Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

USA.TO ·

Americas Silver Corporation Provides Second Quarter Production and Cost Update

Corporate Updates

1 

AMERICAS SILVER CORPORATION PROVIDES SECOND QUARTER PRODUCTION AND COST UPDATE  

TORONTO,  ONTARIO—July  19,  2018—Americas  Silver  Corporation  (TSX:  USA)  (NYSE  American:  USAS) 

(“Americas  Silver”  or  the  “Company”)  today  announced  production  and  operating  cost  results  for  the 

second  quarter  of  2018  on  a  consolidated  basis  and  individually f o r  i t s  C o s a l á  O p e r a t i o n s  a n d  G a l e n a  

Complex. All figures are in U.S. dollars unless otherwise indicated. 

Second Quarter Highlights  

 Consolidated silver production for the quarter of approximately  300,000 silver ounces and 1.5 million 

silver equivalent1 ounces, representing decreases of 24% and 9%, respectively, when compared to Q1, 

2018, and a decrease of 46% and an increase of 24%, respectively, year‐over‐year.  

 Consolidated  cash  costs2  for  the  quarter  were  approximately  negative  ($6.15)  per  silver o u n c e ,  a  

decrease  of  125%  when  compared  to  Q1,  2018  and  185%  year‐over‐year,  while  consolidated  all‐in 

sustaining  costs2 ( “ A I S C ” )  w e r e  a p p r o x i m a t e l y  $ 5 . 4 0  p e r  s i l v e r  o u n c e ,  a  d e c r e a s e  of  13%  when 

compared to Q1, 2018 and 49% year‐over‐year. 

 Cosalá  Operations  milled  tonnage  increased  by  13%  over  Q1,  2018   as  San  Rafael  continued  to 

successfully ramp up both mining and milling rates in the secon d quarter of commercial production.  

As a result, silver production increased to approximately 90,00 0  silver ounces and 1.0 million silver 

equivalent  ounces  during  the  quarter,  representing  increases  of  19%  and  10%,  respectively,  when 

compared to Q1, 2018. Cash costs  were approximately  negative ($60.13) per silver ounce and AISC 

were approximately negative ($41.66) per silver ounce representing a decrease of 15% when compared 

to Q1, 2018. 

 As previously announced, Galena Complex production for the quarter was negatively impacted by two 

separate issues at its No.3 Shaft that inhibited normal hoisting for approximately 27 days in total. As a 

result,  the  Complex  produced  approximately  210,000  silver  ounces  and  420,000  silver  equivalent 

ounces,  representing  decreases  of  35%  and  37%,  respectively,  when  compared  to  Q1,  2018,  and 

decreases of 34% and 31%, respectively, year‐over‐year.  Cash c osts were approximately $18.36 per 

silver ounce and AISC were approximately $26.77 per silver ounce. The issues impacting second quarter 

production are not expected to affect production in the second half of the year.  

 Guidance for 2018 remains unchanged  at 1.6 – 2.0  million silver   ounces and 7.2 – 8.0 million silver 

equivalent ounces at cash costs  of negative ($10.00) to negativ e ($5.00) per silver ounce and AISC of 

negative ($1.00) to $4.00 per silver ounce. The Company expects to release its second quarter financial 

results on or before August 9, 2018. 

 The Company had cash and cash equivalents of $7.8 million at June 30, 2018.

 “The San Rafael mine successfully increased mining and milling  rates by almost 15% during the quarter 

and we expect further increases in the third quarter as it cont inues to ramp up the mill to capacity,” said 

1 Silver equivalent production throughout this press release was  calculated based on silver, zinc, lead and copper realized pri ces 

during each respective period. 

2 Cash cost per ounce and all‐in sustaining cost per ounce are n on‐IFRS performance measures with no standardized definition. 

For  further  information  and  detailed  reconciliations,  please  refer  to  the  Company’s  2017  year‐end  and  quarterly  MD&A.  The 

performance measures for the  quarter ended June 30, 2018 are pr eliminary throughout this press release subject to refinement 

from the Company’s second quarter financial results to be released on or before August 9, 2018. 

2 

Darren Blasutti, President & CEO of Americas Silver. “These increases allowed the Company to continue to 

drive  down  its  industry‐leading  cash  costs  and  AISC  when  compared  to  both  last  quarter  and  last  year, 

despite  lower  than  expected  production  from  the  Galena  Complex. N o w  t h a t  t h e  n e c e s s a r y  r e p a i r s  a t  

Galena  have  been  successfully  completed  in  the  second  quarter,  we  can  continue  to  execute  our 

operational plan for the remainder of the year.” 

Consolidated Second Quarter Production Details 

Consolidated silver production for the second quarter of 2018 was 301,711 silver ounces which represents 

a decrease of 24% over the previous quarter and 46% year‐over‐y ear. Silver equivalent production was 

approximately  1.5  million  ounces, down  9%  over  the  previous  quarter  and  up  24%  year‐over‐year.  The 

increase in the milling rate achieved at Cosalá Operations was  offset by the lower tonnage at the Galena 

Complex during the quarter.  Consolidated cash costs decreased 125% to negative ($6.15) per silver ounce 

comparted to previous quarter and 185% year‐over‐year, and AISC decreased 13% to $5.40 per silver ounce 

compared to the previous quarter and 49% year‐over‐year. Consolidated zinc production increased by 19% 

compared to Q1, 2018 and 201% compared to Q2, 2017; consolidate d lead production decreased by 18% 

compared  to  Q1,  2018.  The  decreases  in  silver,  silver  equivalen t,  silver  grade,  and  lead  production 

compared to Q1, 2018 are primarily due the issues associated with the No.3 Shaft at the Galena Complex.  

Table 1 

Consolidated Production Highlights 

  Q2 2018  Q2 2017  Change  Q1 2018  Change 

Processed Ore (tonnes milled)  164,313  179,427  ‐8%  163,875  1% 

Silver Production (ounces)  301,711  557,892  ‐46%  397,035  ‐24% 

Silver Equivalent Production (ounces)  1,462,170  1,175,836  24%  1 ,613,711  ‐9% 

Silver Grade (grams per tonne)  77  107  ‐28%  95  ‐19% 

Cost of Sales ($ per equiv. ounce silver) 1  $8.19  $11.00  ‐26%  $8.14  1% 

Cash Costs ($ per ounce silver) 1  ($6.15)  $7.21  ‐185%  ($2.73)  ‐125% 

All‐in Sustaining Costs ($ per ounce silver) 1   $5.40  $10.65  ‐49%  $6.17  ‐13% 

Zinc Production (pounds)  8,756,201  2,904,374  201%  7,332,978  19%  

Lead Production (pounds)  6,216,592  6,435,048  ‐3%  7,624,685  ‐18%  

Copper Production (pounds)  ‐  273,475  ‐100%  ‐  ‐ 

1   Cost of sales per silver equivalent ounce, cash costs per sil ver ounce, and all‐in sustaining  costs per silver ounce for Q2,  2017 

excludes pre‐production of 22,549 silver ounces and 32,955 silver equivalent ounces, respectively, mined from El Cajón during 

its commissioning period. Pre‐production revenue and cost of sales from El Cajón are capitalized as an offset to development 

costs. 

Cosalá Operations Production Details 

The Cosalá Operations produced 94,231 ounces of silver during the second quarter of 2018 and 1,041,246 

ounces of silver equivalent during the same period at cash cost s of negative ($60.13) per silver ounce and 

AISC of negative ($41.66) per silver ounce. Silver production increased 19% over the previous quarter while 

silver equivalent production increased 10% over the previous qu arter and 85% year‐over‐year. Cash costs 

and  AISC  were  down  compared  to  the  previous  quarter  from  negative  ($59.52)  per  silver  ounce  and 

negative  ($36.28)  per  silver  ounce,  respectively,  and  down  significantly  year‐over‐year  from  negative 

($2.81) per silver ounce and negative ($2.81) per silver ounce,  respectively. The improved results at San 

Rafael relative to Q1, 2018 are a result of the increase in milling rate (13%) as the process plant continued 

to ramp‐up operations to targeted levels during the quarter.    

3 

Table 2 

Cosalá Operations Highlights 

  Q2 2018  Q2 2017  Change  Q1 2018  Change 

Processed Ore (tonnes milled)  138,708  134,778  3%  123,285  13% 

Silver Production (ounces)  94,231  242,523  ‐61%  79,382  19% 

Silver Equivalent Production (ounces)  1,041,246  564,112  85%  948 ,081  10% 

Silver Grade (grams per tonne)  42  66  ‐36%  42  0% 

Cost of Sales ($ per equiv. ounce silver) 1  $5.34  $7.57  ‐29%  $5.92  ‐10% 

Cash Costs ($ per ounce silver) 1  ($60.13)  ($2.81)  >‐100%  ($59.52)  ‐1% 

All‐in Sustaining Costs ($ per ounce silver) 1   ($41.66)  ($2.81)  >‐100%  ($36.28)  ‐15% 

Zinc Production (pounds)  8,756,201  2,904,374  201%  7,332,978  19%  

Lead Production (pounds)  2,982,316  1,351,258  121%  2,679,485  11%  

Copper Production (pounds)  ‐  273,475  ‐100%  ‐  ‐ 

1   Cost of sales per silver equivalent ounce, cash costs per sil ver ounce, and all‐in sustaining  costs per silver ounce for Q2,  2017 

excludes pre‐production of 22,549 silver ounces and 32,955 silver equivalent ounces, respectively, mined from El Cajón during 

its commissioning period. Pre‐production revenue and cost of sales from El Cajón are capitalized as an offset to development 

costs. 

Galena Complex Production Details  

As previously announced on June 14, 2018, production at the Galena Complex was negatively impacted by 

two issues affecting the No.3 Shaft: a 10‐day suspension of hoisting in late April to allow the repair of steel 

sets in the shaft, and a 17‐day shutdown of the hoist in June t o address a mechanical failure in the brake 

m e c h a n i s m .  T h e  C o m p l e x  w a s  t e m p o r a r i l y  c o n s i d e r e d  t o  b e  o n  c a r e  and  maintenance  for  the  17‐day 

shutdown as repairs were performed with certain costs excluded from the cash costs and AISC calculations. 

Repairs were completed by the  end of June 2018 and these issues  are not expected to impact production 

rates for the remainder of the year.  

As a result, the Galena Complex produced 207,480 ounces of silver and 420,924 ounces of silver equivalent 

during the second quarter of 2018 at cash costs of $18.36 per s ilver ounce and AISC of $26.77 per silver 

ounce.  Silver  and  silver  equivalent  production  decreased  35%  and  37%,  respectively,  compared  to  the 

previous quarter, and decreased 34% and 31%, respectively, year ‐over‐year. Cash costs increased by 60% 

compared  to  the  prior  quarter  and  29%  year‐over‐year,  and  AISC were  up  60%  compared  to  the  prior 

quarter and 34% year‐over‐year. 

Table 3 

Galena Complex Highlights 

  Q2 2018  Q2 2017  Change  Q1 2018  Change 

Processed Ore (tonnes milled)  25,605  44,649  ‐43%  40,590  ‐37% 

Silver Production (ounces)  207,480  315,369  ‐34%  317,653  ‐35% 

Silver Equivalent Production (ounces)  420,924  611,724  ‐31%  665, 630  ‐37% 

Silver Grade (grams per tonne)  263  231  14%  256  3% 

Cost of Sales ($ per equiv. ounce silver)   $15.23  $13.98  9%  $11.31  35% 

Cash Costs ($ per ounce silver)   $18.36  $14.20  29%  $11.46  60% 

All‐in Sustaining Costs ($ per ounce silver)   $26.77  $20.03  34%  $16.78  60% 

Lead Production (pounds)  3,234,276  5,083,790  ‐36%  4,945,200  ‐35 % 

4 

About Americas Silver Corporation  

Americas Silver is a silver mining company focused on growth in  precious metals from its existing asset 

base  and  execution  of  targeted  accretive  acquisitions.    It  owns  and  operates  the  Cosalá  Operations  in 

Sinaloa, Mexico and the Galena Mine Complex in Idaho, USA. The  Company holds an option on the San 

Felipe development project in Sonora, Mexico. 

Cautionary Statement on Forward‐Looking Information: 

This news release contains “forward‐looking information” within the meaning of applicable securities laws. 

Forward‐looking information includes, but is not limited to, the Company’s expectations intentions, plans, 

assumptions and beliefs with respect to, among other things, th e realization of exploration, operational, 

production, and development plans, the Cosalá Operations and Galena Complex as well as the Company’s 

financing efforts. Often, but not always, forward‐looking information can be identified by forward‐looking 

words such as “anticipate”, “believe”, “expect”, “goal”, “plan”, “intend”, “estimate”, “may”, “assume” and 

“will”  or  similar  words  suggesting  future  outcomes,  or  other  ex pectations,  beliefs,  plans,  objectives, 

assumptions, intentions, or statements about future events or performance. Forward‐looking information 

is based on the opinions and estimates of the Company as of the  date such information is provided and is 

subject to known and unknown risks, uncertainties, and other fa ctors that may cause the actual results, 

level  of  activity,  performance,  or  achievements  of  the  Company t o  b e  m a t e r i a l l y  d i f f e r e n t  f r o m  t h o s e  

expressed or implied by such forward looking information. This includes the ability to develop and operate 

the  Cosalá  and  Galena  properties,  risks  associated  with  the  mining  industry  such  as  economic  factors 

(including  future  commodity  prices,  currency  fluctuations  and  e nergy  prices),  ground  conditions  and 

factors  other  factors  limiting  mine  access,  failure  of  plant,  e quipment,  processes  and  transportation 

services to operate as anticipat ed, environmental risks, govern ment regulation, actual results of current 

exploration  and  production  activities,  possible  variations  in  o re  grade  or  recovery  rates,  permitting 

timelines, capital expenditures, reclamation activities, social and political developments and other risks of 

the mining industry. Although the Company has attempted to iden tify important factors that could cause 

actual results to differ materially from those contained in forward‐looking information, there may be other 

factors that cause results not to be as anticipated, estimated,  or intended. Readers are cautioned not to 

place undue reliance on such information. By its nature, forwar d‐looking information involves numerous 

assumptions, inherent risks and uncertainties, both general and  specific that contribute to the possibility 

that  the  predictions,  forecasts, a n d  p r o j e c t i o n s  o f  v a r i o u s  f u tu r e  e v e n t s  w i l l  n o t  o c c u r .  T h e  C o m p a n y  

undertakes no obligation to update publicly or otherwise revise any forward‐looking information whether 

as a result of new information, future events or other such factors which affect this information, except as 

required by law. 

For more information: 

Darren Blasutti 

President and CEO 

416‐848‐9503