Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

USA.TO ·

Americas Silver Corporation Provides First Quarter Production and Cost Update Including Record Low Cash Costs and All‐in Sustaining Costs

Corporate Updates

1 

AMERICAS SILVER CORPORATION PROVIDES FIRST QUARTER PRODUCTION AND COST UPDATE 

INCLUDING RECORD LOW CASH COSTS AND ALL‐IN SUSTAINING COSTS  

TORONTO,  ONTARIO—April  17,  2018—Americas  Silver  Corporation  (TSX:  USA)  (NYSE  American:  USAS) 

(“Americas Silver” or the “Company”) today announced consolidated production and operating cost results 

for the first quarter of 2018 and individually for its Cosalá Operations and Galena Complex.  All figures are 

in U.S. dollars unless otherwise indicated. 

First Quarter Highlights (compared to Q1, 2017) 

 Consolidated  silver  production  of  approximately  400,000  silver  ounces  and  1.6  million  silver 

equivalent1 ounces.  

 Consolidated cash costs 2 were approximately negative ($2.50) per silver ounce, a decrea se of 125%. 

Consolidated all‐in sustaining costs2 (“AISC”) were approximately $6.40 per silver ounce, a decrease of 

50%. 

 Cosalá  Operations  silver  production  solely  from  the  Company’s  San  Rafael  mine  of  approximately 

80,000 silver ounces and 950,000 silver equivalent ounces. Cash  costs were approximately negative 

($58.45) per silver ounce and all‐in sustaining costs were appr oximately negative ($35.20) per silver 

ounce. 

 Galena  Complex  silver  production  of  approximately  320,000  silve r  ounces  and  666,000  silver 

equivalent ounces representing increases of 16% and 17%, respectively. Cash costs were approximately 

$11.45 per silver ounce and all‐in sustaining costs were approx imately $16.75 per silver ounce down 

28% and 23%, respectively.  

 Guidance for 2018 remains unchanged  at 1.6 – 2.0  million silver   ounces and 7.2 – 8.0 million silver 

equivalent  ounces  at  cash  costs  of  negative  ($10.00)  to  negative  ($5.00)  per  silver  ounce  and  all‐in 

sustaining cash costs of negative ($1.00) to $4.00 per silver ounce. The Company expects to release its 

first quarter financial results on or before May 10, 2018. 

“The Company had a strong first quarter at both operations as S an Rafael continued to ramp up in terms 

of mining rate and mill throughput,” said Americas Silver President and CEO Darren Blasutti. “Shareholders 

will be pleased with the significant reductions in our cash cos ts and AISC year‐over‐year as the benefits of 

San  Rafael  begin  to  be  realized.  We  expect  further  reductions  into  the  second  half  of  the  year  as  mill 

throughput reaches a steady state at 1,700 tonnes per day and S an Rafael capital expenditures reduce to 

sustaining levels. Galena also delivered notable decreases in cash costs while increasing silver production, 

supporting the consolidated results.” 

Consolidated First Quarter Production Details 

Consolidated  silver  production  for  the  first  quarter  of  2018  was  397,035  ounces  which  represents  a 

decrease  of  3%  over  the  previous  quarter  and  a  decrease  of  24%  year‐over‐year.  Silver  equivalent 

production was approximately 1.6 million ounces, up 19% over th e previous quarter and 46% year‐over‐

1 Silver equivalent production throughout this press release was  calculated based on silver, zinc, lead and copper realized pri ces 

during each respective period. 

2 Cash cost per ounce and all‐in sustaining cost per ounce are n on‐IFRS performance measures with no standardized definition. 

For  further  information  and  detailed  reconciliations,  please  refer  to  the  Company’s  2017  year‐end  and  quarterly  MD&A.  The 

performance measures for the quarter ended March 31, 2018 are preliminary throughout this press release subject to refinement 

from the Company’s first quarter financial results to be released on or before May 10, 2018. 

2 

year.  Consolidated  cash  costs  decreased  129%  to  negative  ($2.52)  per  silver  ounce  compared  to  the 

previous quarter and 126% year‐over‐year, and all‐in sustaining  costs decreased 55% to $6.38 per silver 

ounce compared to the previous quarter and 52% year‐over‐year. 

Table 1 

Consolidated Production Highlights 

  Q1 2018  Q1 2017  Change  Q4 2017  Change 

Processed Ore (tonnes milled)  1 63,875  167,493  ‐2 %  168,901  ‐3% 

Silver Production (ounces)  397,035  523,747  ‐24%  409,545  ‐3% 

Silver Equivalent Production (ounces)  1,613,711  1,104,237  46%  1 ,358,441  19% 

Silver Grade (grams per tonne)  95  107  ‐12%  91  4% 

Cost of Sales ($ per equiv. ounce silver)1  $8.12  $9.93  ‐18%  $10.16  ‐20% 

Cash Costs ($ per ounce silver)1  ($2.52)  $9.89  ‐126%  $8.75  ‐129% 

All‐in Sustaining Costs ($ per ounce silver)1  $6.38  $13.37  ‐52%  $14.20  ‐55% 

Zinc Production (pounds)  7,332,978  2,389,133  207%  4,895,670  50%  

Lead Production (pounds)  7,624,685  6,160,732  24%  7,427,357  3% 

Copper Production (pounds)  ‐  308,100  ‐  78,541  ‐ 

1   Cost of sales per silver equivalent ounce, cash costs per sil ver ounce, and all‐in sustaining  costs per silver ounce for Q1,  2017 

excludes  pre‐production  of  62, 714  silver  ounces,  and  88,656  sil ver  equivalent  ounces  mined  from  El  Cajón  during  its 

commissioning period, and for Q4, 2017 excludes pre‐production of 45,344 silver ounces, and 405,162 silver equivalent ounces 

mined from San Rafael during its commissioning period. Pre‐production revenue and cost of sales from El Cajón and San Rafael 

are capitalized as an offset to development costs. 

Consolidated  silver  production  was  lower  compared  to  prior  quarters  as  the  Company  had  its  first  full 

quarter of operations from its new San Rafael mine after declar ing commercial production in December 

2017. San Rafael will provide lower silver production compared  to the previously mined deposits at the 

Cosalá Operations until mining sequences to the higher silver g rade areas of the ore body later next year.  

The consolidated silver equivalent production increased substantially and the consolidated cash costs and 

all‐in  sustaining  costs  decreased  when  compared  to  prior  quarte r  and  year‐over‐year  due  to  the 

comparatively higher base metal grades generally present in the San Rafael deposit. Galena is returning to 

an  acceptable  level  of  profitable  operating  performance  with  grades  returning  to  historical  norms  with 

consistent contribution from production areas. 

Cosalá Operations Production Details 

The  Cosalá  Operations  produced  79,382  ounces  of  silver  during  the  first  quarter  of  2018  and  948,081 

ounces of silver equivalent during the same period at cash cost s of negative ($58.47) per silver ounce and 

all‐in  sustaining  costs  of  negative  ($35.22)  per  silver  ounce.  S i l v e r  p r o d u c t i o n  d e c r e a s e d  4 7 %  o v e r  t h e  

previous  quarter  and  68%  year‐over‐year,  while  silver  equivalent  production  increased  25%  over  the 

previous quarter and 78% year‐over‐year. Cash costs and all‐in  sustaining costs were down significantly 

c o m p a r e d  t o  t h e  p r e v i o u s  q u a r t e r  f r o m  n e g a t i v e  ( $ 0 . 2 8 )  p e r  s i l ver  ounce  and  $3.74  per  silver  ounce, 

respectively, and down significantly year‐over‐year from $1.13 per silver ounce and $1.21 per silver ounce, 

respectively.  

3 

Table 2 

Cosalá Operations Highlights 

  Q1 2018  Q1 2017  Change  Q4 2017  Change 

Processed Ore (tonnes milled)  1 23,285  128,577  ‐4 %  129,098  ‐5% 

Silver Production (ounces)  79,382  250,296  ‐68%  150,235  ‐47% 

Silver Equivalent Production (ounces)  948,081  533,762  78%  759,4 39  25% 

Silver Grade (grams per tonne)  42  70  ‐40%  54  ‐22% 

Cost of Sales ($ per equiv. ounce silver) 1  $5.92  $7.22  ‐18%  $7.39  ‐20% 

Cash Costs ($ per ounce silver) 1  ($58.47)  $1.13  >‐100%  ($0.28)  >‐100% 

All‐in Sustaining Costs ($ per ounce silver) 1  ($35.22)  $1.21  >‐100%  $3.74  >‐100% 

Zinc Production (pounds)  7,332,978  2,389,133  207%  4,895,670  50%  

Lead Production (pounds)  2,679,485  1,124,464  138%  2,348,125  14%  

Copper Production (pounds)  ‐  308,100  ‐  78,541  ‐ 

1   Cost of sales per silver equivalent ounce, cash costs per sil ver ounce, and all‐in sustaining  costs per silver ounce for Q1,  2017 

excludes  pre‐production  of  62, 714  silver  ounces,  and  88,656  sil ver  equivalent  ounces  mined  from  El  Cajón  during  its 

commissioning period, and for Q4, 2017 excludes pre‐production of 45,344 silver ounces, and 405,162 silver equivalent ounces 

mined from San Rafael during its commissioning period. Pre‐production revenue and cost of sales from El Cajón and San Rafael 

are capitalized as an offset to development costs. 

As  previously  noted,  Cosalá  silver  production  was  lower  compared  to  prior  quarters  as  the  Company 

completed  its  first  full  quarter  of  operations  from  its  new  San  Rafael  mine  after  declaring  commercial 

production  in  December  2017.  San  Rafael  is  expected  to  produce lower  grade  silver  compared  to  the 

previously mined deposits at the Cosalá Operations until mining  operations move to higher silver grade 

areas of the ore body later next year. Additionally, the initia l development in the San Rafael ore body was 

in an area closest to the portal where the silver grade is less than half of the reserve silver grade. As a result, 

the silver production was lower in the first quarter compared to prior quarters. The Cosalá Operations had 

a significant increase in silver equivalent production as well as a significant reduction in cash costs and all‐

in sustaining costs during Q1, 2018, primarily due to the by‐pr oduct metal production from zinc and lead 

during the period, which increased by 50% and 14%, respectively , when compared to prior quarter, and 

increased by 207% and 138%, respectively, year‐over‐year. 

Galena Complex Production Details  

The Galena Complex produced 317,653 ounces of silver during the first quarter of 2018 and 665,630 ounces 

of silver equivalent during the same period at cash costs of $1 1.46 per silver ounce and all‐in sustaining 

costs  of  $16.78  per  silver  ounce.    Silver  and  silver  equivalent   production  increased  22%  and  11%, 

respectively, compared to the prior quarter, and increased 16% and 17%, respectively, year‐over‐year. Cash 

costs were down 8% compared to the prior quarter and 28% year‐over‐year and all‐in sustaining costs were 

down 9% compared to the prior quarter and 23% year‐over‐year.  

4 

Table 3 

Galena Complex Highlights 

  Q1 2018  Q1 2017  Change  Q4 2017  Change 

Processed Ore (tonnes milled)  40,590  38,916  4%  39,803  2% 

Silver Production (ounces)  317,653  273,451  16%  259,310  22% 

Silver Equivalent Production (ounces)  665,630  570,475  17%  599,002  11% 

Silver Grade (grams per tonne)  256  230  11%  213  20% 

Cost of Sales ($ per equiv. ounce silver)  $11.26  $12.05  ‐7%  $11.79  ‐5% 

Cash Costs ($ per ounce silver)  $11.46  $15.89  ‐28%  $12.40  ‐8% 

All‐in Sustaining Costs ($ per ounce silver)  $16.78  $21.71  ‐23%  $18.43  ‐9% 

Lead Production (pounds)  4,945,200  5,036,268  ‐2%  5,079,232  ‐3% 

The Company is focused on returning Galena to an acceptable level of operating performance during 2018 

by advancing several planning‐related initiatives, including gr ade optimization, in order to recapture and 

build on the gains which were made in 2015 and 2016. Improvements were realized in Q1, 2018 and should 

continue throughout the year as grades are returning to targeted norms with consistent contribution from 

production areas. 

About Americas Silver Corporation  

Americas Silver is a silver mining company focused on growth in  precious metals from its existing asset 

base  and  execution  of  targeted  accretive  acquisitions.    It  owns  and  operates  the  Cosalá  Operations  in 

Sinaloa, Mexico and the Galena Mine Complex in Idaho, USA. The  Company holds an option on the San 

Felipe development project in Sonora, Mexico. 

Daren  Dell,  Chief  Operating  Officer  and  a  Qualified  Person  under  Canadian  Securities  Administrators 

guidelines, has approved the applicable contents of this news r elease. For further information please see 

SEDAR or americassilvercorp.com. 

Cautionary Statement on Forward‐Looking Information: 

This news release contains “forward‐looking information” within the meaning of applicable securities laws. 

Forward‐looking information includes, but is not limited to, the Company’s expectations intentions, plans, 

assumptions and beliefs with respect to, among other things, th e realization of exploration, operational 

and development plans, the Cosalá Operations and Galena Complex  as well as the Company’s financing 

e f f o r t s .  O f t e n ,  b u t  n o t  a l w a y s ,  f o r w a r d ‐ l o o k i n g  i n f o r m a t i o n  c a n  be  identified  by  forward‐looking  words 

such as “anticipate”, “believe”, “expect”, “goal”, “plan”, “intend”, “estimate”, “may”, “assume” and “will” 

or similar words suggesting future outcomes, or other expectations, beliefs, plans, objectives, assumptions, 

intentions, or statements about future events or performance. F orward‐looking information is based on 

the opinions and estimates of the Company as of the date such i nformation is provided and is subject to 

known  and  unknown  risks,  uncertainties,  and  other  factors  that may  cause  the  actual  results,  level  of 

activity, performance, or achievements of the Company to be materially different from those expressed or 

implied by such forward looking information. This includes the  ability to develop and operate the Cosalá 

and Galena properties, risks associated with the mining industry such as economic factors (including future 

commodity prices, currency fluctuations and energy prices), gro und conditions and factors other factors 

limiting  mine  access,  failure  of  plant,  equipment,  processes  and  transportation  services  to  operate  as 

anticipated,  environmental  risks,  government  regulation,  actual  r e s u l t s  o f  c u r r e n t  e x p l o r a t i o n  a n d  

p r o d u c t i o n  a c t i v i t i e s ,  p o s s i b l e  v a r i a t i o n s  i n  o r e  g r a d e  o r  r e c overy  rates,  permitting  timelines,  capital 

expenditures,  reclamation  activities,  social  and  political  devel o p m e n t s  a n d  o t h e r  r i s k s  o f  t h e  m i n i n g  

5 

industry. Although the Company has attempted to identify important factors that could cause actual results 

to differ materially from those contained in forward‐looking in formation, there may be other factors that 

cause results not to be as anticipated, estimated, or intended.  Readers are cautioned not to place undue 

reliance on such information. By its nature, forward‐looking in formation involves numerous assumptions, 

inherent  risks  and  uncertainties,  both  general  and  specific  that  contribute  to  the  possibility  that  the 

predictions, forecasts, and projections of various future events will not occur. The Company undertakes no 

obligation to update publicly or otherwise revise any forward‐l ooking information whether as a result of 

new information, future events or other such factors which affe ct this information, except as required by 

law. 

For more information: 

Darren Blasutti 

President and CEO 

416‐848‐9503