Production Results

THIS PRESS RELEASE CONSTITUTES A "DESIGNATED NEWS RELEASE" FOR THE PURPOSES OF THE COMPANY'S PROSPECTUS  SUPPLEMENT DATED MAY 17, 2021, TO ITS SHORT FORM BASE SHELF PROSPECTUS DATED JANUARY 29, 2021. 

TORONTO, ONTARIO—July 18, 2022—Americas Gold and Silver Corporation (TSX: USA) (NYSE American: USAS) (“Americas” or the “Company”), a growing North American precious metals producer, is pleased to report production for the second quarter ended June 30, 2022.  Production results, outlook and costs throughout  this  release  production  results  are  based  on  the  Company’s  100%  interest  in  the  Cosalá Operations and 60% interest in the Galena Complex.

Highlights 

  • For Q2‐2022, consolidated attributable production totalled approximately 300,000 silver ounces and 1,343,000 silver equivalent1 ounces.  Silver production was unchanged quarter‐over‐quarter and increased 115% year‐over‐year.   Silver equivalent production increased by over 5% quarter‐ over‐quarter and over 475% year‐over‐year.
  • The Company estimates consolidated Q2‐2022 cash cost2 per silver ounce of negative $0.12 per ounce and consolidated Q2‐2022 all‐in sustaining cost2 per silver ounce of $7.96 per ounce.
  • Silver production is expected to increase into the second half of 2022 as production ramps‐up into the higher‐silver grade Upper Zone of the San Rafael deposit at the Cosalá Operations and the Galena Hoist project at the Galena Complex is completed.
  • Year‐to‐date, consolidated attributable production totalled approximately 600,000 silver ounces and  2,618,000  silver  equivalent  ounces  at  a  YTD  cash  cost  per  silver  ounce  of  approximately negative $4.84 per ounce and consolidated YTD all‐in sustaining cost per silver ounce of $2.64 per ounce.
  • The Company’s silver equivalent production guidance remains at 4.8 to 5.2 million ounces in 2022 with further increases forecast at 7.0 to 7.4 million ounces in 2024, increases of approximately 240% and 375%, respectively, compared with 2021.
  • The  Company  has  a  cash  and  cash  equivalents  balance  of  $8.8  million  as  of  June  30,  2022, compared with a cash and cash equivalents balance of $2.9 million as of December 31, 2021.

“The Company had a strong operating quarter which we expect to continue for the remainder of 2022,” stated  Americas  President  and  CEO  Darren  Blasutti.    “The  second  quarter  production  plan  in  Mexico focused on mining the Main Zone at San Rafael to maximize revenue given the strong zinc prices.  We expect to see an appreciable increase in silver production over the second half of the year as the Galena Complex plan begins to mine more higher‐grade silver stopes and San Rafael sees increased contribution from the high‐grade silver Upper Zone.  As a result of these factors, the Company expects to be at the higher end of its 2022 guidance of 4.8 to 5.2 million silver equivalent ounces.  The balance sheet continues to improve with a stable cash balance and reduced debt.”

Consolidated Quarterly Attributable Production* 

Q2 – 2022Q1 – 2022Q2 – 2021% Increase (Q‐over‐Q)% Increase (Y‐over‐Y)
Silver Production (ounces)299,227 oz300,316 oz138,043 oz0%117%
Zinc Production (million pounds)9.9 Mlbs9.6 MlbsN/A3%N/A
Lead Production (million pounds)6.4 Mlbs6.4 Mlbs2.6 Mlbs0%146%
Silver Equivalent Production (ounces)1,343,061 oz1,274,470 oz232,561 oz5%478%
  • Silver equivalent ounces for Q2‐2022, Q1‐2022 and Q2‐2021 were calculated based on silver, zinc and lead realized prices during

each respective period throughout this press release.

Cosalá Operations 

The Cosalá Operations produced 128,000 ounces of silver, 3.9 million pounds of lead and 9.9 million pounds of zinc in Q2‐2022.  Cash costs per silver ounce and all‐in sustaining costs per silver at the Cosalá Operations have continued to benefit from strong current zinc and lead prices.

With  the  strong  zinc  and  lead  prices  during  the  quarter  coupled  with  the  decreasing  silver  price,  the Company  focused  on  mining  the  higher‐grade  zinc  and  lower‐grade  silver  areas  of  the  Main  Zone  to maximize the revenue mix generated from the Cosalá Operations.  The Company expects silver production to increase in H2‐2022 with a growing contribution from higher‐grade silver areas in the Upper Zone of the San Rafael mine.  Silver production from the Cosalá Operations for the year is expected to be towards the bottom end of the forecasted range of 0.7 to 0.9 million silver ounces with the change in focus to continue to  mine  the  higher‐grade  zinc  Main  Zone  and  delay  mining  the  higher‐grade  silver  Upper  Zone.    Zinc production from the Cosalá Operations is expected to be towards the upper end of the forecasted range of 36 to 40 million pounds while lead production is also expected to be towards the upper end of the forecasted range of 13 to 15 million pounds.

Galena Complex 

The Galena Complex attributable production was approximately 171,000 ounces of silver and 2.5 million pounds of lead in Q2‐2022.  Silver production is estimated to increase in H2‐2022 from a combination of mining higher tonnage in higher‐grade silver copper stopes.  The Company aims to complete the Galena Hoist project in Q4‐2022 which will increase hoisting capacity at the operation in Q4‐2022 and beyond. Cash costs per ounce and all‐in sustaining costs per ounce at the Galena Complex are also anticipated to improve with the completion of the Galena Hoist project as most of the operations costs are fixed and are expected to decrease on a per silver ounce basis assuming expected higher silver and lead production beyond 2022.

The outlook for expected attributable metal production from the Galena Complex in fiscal 2022 remains unchanged and is estimated to be 0.7 to 0.9 million silver ounces and 9 to 11 million pounds of lead.

About Americas Gold and Silver Corporation

Americas Gold and Silver Corporation is a growing precious metals mining company with multiple assets in North America.  The Company owns and operates the Cosalá Operations in Sinaloa, Mexico, manages the 60%‐owned Galena Complex in Idaho, USA, and is re‐evaluating the Relief Canyon mine in Nevada, USA. The Company also owns the San Felipe development project in Sonora, Mexico.  For further information, please see SEDAR or www.americas‐gold.com.

For more information: 

Stefan Axell  Darren Blasutti VP, Corporate Development & Communications  President and CEO Americas Gold and Silver Corporation  Americas Gold and Silver Corporation 416‐874‐1708  416‐848‐9503

Cautionary Statement on Forward‐Looking Information: 

This news release contains “forward‐looking information” within the meaning of applicable securities laws. Forward‐looking information includes, but is not limited to, the Company’s expectations, intentions, plans, assumptions and beliefs with respect to, among other things, estimated and targeted production rates and results for gold, silver and other metals, the expected prices of gold, silver and other metals, as well as the related costs, expenses and capital expenditures; the Company’s production guidance and anticipated production results for the full year of 2022; the recapitalization plan at the Galena Complex, including the expected production levels and potential additional mineral resources thereat; the expected timing and completion of the Galena Hoist project and the anticipated benefits thereof including increased hoisting capacity at the operations and expected improvements to cash costs per ounce and all‐in sustaining costs per  ounce  following  such  completion;  the  expected  continuity  of  full  production  levels  at  the  Cosalá Operations and the continuity of legal access for employees and contractors; the expectations regarding the  level  of  support  from  the  Mexican  government  with  respect  to  the  long‐term  stability  of  Cosalá Operations, and its ability to maintain such support in the near‐ and long‐term.  Guidance and outlook contained in this press release was prepared based on current mine plan assumptions with respect to production, costs and capital expenditures, the metal price assumptions disclosed herein, and assumes no adverse impacts to operations from the COVID 19 pandemic, no further adverse impacts to the Cosalá Operations from blockades, and completion of the Galena Hoist project on its expected schedule and the realization of the anticipated benefits therefrom, and is subject to the risks and uncertainties outlined below.  Often, but not always, forward‐looking information can be identified by forward‐looking words such as “anticipate”, “believe”, “expect”, “goal”, “plan”, “intend”, “potential’, “estimate”, “may”, “assume” and “will” or similar words suggesting future outcomes, or other expectations, beliefs, plans, objectives, assumptions, intentions, or statements about future events or performance.  Forward‐looking information is based on the opinions and estimates of the Company as of the date such information is provided and is subject to known and unknown risks, uncertainties, and other factors that may cause the actual results, level of activity, performance, or achievements of Americas Gold and Silver to be materially different from those expressed or implied by such forward‐looking information.  With respect to the business of the Company,  these  risks  and  uncertainties  include  risks  relating  to  widespread  epidemics  or  pandemic outbreak including the COVID‐19 pandemic; the impact of COVID‐19 on our workforce, suppliers and other essential resources and what effect those impacts, if they occur, would have on our business, including our ability  to  access  goods  and  supplies,  the  ability  to  transport  our  products  and  impacts  on  employee productivity, the risks in connection with the operations, cash flow and results of the Company relating to the  unknown  duration  and  impact  of  the  COVID‐19  pandemic;  interpretations  or  reinterpretations  of geologic  information;  unfavorable  exploration  results;  inability  to  obtain  permits  required  for  future exploration,  development  or  production;  general  economic  conditions  and  conditions  affecting  the industries in which the Company operates; the uncertainty of regulatory requirements and approvals; fluctuating mineral and commodity prices; the ability to obtain necessary future financing on acceptable terms or at all; the ability to operate the Company’s projects; and risks associated with the mining industry such as economic factors (including future commodity prices, currency fluctuations and energy prices), ground conditions, illegal blockades and other factors limiting mine access or regular operations without interruption, failure of plant, equipment, processes and transportation services to operate as anticipated, environmental risks, government regulation, actual results of current exploration and production activities, possible  variations  in  ore  grade  or  recovery  rates,  permitting  timelines,  capital  and  construction expenditures, reclamation activities, labor relations or disruptions, social and political developments and other risks of the mining industry.  The potential effects of the COVID‐19 pandemic on our business and operations are unknown at this time, including the Company’s ability to manage challenges and restrictions arising from COVID‐19 in the communities in which the Company operates and our ability to continue to safely operate and to safely return our business to normal operations.  The impact of COVID‐19 on the Company  is  dependent  on  a  number  of  factors  outside  of  its  control  and  knowledge,  including  the effectiveness of the measures taken by public health and governmental authorities to combat the spread of the disease, global economic uncertainties and outlook due to the disease, and the evolving restrictions relating  to  mining  activities  and  to  travel  in  certain  jurisdictions  in  which  it  operates.    Although  the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward‐looking information, there may be other factors that cause results not to be as anticipated, estimated, or intended.  Readers are cautioned not to place undue reliance on such information.

The 2022 and 2024 production outlook expectations set out in this press release are considered forward‐ looking statements and represent management’s good faith estimates or expectations of future production results as of the date hereof.  Outlook is based upon certain assumptions, including, but not limited to, metal prices, certain exchange rates, the completion of the Recapitalization Plan at the Galena Complex on time and on budget, including the completion of the Galena hoist project and related engineering by Q4‐ 2022, the Cosalá Operations remaining at full production and not experiencing any unanticipated work stoppages or interruptions, the Cosalá Operations accessing higher‐grade silver areas in the Upper Zone of the  San  Rafael  mine  staring  in  the  second  half  of  2022  and  other  assumptions.  For  example,  2022 production outlook includes actual results through [June 30], 2022.  Production estimates include the Galena  Complex  and  assumes  the  completion  of  the  Recapitalization  Plan  on  time  and  on  budget. Assumptions used for purposes of production outlook may prove to be incorrect and actual results may differ from those anticipated.  Production outlook cannot be guaranteed.  As such, investors are cautioned not to place undue reliance upon production outlook and forward‐looking statements as there can be no assurance that the plans, assumptions, or expectations upon which they are placed will occur.

Additional information regarding the factors that may cause actual results to differ materially from this forward‐looking  information  is  available  in  the  Company’s  filings  with  the  Canadian  Securities Administrators on SEDAR and with the SEC.  The Company does not undertake any obligation to update publicly or otherwise revise any forward‐looking information whether as a result of new information, future events or other such factors which affect this information, except as required by law.  The Company does not give any assurance (1) that the Company will achieve its expectations, or (2) concerning the result or timing thereof.  All subsequent written and oral forward‐looking information concerning the Company are expressly qualified in their entirety by the cautionary statements above.

Non‐IFRS Financial Measures 

This press release makes reference to certain non‐IFRS measures, including certain metrics specific to the industry in which we operate. These measures are not recognized measures under International Financial Reporting Standards as issued by the International Accounting Standards Board (“IFRS”), do not have a standardized meaning prescribed by IFRS and, therefore, may not be comparable to similar measures presented  by  other  companies.    Rather,  these  measures  are  provided  as  additional  information  to complement those IFRS measures by providing further understanding of our results of operations from management’s perspective.  Accordingly, these measures are not intended to represent, and should not be considered as alternatives to net income or other performance measures derived in accordance with IFRS as measures of operating performance or operating cash flows or as a measure of liquidity.  In addition to our results determined in accordance with IFRS, we use non‐IFRS measures including cash costs per ounce, all in sustaining costs per ounce and average realized silver, zinc and lead prices.  We believe these non‐IFRS  measures  provide  useful  information  to  both  management  and  investors  in  measuring  our financial performance and condition and highlight trends in our core business that may not otherwise be apparent  when  relying  solely  on  IFRS  measures.    For  further  information  regarding  these  non‐IFRS measures, please refer to “Non‐GAAP and Other Financial Measures” in our management’s discussion and analysis for the financial year ended December 31, 2021, which is incorporated by reference herein and is available on our SEDAR profile at www.SEDAR.com or the Company’s website at www.americas‐gold.com.

1 Silver equivalent ounces for the 2022 guidance, and 2023 and 2024 outlook references were calculated based on $22.00/oz silver, $0.95/lbs lead and $1.30/lbs zinc throughout this press release.  Silver equivalent ounces for Q2‐2022, Q1‐2022, Q1‐2021 and YTD 2022 were calculated based on silver, zinc and lead realized prices during each respective period throughout this press release.

2 This metric is a non‐GAAP financial measure or ratio.  The Company uses the financial measures “Cash Cost”, “Cash Cost/Ag Oz Produced”, “All‐In Sustaining Cost”, and “All‐In Sustaining Cost/Ag Oz Produced” in accordance with measures widely reported in the silver mining industry as a benchmark for performance measurement and because it understands that, in addition to conventional measures prepared in accordance with IFRS, certain investors and analysts use this information to evaluate the Company’s underlying cash costs and total costs of operations. Cash cost is determined on a mine‐by‐ mine basis and include mine site operating costs such as mining, processing, administration, production taxes and royalties which are not based on sales or taxable income calculations, while all‐in sustaining cost is the cash cost plus all development, capital expenditures, and exploration spending. A full reconciliation of these non‐GAAP financial measures will be provided when the Company reports its quarterly results on or before August 15, 2022.