Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

USA.TO ·

Americas Silver Corporation Provides Second Quarter Production and Cost Update

Corporate Updates

1 

AMERICAS SILVER CORPORATION PROVIDES SECOND QUARTER PRODUCTION AND COST UPDATE  

TORONTO,  ONTARIO —July  24,  2017—Americas  Silver  Cor poration  (TSX:  USA)  (NYSE  “MK T”:  USAS) 

(“Americas Silver” or the “Company”) today announced consolidated production and operating cost results 

for the second quarter of 2017 and individually for its Cosalá  Operations and Galena Complex.  All figures 

are in U.S. dollars unless otherwise indicated. 

Second Quarter Highlights  

 Consolidated silver production for the quarter of approximately  558,000 silver ounces and 1.2 million 

silver equivalent1 ounces, representing increases of 7% and 6%, respectively, whe n compared to Q1, 

2017, and increases of 1% and 18%, respectively, year‐over‐year.  

 Consolidated cash costs2 for the quarter were approximately $6.31 per silver ounce, a decrease of 40% 

when compared to Q1, 2017 and 45% year‐over‐year, while consoli dated all‐in sustaining costs2 were 

approximately $9.74 per silver ounce, a decrease of 30% when co mpared to Q1, 2017 and 33% year‐

over‐year. 

 As at June 30, 2017, the Company had spent approximately $10.5  million of the revised $18 million 

budget  for  the  San  Rafael  development  project  located  in  Sinalo a ,  M e x i c o  a n d  e x p e c t s  t o  h a v e  

sufficient resources from cash on hand and cash flow generated  from continuing operations to fund 

the remaining project development. The project is on time and o n budget for production before the 

end of the third quarter. 

 Guidance for 2017 remains at 2.0 ‐ 2.5 million ounces of silver production with projected cash costs of 

$4.00 ‐ $5.00 per silver ounce and all‐in sustaining cash costs  of $9.00 ‐ $10.00 per silver ounce. Silver 

equivalent production has been reduced slightly to 5.0 ‐ 5.5 million ounces. 

 The Company had cash and cash equivalents of $12.8 million at June 30, 2017. 

“I am very pleased with the Company’s overall performance in th e second quarter”, said Darren Blasutti, 

President  &  CEO  of  Americas  Silver.  “Silver  production  met  expe c t a t i o n s ,  w e  l o w e r e d  o u r  c o s t s  

substantially over last year and last quarter, we had tremendou s exploration succe ss at both mines and 

made  significant  progress  at  the  San  Rafael  project  for  its  first  production  before  the  end  of  the  third 

quarter.” 

The Company expects to release its second quarter financial results on or before August 10, 2017. 

Consolidated Second Quarter Production Details 

Consolidated silver production for the second quarter of 2017 was 557,892 silver ounces which represents 

a n  i n c r e a s e  o f  7 %  o v e r  t h e  p r e v ious  quarter  and  1%  year‐over‐year.  Silver  equivalent  production  was 

approximately 1.2 million ounces, up 6% over the previous quart er and 18% year‐over‐year. The increase 

1 Silver equivalent production throughout this press release was  calculated based on silver, zinc, lead and copper realized pri ces 

during each respective period. 

2 Cash cost per ounce and all‐in sustaining cost per ounce are n on‐IFRS performance measures with no standardized definition. 

For  further  information  and  detailed  reconciliations,  please  refer  to  the  Company’s  2016  year‐end  and  quarterly  MD&A.  The 

performance measures for the  quarter ended June 30, 2017 are pr eliminary throughout this press release subject to refinement 

from the Company’s second quarter financial results to be released on or before August 10, 2017. 

2 

in silver and silver equivalent production is primarily due to  increased tonnage at t he Galena mine and 

continuing strong production from the Nuestra Señora mine as it winds down operations prior to the start 

of San Rafael in the fall.  

Table 1 

Consolidated Production Highlights 

   Q2 2017  Q1 2017  Change  Q2 2016  Change 

Processed Ore (tonnes milled)  179,427  167,493  7%  161,700  11% 

Silver Production (ounces)  557,892  523,747  7%  556,404  0% 

Silver Equivalent Production (ounces)  1,175,836  1,104,237  6%  997,537  18% 

Silver Grade (grams per tonne)  107  107  0%  130  ‐18% 

Cost of Sales ($ per equiv. ounce silver)1  $10.93  $9.93  10%  $10.80  1% 

Cash Costs ($ per ounce silver)1  $6.31  $10.49  ‐40%  $11.38  ‐45% 

All‐in Sustaining Costs ($ per ounce silver)1  $9.74  $13.97  ‐30%  $14.62  ‐33% 

Zinc Production (pounds)  2,904,374  2,389,133  22%  2,081,046  40% 

Lead Production (pounds)  6,435,048  6,160,732  4%  6,677,247  ‐4% 

Copper Production (pounds)  273,475  308,100  ‐11%  225,785  21% 

1   Cost of sales per silver equivalent ounce, cash costs per sil ver ounce, and all‐in sustaining  costs per silver ounce for Q2,  2017 

and  Q1,  2017  excludes  pre‐production  of  22,549  and  62,714  silve r  ounces,  respectively,  and  32,955  and  88,656  silver 

equivalent ounces, respectively,  mined from El Cajón during its  commissioning period. Pre‐pr oduction revenue and cost of 

sales from El Cajón are capitalized as an offset to development costs. 

Consolidated cash costs decreased 40% to $6.31 per silver ounce  compared to the previous quarter and 

45%  year‐over‐year.  All‐in  sustaining  costs  decreased  30%  to  $9.74  per  silver  ounce  compared  to  the 

previous  quarter  and  33%  year‐over‐year.  The  decrease  in  cash  costs  and  all‐in  sustaining  costs  was 

primarily due to lower operating costs, lower development required at Nuestra Señora, increased zinc and 

lead production, and the increase in the realized prices from these by‐product metals. 

Cosalá Operations Production Details 

The Cosalá Operations produced 242,523 ounces of silver during  the second quarter of 2017 and 564,112 

ounces  of  silver  equivalent  inclusive  of  pre‐production  material  from  El  Cajón.  Excluding  the  El  Cajón 

material, the Cosalá Operations produced 219,974 ounces of silver during the second quarter of 2017 and 

531,157 ounces of silver equivalent during the same period at c ost of sales of $7.57 per silver equivalent 

ounce, cash  costs and all‐in sustaining  costs of negative $2.43  per silver ounce. While silver production 

remained relatively flat year‐over‐year, silver equivalent prod uction increased 39% year‐over‐year as ore 

production was suspended briefly during Q2, 2016 due to the pro cessing of oxidized stockpiles as a result 

of  unexpected  ground  movements  at  Nuestra  Señora.  Cash  costs  improved  by  193%  compared  to  the 

previous  quarter  and  decreased  126%  year‐over‐year  while  all‐in   sustaining  costs  improved  190% 

compared to the previous quarter and 120% year‐over‐year.  

3 

Table 2 

Cosalá Operations Highlights 

   Q2 2017  Q1 2017  Change  Q2 2016  Change 

Processed Ore (tonnes milled)  134,778  128,577  5%  120,347  12% 

Silver Production (ounces)  242,523  250,296  ‐3%  244,548  ‐1% 

Silver Equivalent Production (ounces)  564,112  533,762  6%  405,797  39% 

Silver Grade (grams per tonne)  66  70  ‐7%  88  ‐25% 

Cost of Sales ($ per equiv. ounce silver)1  $7.57  $7.22  5%  $9.51  ‐20% 

Cash Costs ($ per ounce silver)1  ($2.43)  $2.61  ‐193%  $9.34  ‐126% 

All‐in Sustaining Costs ($ per ounce silver)1  ($2.43)  $2.69  ‐190%  $11.89  ‐120% 

Zinc Production (pounds)  2,904,374  2,389,133  22%  2,081,046  40% 

Lead Production (pounds)  1,351,258  1,124,464  20%  574,775  135% 

Copper Production (pounds)  273,475  308,100  ‐11%  225,785  21% 

1   Cost of sales per silver equivalent ounce, cash costs per sil ver ounce, and all‐in sustaining  costs per silver ounce for Q2,  2017 

and  Q1,  2017  excludes  pre‐production  of  22,549  and  62,714  silve r  ounces,  respectively,  and  32,955  and  88,656  silver 

equivalent ounces, respectively,  mined from El Cajón during its  commissioning period. Pre‐pr oduction revenue and cost of 

sales from El Cajón are capitalized as an offset to development costs. 

Production for the Cosalá Operations was primarily sourced from the Nuestra Señora mine during Q2, 2017 

as higher zinc and lead prices prioritized this ore above the s tockpiled silver‐copper El Cajón ore. Nuestra 

Señora was initially planned to cease production in early Q2, 2 017, however further economic material 

continues to be sourced at lower operating costs and with minim al development cost from various levels 

of existing workings. It is expected that both the stockpiled El Cajón ore and remaining Nuestra Señora ore 

will be processed during Q3, 2017 up to the commencement of San Rafael. The significant decrease in cash 

costs and all‐in sustaining cost s was due to lower operating co sts and lack of capitalized development at 

Nuestra Señora, increased zinc and lead production, and the increase in the realized prices from these by‐

product metals. 

The Company updated its sharehol ders on July 17, 2017 on the st atus of development at the San Rafael 

project in Sinaloa, Mexico. The development remains on budget a nd on time to begin processing ore by 

the  end  of  the  Q3,  2017  with  mill  modifications,  machinery  refurbishments,  and  ramp  development 

progressing  well.    The  March  30,  2016  San  Rafael  Pre‐Feasibilit y  Study  forecasted  average  annual 

production of 1 million ounces of silver, 50 million pounds of  zinc and 20 million pounds of lead over an 

initial 6‐year mine life at negative all‐in sustaining costs ba sed on current reserves and metal prices. The 

mine is expected to have an IRR  of greater than 100%, generate  substantial free cash flow and provide a 

step change in the Company’s cash cost and all‐in sustaining cost profile in 2018. 

The Company expects to provide an exploration update on its Cosalá properties before the end of the third 

quarter as results have been encouraging to date. 

Galena Complex Production Details  

The Galena Complex produced 315, 369 ounces of silver during the  second quarter of 2017 and 611,724 

ounces of silver equivalent during the same period at cost of s ales of $13.85 per silver equivalent ounce, 

cash costs of $12.40 per silver ounce and all‐in sustaining costs of $18.23 per silver ounce. Silver and silver 

equivalent  production  increased  15%  and  7%,  respectively,  compa red  to  the  previous  quarter,  and 

4 

increased 1% and 3%, respectively, year‐over‐year. Cash costs improved by 22% compared to the previous 

quarter  and  5%  year‐over‐year  and  all‐in  sustaining  costs  were down  16%  compared  to  the  previous 

quarter.  

Table 3 

Galena Complex Highlights 

   Q2 2017  Q1 2017  Change  Q2 2016  Change 

Processed Ore (tonnes milled)  44,649  38,916  15%  41,353  8% 

Silver Production (ounces)  315,369  273,451  15%  311,856  1% 

Silver Equivalent Production (ounces)  611,724  570,475  7%  591,740  3% 

Silver Grade (grams per tonne)  231  230  0%  251  ‐8% 

Cost of Sales ($ per equiv. ounce silver)  $13.85  $12.05  15%  $11.68  19% 

Cash Costs ($ per ounce silver)  $12.40  $15.89  ‐22%  $12.98  ‐5% 

All‐in Sustaining Costs ($ per ounce silver)  $18.23  $21.71  ‐16%  $16.76  9% 

Lead Production (pounds)  5,083,790  5,036,268  1%  6,102,472  ‐17% 

Despite greater tonnage, both silver and lead production were b elow expectations in the second quarter 

due to a shortfall in grade. This shortfall was primarily a result of operational challenges, including reduced 

equipment availability and inade quate cemented fill quality, in  some of the key production areas in the 

lower parts of the mine. The mill relied more than expected on  lower grade development ore from the 

upper levels of the mine. The specific issues are being address ed and site personnel continue to advance 

their planning practices to improve production flexibility in the future. As a result of the lower lead grades 

p r o c e s s e d  i n  t h e  f i r s t  h a l f  o f  t h e  y e a r ,  l e a d  p r o d u c t i o n  w a s  a pproximately  3.5  million  pounds  below 

expectations.  This  underperformance  is  the  primary  reason  for  reducing  silver  equivalent  production 

guidance to 5.0 ‐ 5.5 million ounces. 

Direct operating costs have been tracking well against expectations excluding of an unexpected increase in 

employee related medical costs in the quarter. The shortfall in  lead production negatively impacted the 

cash costs because of lower by‐product credits. Improvements will be realized as grades return to historic 

norms and new production areas begin to contribute consistently. 

About Americas Silver Corporation  

Americas Silver is a silver mining company focused on growth in  precious metals from its existing asset 

base  and  execution  of  targeted  accretive  acquisitions.    It  owns  and  operates  the  Cosalá  Operations  in 

Sinaloa, Mexico and the Galena Mine Complex in Idaho, USA. The Company has acquired an option on the 

San Felipe development project in Sonora, Mexico. 

Daren  Dell,  Chief  Operating  Officer  and  a  Qualified  Person  under  Canadian  Securities  Administrators 

guidelines, has approved the applicable contents of this news r elease. For further information please see 

SEDAR or americassilvercorp.com. 

Cautionary Statement on Forward‐Looking Information: 

This news release contains “forward‐looking information” within the meaning of applicable securities laws. 

Forward‐looking information includes, but is not limited to, the Company’s expectations intentions, plans, 

assumptions  and  beliefs  with  respect  to,  among  other  things,  th e  realization  of  operational  and 

development plans (including the successful completion of the S an Rafael project), the Cosalá Operations 

5 

and Galena Complex as well as the Company’s financing efforts.  Often, but not always, forward‐looking 

information can be identified by forward‐looking words such as  “anticipate”, “believe”, “expect”, “goal”, 

“plan”, “intend”, “estimate”, “may”, “assume” and “will” or sim ilar words suggesting future outcomes, or 

other expectations, beliefs, plans, objectives, assumptions, in tentions, or statements about future events 

or performance. Forward‐looking  information is based on the opi nions and estimates of the Company as 

of the date such information is provided and is subject to know n and unknown risks, uncertainties, and 

o t h e r  f a c t o r s  t h a t  m a y  c a u s e  t h e  a c t u a l  r e s u l t s ,  l e v e l  o f  a c t i vity,  performance,  or  achievements  of  the 

Company to be materially different from those expressed or implied by such forward looking information. 

This includes the ability to develop and operate the Cosalá and Galena properties, risks associated with the 

mining industry such as economic factors (including future comm odity prices, currency fluctuations and 

energy  prices),  ground  conditions  and  factors  other  factors  lim i t i n g  m i n e  a c c e s s ,  f a i l u r e  o f  p l a n t ,  

equipment,  processes  and  transportation  services  to  operate  as  anticipated,  environmental  risks, 

government regulation, actual results of current exploration an d production activities, possible variations 

in ore grade or recovery rates, permitting timelines, capital expenditures, reclamation activities, social and 

political developments and other risks of the mining industry.  Although the Company has attempted to 

identify  important  factors  that  could  cause  actual  results  to  differ  materially  from  those  contained  in 

forward‐looking  information,  there  may  be  other  factors  that  cause  results  not  to  be  as  anticipated, 

estimated,  or  intended.  Readers  are  cautioned  not  to  place  undue  reliance  on  such  information.  By  its 

nature,  forward‐looking  information  involves  numerous  assumptions,  inherent  risks  and  uncertainties, 

both general and specific that contribute to the possibility th at the predictions, forecasts, and projections 

of  various  future  events  will  not  occur.  The  Company  undertakes  no  obligation  to  update  publicly  or 

otherwise revise any forward‐looking information whether as a result of new information, future events or 

other such factors which affect this information, except as required by law. 

For more information: 

Darren Blasutti 

President and CEO 

416‐848‐9503