4 million silver ounces and 4.7 million silver equivalent ounces2 at cost of sales of $9.86 per silver 

equivalent ounce, by‐product cash costs of $10.00 per silver ounce and all‐in sustaining costs of $12.71 

per silver ounce for the year. 

 Fourth quarter production was approximately 565,000 silver ounces and 1.1 million silver equivalent 

ounces at cost of sales of $10.47 per silver equivalent ounce, by‐product cash costs of $8.91 per silver 

ounce, and all‐in sustaining costs of $11.57 per silver ounce. 

 Consolidated operating cash flow generated was $5.4 million in fiscal 2016 compared to ($5.7 million) 

in fiscal 2015, an increase of $11.1 million or 195%. 

 Revenues  of  $58.9  million  and  net  loss  of  ($5.2)  million  or  ($0.15)  cents  per  share  for  the  year 

compared to revenues of $53.5 million and net loss of ($19.4) million and ($0.68) cents per share for 

the year ended December 31, 2015. 

 Consolidated guidance3 for 2017 is 2.0 ‐ 2.5 million silver ounces and 5.5 ‐ 6.0 million silver equivalent 

ounces at cost of sales of $8.00 ‐ $10.00 per silver equivalent ounce, by‐product cash costs of $4.00 ‐ 

$5.00 per ounce, and all‐in sustaining cash costs of $9.00 ‐ $10.00 per ounce. 

 The  fully‐funded  San  Rafael  Project  continues  to  progress  on  time  and  budget  for  commercial 

production in late Q3, 2017 following its formal construction commencement in October 2016. San 

Rafael is expected to be the Company’s key cash flow generator for 2018 and beyond, targeted to 

produce free cash flow of approximately $30 million annually at current spot prices with an unlevered 

IRR of +100%. 

 Cash  and  cash  equivalents  were  $24.1  million  at  December  31,  2016  with  net  working  capital  of 

approximately $20.1 million. A low interest rate $15.0 million concentrate pre‐payment facility was 

entered  in  January  2017  after  year  end  with  a  subsidiary  of  Glencore  PLC  (“Glencore”)  to  fund  a 

portion of the development costs for San Rafael. 

“The Company had a stronger year in 2016, generating increased cash flow in the second half of the year 

due  to  higher  silver  and  base  metal  prices,  and  our  ongoing  focus  on  cost  management,”  said  Darren 

1 Cash cost per ounce and all‐in sustaining costs per ounce are non‐IFRS financial performance measures with no standardized 

definition.  For  further  information  and  detailed  reconciliations,  please  refer  to  the  Company’s  2016  year‐end  and  quarterly 

MD&A. 

2 Silver equivalent production for 2016 throughout this press release is based on prices of $14.50 per ounce silver, $0.75 per 

pound zinc, $0.80 per pound lead and $2.00 per pound copper. 

3 Silver equivalent figures and silver cost guidance for 2017 are based on prices of $16.50 per ounce silver, $1.15 per pound 

zinc, $0.95 per pound lead and $2.50 per pound copper.

2 

Blasutti, President and CEO.  “We expect to continue to create positive operating cash flow until the San 

Rafael Project begins commercial production, which is expected to increase the Company’s revenue and 

cash flow while significantly decreasing operating costs in late 2017 and beyond. San Rafael, coupled with 

our acquisition of the San Felipe Project and strategic partnership with Glencore, will drive accretive future 

growth for our shareholders  

Consolidated Production and Operating Costs 

Consolidated Production and Cost Details  

   Q4 2016  Q4 2015  YE 2016  YE 2015 

Total ore processed (tonnes milled)  168,038  167,398  671,616  657,617 

Silver produced (ounces)  564,475  599,677  2,389,808  2,652,026 

Zinc produced (pounds)  2,671,391  3,075,468  10,488,773  11,647,962 

Lead produced (pounds)  7,277,346  7,067,802  29,067,673  22,905,826 

Copper produced (pounds)  260,018  321,616  1,058,250  2,054,896 

Silver equivalent produced (ounces)  1,140,024  1,200,583  4,682,030  4,866,145 

Silver recovery (percent)  90.4  88.6  87.8  89.3 

Silver grade (grams per tonne)  116  126  126  141 

Silver sold (ounces)  539,872  638,473  2,341,319  2,682,399 

Zinc sold (pounds)  2,658,194  2,819,226  10,258,081  11,267,595 

Lead sold (pounds)  7,242,694  6,928,136  29,228,720  22,853,476 

Copper sold (pounds)  274,722  345,727  1,017,940  2,055,008 

Cost of sales ($ per silver equivalent ounce)  $10.47  $11.11  $9.86  $10.80 

Silver cash cost ($ per silver ounce)  $8.91  $14.38  $10.00  $12.75 

All‐in sustaining cost ($ per silver ounce)  $11.57  $18.45  $12.71  $17.16 

A net loss of ($5.2) million was recorded for the year ended 2016, compared with a net loss of ($19.4) 

million for the year ended 2016. The decrease in net loss is primarily attributable to increased lead by‐

product  sales,  higher  realized  silver  and  base  metal  prices,  and  lower  cost  of  sales,  among  other  cost 

reductions, partially offset by higher interest and financing expense. Further information is available in 

the Company’s Management’s Discussion and Analysis for the year ended December 31, 2016. 

Consolidated silver production for 2016 totalled 2,389,808 silver ounces which represents a decrease of 

10% compared to 2015. Silver equivalent production totalled approximately 4.7 million ounces, a decrease 

of  4%  year‐over‐year,  while  lead  production  increased  by  27%  year‐over‐year.  Silver,  zinc  and  copper 

production was down year‐over‐year primarily due to the suspension of production at the Nuestra Señora 

mine due to ground movements in Q2, 2016 offset by higher lead production at Galena during the year. 

Realized silver, zinc, and lead prices increased year‐over‐year by 10%, 10%, and 7%, respectively, while 

copper fell year‐over‐year by 13%.  Consolidated cost of sales improved 9% to $9.86 per silver equivalent 

ounce year‐over‐year as a result of planned workforce reductions. Consolidated cash costs improved 22% 

to $10.00 per silver ounce year‐over‐year as a result of systematic cost controls in labour and supplies 

costs, and all‐in sustaining costs improved 26% to $12.71 per silver ounce year‐over‐year as a result of 

capital and exploration spending reductions. 

Further  information  concerning  the  consolidated  and  individual  mine  operations  is  included  in  the 

Company’s Consolidated Financial Statements for the year ended December 31, 2016 and Management’s 

Discussion and Analysis for the same period.

San Rafael Update 

San Rafael is a fully permitted, brownfield development that will utilize certain existing infrastructure at 

the  Cosalá  Operations.  The  Pre‐Feasibility  Study  initial  capital  cost  estimate  has  been  reduced  to 

3 

approximately $18 million through improvements in mine design, improved foreign exchange rates, and 

refurbishment of existing equipment from the Nuestra Señora mine. The San Rafael Pre‐Feasibility Study 

shows average annual production of 1.0 million ounces of silver, 50 million pounds of zinc, and 20 million 

pounds of lead over a 6‐year initial mine life at negative all‐in sustaining costs based on current reserves.  

Since publishing of the Pre‐Feasibility Study in H1‐2016, metal prices have increased significantly. Current 

prices  may  allow  the  San  Rafael  to  extend  its  mine  life  by  lowering  the  cut‐off  grade  and  converting 

additional resources to economical ore4. The Company is executing an exploration program at San Rafael’s 

Zone 120 area with a goal of upgrading the existing resource and testing the southeast extension of known 

mineralization. This drilling has strong potential to extend the mine life of San Rafael beyond that defined 

in the Pre‐Feasibility Study. The Company will be updating its shareholders on this program and other 

exploration programs at its operations throughout the year as the results become available.

The  Company  commenced  construction  of  San  Rafael  in  October  2016  following  Board  approval  in 

September  2016.  Earthworks  are  complete,  primary  ramp  development  is  advancing,  the  electrical 

substation has been energized, water storage facilities have been constructed, and San Rafael received 

delivery of its new mobile equipment, including a new scoop, scaler and bolter. Progress is well‐advanced 

in the refurbishment of other equipment transferred from the Nuestra Señora mine. San Rafael is targeted 

to begin stockpiling ore in late second quarter of 2017 with first concentrate production in third quarter 

of 2017. 

Ramp development has recently been slowed by difficult ground conditions at the boundary between the 

overlying volcanic rock and the limestone beneath.  Development should be through this area early in the 

second quarter of 2017. However, improvements have been found in other areas of the mine design and 

the  Company  expects  to  begin  stockpiling  ore  in  late  June.   Construction  of  the  mill  modifications  is 

scheduled to be complete by early August with plant commissioning and first concentrate production to 

occur later in Q3, 2017. 

Though  the  Company  has  necessary  cash  on  hand  to  build  San  Rafael,  a  low  interest  rate  $15  million 

concentrate pre‐payment facility was entered in January 2017 with Metagri S.A. de C.V., a subsidiary of 

Glencore,  to  fund  a  portion  of  the  development  costs  for  San  Rafael  in  order  to  maintain  corporate 

flexibility and further optimize San Rafael. The facility was fully drawn in late March 2017. 

The  Company  made  early  principal  repayments  of  approximately  $0.7  million  towards  its  outstanding 

November 2015 debt facility in September and $1.3 million towards its outstanding February 2016 debt 

facility in October. Subsequent to year‐end, the Company made a principal repayment of $1.6 million on 

maturity of another outstanding February 2016 debt facility and made an early principal repayment of 

approximately $5.6 million towards the August 2013 debt facility in late March. As a result, the Company 

has fully repaid all pre‐existing credit facilities as at December 21, 2016 with only the Glencore $15 million 

of long‐term debt currently outstanding.  

Timing of reserve and resource updates moved to mid‐year to better support basis for 2018 budgeting 

and life‐of‐mine modelling.

2017 Consolidated Guidance 

Consolidated silver production for 2017 is forecast between 2.0 ‐  2.5 million silver ounces and 5.5 ‐  6.0 

million silver  equivalent ounces. Cost of sales is forecast between $8.00 ‐  $10.00 per silver  equivalent 

ounce, while cash costs are projected to fall approximately 55% year‐over‐year to between $4.00 ‐ $5.00 

per silver ounce, and all‐in sustaining costs are projected to drop approximately 25% year‐over‐year to 

$9.00 ‐ $10.00 per silver ounce. The Galena mill was down for maintenance in Q1 2017, though production 

levels  for  the  remainder  of  the  year  at  the  Galena  Complex  are  expected  to  be  similar  to  2016.  The 

Company expects to see a gradual reduction in consolidated cash costs and all‐in sustaining costs until 

4 Please see Company press release dated September 13, 2016 for a discussion of San Rafael Pre‐Feasibility study published April 

30, 2016 and subsequent updates and optimization. 

4 

San  Rafael  enters  commercial  production  late  in  the  third  quarter  at  which  time  cash  costs  and  all‐in 

sustaining costs will drop significantly.  

About Americas Silver Corporation  

Americas Silver is a silver mining company focused on growth in precious metals from its existing asset 

base and execution of targeted accretive acquisitions.  It owns and operates the Cosalá Operations in 

Sinaloa, Mexico and the Galena Mine Complex in Idaho, USA. The Company has acquired an option on 

the San Felipe development project in Sonora, Mexico. 

Daren  Dell,  Chief  Operating  Officer  and  a  Qualified  Person  under  Canadian  Securities  Administrators 

guidelines, has approved the applicable contents of this news release. For further information please see 

SEDAR or americassilvercorp.com. 

Cautionary Statement on Forward‐Looking Information: 

This  news  release  contains  “forward‐looking  information”  within  the  meaning  of  applicable  securities 

laws. Forward‐looking information includes, but is not limited to, the Company’s expectations intentions, 

plans, assumptions and beliefs with respect to, among other things, the realization of operational and 

development plans (including the San Rafael Project), the Cosalá Operations and Galena Complex as well 

as the Company’s financing efforts. Often, but not always, forward‐looking information can be identified 

by forward‐looking words such as “anticipate”, “believe”, “expect”, “goal”, “plan”, “intend”, “estimate”, 

“may”, “assume” and “will” or similar words suggesting future outcomes, or other expectations, beliefs, 

plans, objectives, assumptions, intentions, or statements about future events or performance. Forward‐

looking  information  is  based  on  the  opinions  and  estimates  of  the  Company  as  of  the  date  such 

information is provided and is subject to known and unknown risks, uncertainties, and other factors that 

may  cause  the  actual  results,  level  of  activity,  performance,  or  achievements  of  the  Company  to  be 

materially different from those expressed or implied by such forward looking information. This includes 

the  ability  to  develop  and  operate  the  Cosalá  and  Galena  properties,  risks  associated  with  the  mining 

industry such as economic factors (including future commodity prices, currency fluctuations and energy 

prices),  ground  conditions  and  factors  other  factors  limiting  mine  access,  failure  of  plant,  equipment, 

processes  and  transportation  services  to  operate  as  anticipated,  environmental  risks,  government 

regulation, actual results of current exploration and production activities, possible variations in ore grade 

or recovery rates, permitting timelines, capital expenditures, reclamation activities, social and political 

developments and other risks of the mining industry. Although the Company has attempted to identify 

important factors that could cause actual results to differ materially from those contained in forward‐

looking information, there may be other factors that cause results not to be as anticipated, estimated, or 

intended. Readers are cautioned not to place undue reliance on such information. By its nature, forward‐

looking information involves numerous assumptions, inherent risks and uncertainties, both general and 

specific that contribute to the possibility that the predictions, forecasts, and projections of various future 

events will not occur. The Company undertakes no obligation to update publicly or otherwise revise any 

forward‐looking information whether as a result of new information, future events or other such factors 

which affect this information, except as required by law. 

Cautionary Note to U.S. Investors: 

The  terms  “mineral  resource”,  “measured  mineral  resource”,  “indicated  mineral  resource”,  “inferred 

mineral resource” used in the press release are Canadian mining terms used in accordance with National 

Instrument  43‐101 ‐  Standards  of  Disclosure  for  Mineral  Projects  under  the  guidelines  set  out  in  the 

Canadian  Institute  of  Mining,  Metallurgy  and  Petroleum  Standards.   Mineral  resources  which  are  not 

mineral reserves do not have demonstrated economic viability.  

While  the  terms  “mineral  resource”,  “measured  mineral  resource”,  “indicated  mineral  resource”,  and 

“inferred mineral resource” are recognized and required by Canadian regulations, they are not defined 

5 

terms under standards in the United States and normally are not permitted to be used in reports and 

registration statements filed with the Securities & Exchange Commission (“SEC”).  As such, information 

contained  in  the  Company's  disclosure  concerning  descriptions  of  mineralization  and  resources  under 

Canadian standards may not be comparable to similar information made public by U.S companies in SEC 

filings.  With  respect  to  “inferred  mineral  resource”  there  is  a  great  amount  of  uncertainty  as  to  their 

existence and a great uncertainty as to their economic and legal feasibility.  It cannot be assumed that all 

or any part of an “inferred mineral resource” will ever be upgraded to a higher category.  Investors are 

cautioned not to assume that any part or all of mineral deposits in these categories will ever be converted 

into reserves.  

For more information: 

Darren Blasutti      

President and CEO  

416‐848‐9503