Americas GOLD and Silver Corporation Reports Full‐year 2019 Financial Results

Financials

1 

AMERICAS GOLD AND SILVER CORPORATION REPORTS FULL‐YEAR 2019 FINANCIAL RESULTS 

TORONTO, ONTARIO—March  9, 2020—Americas  Gold and Silver Corporation (TSX: USA) (NYSE American: 

USAS)  (“Americas”  or  the  “Company”),  a  growing  North  American  precious  metals  producer,  today 

reported  consolidated  financial  and  operational  results  for  the  year  ended  December  31,  2019  and 

provided a general update on the operations. 

This  earnings  release  should  be  read  in  conjunction  with  the  Company’s  Management’s  Discussion  and 

Analysis, Financial Statements and Notes to Financial Statements for the corresponding period, which have 

been posted on the Americas Gold and Silver Corporation SEDAR profile at www.sedar.com, on its EDGAR 

profile at www.sec.gov, and are also available on the Company’s website at www.americas‐gold.com.  All 

figures are in U.S. dollars unless otherwise noted. 

Year‐End and Operational Highlights

● Revenue of $58.4 million and net loss of $34.2 million for the full‐year of 2019 or ($0.46) per share, 

a decrease of $10.0 million in revenue and an increase in net loss of $23.5 million compared to 

year‐end of 2018.  Adjusted net income1 was $23.3 million prior to one‐time adjustments or ($0.30) 

per share 

● Previously  reported  year‐end  consolidated  production2  of  approximately  5.8  million  silver 

equivalent ounces3 and 1.2 million silver ounces, representing decreases of 7% and 18% year‐over‐

year to both silver equivalent ounces and silver ounces, respectively.  Galena silver production for 

the fourth quarter was not included as a result of the start of the Recapitalization Plan accounting 

for the majority of the production decreases year‐over‐year. 

● Previously  reported  year‐end  consolidated  cash  costs4  of  $4.61  per  silver  ounce  and  all‐in 

sustaining costs4 of $12.71 per silver ounce, both representing increases year‐over‐year. 

● Successfully poured first gold in February 2020 at the Company’s Relief Canyon mine in Nevada 

and completed initial construction estimated to be within the guidance of $28 ‐ $30 million.  

● Mined tonnage at Relief Canyon is tracking ahead of schedule and the ore stacking rate is ramping 

up.  To date, the operation has over 250,000 tonnes of ore placed on the leach pad with commercial 

production expected before the end of Q2‐2020. 

● With the addition of Relief Canyon, precious metals production is expected to increase by over 

300% in 2020 to 60,000 – 70,000 Gold Equivalent Ounces5 (“GEO”) and by over 500% in 2021 to 

90,000 – 110,000 GEOs compared to approximately 14,000 GEOs produced in 2019. 

● The Company has tremendous support from employees and contractors at the Cosalá Operations 

following the illegal blockade of the operations.  The Company continues to actively engage with 

all levels of Government regarding the illegal blockade and hopes to resolve the dispute by the end 

of Q1‐2020. 

● The Galena Complex Recapitalization Plan began in mid Q4‐2019 and continues into 2021.   The 

joint  venture  has  purchased  new  equipment,  refurbished  existing  equipment  and  completed 

extensive re‐development in the 4300 and 5500 Levels.  Over 10,000 feet of new drilling has been 

completed with several promising targets being evaluated.   The operation has already begun to 

experience an increase in production rates over 2019. 

● The Company had a cash balance of approximately $20.0 million as at December 31, 2019. 

2 

“The Company delivered Relief Canyon to first gold pour within nine months from the commencement of 

construction;  an  impressive  accomplishment  for  our  team  in  a  short  period  of  time,”  said  Americas 

President  &  CEO  Darren  Blasutti.   “Relief  Canyon  is  expected  to  significantly  increase  precious  metal 

exposure by 500% by fiscal 2021 and increase the overall profitability of the Company as we deliver full 

production into a rising gold price environment after successfully acquiring the gold asset when gold was 

trading  at  less  than  $1,200  per  ounce  in  early  2019.   The  Cosalá  Operations  successfully  executed  its 

production  plans  for  the  year  increasing  mill  tonnage  to  over  1,750  per  operating  day,  and  increasing 

production  of  precious  and  by‐product  metals.   The  Galena  Recapitalization  Plan  is  being  executed  as 

planned with the purchase and delivery of essential equipment and drilling commencement.  The Company 

is well positioned for the continued transition to a profitable, high‐growth, precious metals producer as 

Relief Canyon ramps up.” 

Consolidated Financial and Operational Results 

Consolidated Financial, Production and Cost Detail 

   20192  2018 

Revenues ($M)  $58.4  $68.4 

Net Loss ($M)  $(34.2)  $(10.7) 

Comprehensive Loss ($M)  $(35.1)  $(9.9) 

Total ore processed (tonnes milled)  701,884  685,152 

Silver produced (ounces)  1,163,618  1,417,537 

Zinc produced (pounds)  43,314,002  34,219,472 

Lead produced (pounds)  26,193,098  30,466,799 

Silver equivalent produced2 (ounces)  5,836,446  6,286,531 

Silver recovery (percent)  73.2  76.6 

Silver grade (grams per tonne)  70  84 

Zinc grade (percent)  3.96  3.65 

Lead grade (percent)  2.12  2.46 

Silver sold (ounces)  1,159,432  1,424,745 

Zinc sold (pounds)  41,733,934  33,714,154 

Lead sold (pounds)  26,129,771  30,620,153 

Realized Silver Price ($ per ounce)  $15.99  $15.65 

Realized Zinc Price ($ per pound)  $1.19  $1.32 

Realized Lead Price ($ per pound)  $0.91  $1.02 

Cost of sales ($ per equivalent silver ounce)  $8.43  $8.29 

Silver cash cost3 ($ per silver ounce)  $4.61  $(0.63) 

All‐in sustaining cost3 ($ per silver ounce)  $12.71  $9.80 

The  Company’s  San  Rafael  mine  in  Mexico  had  continued  success  during  fiscal  2019  as  mill  tonnage 

increased by 13% and sustained an average milling rate of approximately 1,750 tonnes per operating day 

during the year.  Silver grade and recovery both increased by approximately 6% and 8%, respectively, with 

base metal grades and recoveries also increasing.  These improvements resulted in increases of 28%, 27% 

and 27% in silver, zinc and lead production when compared to 2018.  Despite the Cosalá Operation’s strong 

performance, consolidated silver equivalent production decreased 7% to approximately 5.8 million ounces 

compared to production of 6.3 million ounces during 2018.  Consolidated silver production for 2019 was 

approximately  1.2  million  silver  ounces,  a  decrease  of  18%  compared  to  2018.   The  decrease  in  metal 

production  was  due  to  lower  tonnage,  and  silver  and  lead  grades  at  the  Galena  Complex  prior  to 

3 

commencement  of  the  Recapitalization  Plan  in  Q4‐2019,  partially  offset  by  strong  results  at  the  Cosalá 

Operations.  

Gross revenue decreased by $1.4 million compared to 2018 primarily due to a decrease in silver equivalent 

production despite increases in realized silver prices during the year.  The silver spot price increased to an 

average of $16.21 per ounce in 2019 from an average of $15.71 per ounce in 2018 as uncertainty in global 

markets increased during the year with further increases in precious metal prices generally continuing into 

fiscal 2020.  Net revenues were further negatively impacted by an increase in concentrate treatment and 

refining charges of $8.5 million or 32% over 2018 for a net total decrease in revenue of $9.9 million.  

The Company’s profitability was negatively impacted in fiscal 2019 by: the lower tonnage and grades at the 

Galena  Complex  without  a  corresponding  decrease  in  costs;  lower  by‐product  metal  prices;  higher  zinc 

treatment charges at the Cosalá Operations lowering net revenues; higher cost of sales primarily at the 

Cosalá  Operations  due  to  higher  tonnage  mined  and  milled;  higher  depletion  and  amortization  due  to 

higher  production;  and  higher  non‐cash  items  such  as  share‐based  payments  and  loss  on  derivative 

instruments.  Consolidated cash costs increased during the year primarily due to higher industry‐wide zinc 

concentrate treatment charges, as well as lower production and lower grades at the Galena Complex. 

Further  information  concerning  the  consolidated  and  individual  mine  operations  is  included  in  the 

Company’s  year‐end  Consolidated  Financial  Statements  for  the  year  ended  December  31,  2019  and 

Management’s Discussion and Analysis for the year ended December 31, 2019. 

Consolidated 2‐Year Production Outlook 

Table 1* 

Consolidated 2‐Year Outlook (Excluding the Galena Complex) 

  2020 Guidance  2021 Outlook 

Gold Production (ounces)  50 – 60 koz  80 – 90 koz 

Silver Production (ounces)  0.8 – 0.9 Moz  1.0 – 1.5 Moz 

Gold Equivalent Production (ounces)  60 – 70 koz  90 – 110 koz 

All‐in Sustaining Cost ($ per equivalent gold ounce)  $900 – 1,100/oz  $850 – 1,050/oz 

Cost of Sales ($ per equivalent gold ounce)  $1,100 – 1,250/oz  $1,000 – 1,200/oz 

Sustaining Capital Expenditures ($)  $8 – 10 M  $8 – 10 M 

*  Forecasts  for  2020  and  2021  include  only  Relief  Canyon  and  the  Cosalá  Operations.   2020  Guidance  assumes  11  months  of 

production from the Cosalá Operations.  Continuation of the blockade may impact guidance further.

The  Company  reiterates  the  forecasted  production  for  the  next  two  years  and  expects  to  significantly 

increase  precious  metals  production  with  the  gold  contribution  from  Relief  Canyon.   This  represents  a 

significant  transition  from  a  silver/base  metal  producer  to  a  predominantly  precious  metals  producer.  

Precious metal production is expected to increase by over 300% in 2020 and by over 500% in 2021 when 

compared with production in 2019.  For additional detail regarding our production outlook, please refer to 

the Company’s press release on February 18, 2020. 

Relief Canyon 

Relief Canyon poured first gold in February and has over 250,000 tonnes of ore placed on the leach pad.  

Ore crushing and stacking is steadily improving with the addition of the night shift and is now operating on 

a 24‐hour basis.  Heap leach permeability and leaching characteristics of the ore are meeting expectations.  

4 

The  operation  has  a  significant  ore  stockpile  of  over  200,000  tonnes  ahead  of  the  crusher  and  waste 

stripping is ahead of schedule.   Commercial production continues to be expected before the end of Q2‐

2020. 

Cosalá Operations 

The Company continues to have discussions with government authorities at both the state and federals 

levels.  The operation also continues to have tremendous support from its workers, local community, ejidos 

and small businesses in the Cosalá area which have all been negatively impacted by the illegal blockade.  

The Company appreciates this support. 

The  Company  will  not  negotiate  with  representatives  of  this  illegal  blockade  and  is  exploring  all  legal 

channels to resolve this dispute in a peaceful and timely fashion. 

Galena Complex 

The  Galena  Complex  is  benefiting  from  the  Recapitalization  Plan  that  commenced  in  October  2019.  

Equipment has arrived on site and additional equipment will continue to mobilize over the next couple of 

months.   Productivity has improved to start the year as well as worker morale.   Most importantly, there 

has been a steady improvement in worker safety.  There has been extensive repair to the 5500 level and 

4300  level  drifts  which  will  allow  the  operation  to  establish  diamond  drill  stations  to  test  for  deep 

mineralization below the current workings.  Finally, shaft repair at the 5500 level is also progressing which 

will allow the operation to re‐establish the deepest loading pocket.  This will reduce the need to haul ore 

and waste by ramp to higher levels of the mine.  The Company is confident that the Recapitalization Plan 

will provide the Galena Complex with the intended benefits of lower costs, higher production and a longer 

mine life.  

Year‐End 2019 Conference Call 

President & CEO Darren Blasutti will be hosting a year‐end 2019 conference call on Monday, March 9th, 

2020  at  4:30pm  EST.   A  copy  of  the  presentation  will  be  made  available  on  the  company’s  website  at 

www.americas‐gold.com.  

Step 1: Dial‐In 

Canada and USA Toll‐Free: 1‐800‐750‐5861 

International Toll Number: 1 416‐981‐9007 

Step 2: Online Login 

https://cc.callinfo.com/r/1o51voa85hx01&eom   

Callers are advised to dial‐in 10‐15 minutes prior to the call.  As there is no audio on the participant URL, 

please dial‐in to follow along with the presentation.  

About Americas Gold and Silver Corporation 

Americas  Gold  and  Silver  Corporation  is  a  high‐growth  precious  metals  mining  company  with  multiple 

assets in North America.  The Company’s newest asset, Relief Canyon in Nevada, USA, has poured first gold 

and  is  expected  to  ramp  up  to  full  production  over  the  course  of  2020.   The  Company  also  owns  and 

operates the Cosalá Operations in Sinaloa, Mexico and manages the 60%‐owned Galena Complex in Idaho, 

USA.   The Company also holds an option on the San Felipe development project in Sonora, Mexico.   For 

further information, please see SEDAR or www.americas‐gold.com 

5 

For more information: 

Stefan Axell        Darren Blasutti 

VP, Corporate Development & Communications   President and CEO 

Americas Gold and Silver Corporation     Americas Gold and Silver Corporation 

416‐874‐1708        416‐848‐9503 

Cautionary Statement on Forward‐Looking Information: 

This news release contains “forward‐looking information” within the meaning of applicable securities laws.  

Forward‐looking  information  includes,  but  is  not  limited  to,  Americas  Gold  and  Silver’s  expectations, 

intentions, plans, assumptions and beliefs with respect to, among other things, estimated production rates 

and results for gold, silver and other precious metals, as well as the related costs, expenses and capital 

expenditures, the Company’s construction, production, development plans and performance expectations 

at the Relief Canyon Mine, including the anticipated timing of commercial production at Relief Canyon, the 

resolution and removal of the illegal blockade at the Company’s Cosalá Operations and the resumption of 

mining and processing operations.   Often, but not always, forward‐looking information can be identified 

by forward‐looking words such as “anticipate”, “believe”, “expect”, “goal”, “plan”, “intend”, “potential’, 

“estimate”,  “may”,  “assume”  and  “will”  or  similar  words  suggesting  future  outcomes,  or  other 

expectations,  beliefs,  plans,  objectives,  assumptions,  intentions,  or  statements  about  future  events  or 

performance.  Forward‐looking information is based on the opinions and estimates of Americas Gold and 

Silver as of the date such information is provided and is subject to known and unknown risks, uncertainties, 

and  other  factors  that  may  cause  the  actual  results,  level  of  activity,  performance,  or  achievements  of 

Americas  Gold  and  Silver  to  be  materially  different  from  those  expressed  or  implied  by  such  forward‐

looking information.  With respect to the business of Americas Gold and Silver, these risks and uncertainties 

include  interpretations  or  reinterpretations  of  geologic  information;  unfavorable  exploration  results; 

inability to obtain permits required for future exploration, development or production; general economic 

conditions  and  conditions  affecting  the  industries  in  which  the  Company  operates;  the  uncertainty  of 

regulatory requirements and approvals; fluctuating mineral and commodity prices; the ability to obtain 

necessary future financing on acceptable terms or at all; the ability  to develop, complete  construction, 

bring to production and operate the Relief Canyon Project; and risks associated with the mining industry 

such  as  economic  factors  (including  future  commodity  prices,  currency  fluctuations  and  energy  prices), 

ground  conditions  and  other  factors  limiting  mine  access,  failure  of  plant,  equipment,  processes  and 

transportation  services  to  operate  as  anticipated,  environmental  risks,  government  regulation,  actual 

results of current exploration and production activities, possible variations in ore grade or recovery rates, 

permitting  timelines,  capital  and  construction  expenditures,  reclamation  activities,  labor  relations  or 

disruptions,  social  and  political  developments  and  other  risks  of  the  mining  industry.   Although  the 

Company has attempted to identify important factors that could cause actual results to differ materially 

from those contained in forward‐looking information, there may be other factors that cause results not to 

be  as  anticipated,  estimated,  or  intended.   Readers  are  cautioned  not  to  place  undue  reliance  on  such 

information.  Additional information regarding the factors that may cause actual results to differ materially 

from  this  forward‐looking  information  is  available  in  Americas  filings  with  the  Canadian  Securities 

Administrators on SEDAR and with the SEC.  Americas does not undertake any obligation to update publicly 

or otherwise revise any forward‐looking information whether as a result of new information, future events 

or other such factors which affect this information, except as required by law.  Americas does not give any 

assurance (1) that Americas will achieve its expectations, or (2) concerning the result or timing thereof.  All 

subsequent written and oral forward‐looking information concerning Americas are expressly qualified in 

their entirety by the cautionary statements above. 

6 

Cautionary Note to U.S. Investors: 

The terms “proven and probable reserve”, “resource”, “measured resource”,  “indicated resource”, and 

“inferred resource” used in the press release are mining terms used in accordance with Canadian National 

Instrument  43‐101 ‐   Standards  of  Disclosure  for  Mineral  Projects  under  the  guidelines  set  out  in  the 

Canadian  Institute  of  Mining,  Metallurgy  and  Petroleum  Standards.   Mineral  resources  which  are  not 

mineral reserves do not have demonstrated economic viability. 

While  the  terms  “mineral  resource”,  “measured  mineral  resource”,  “indicated  mineral  resource”,  and 

“inferred mineral resource” are recognized and required by Canadian regulations, they are not defined 

terms  under  standards  in  the  United  States  and  normally  are  not  permitted  to  be  used  in  reports  and 

registration  statements  filed  with  the  Securities  &  Exchange  Commission  (“SEC”).   Moreover,  the 

definitions of proven and probable reserves used in NI 43‐101 differ from the definitions in the United 

States  Securities  and  Exchange  Commission's  Industry  Guide  7.   As  such,  information  contained  in  the 

Company's disclosure concerning descriptions of mineralization, reserves and resources under Canadian 

standards may not be comparable to similar information made public by U.S companies in SEC filings.  With 

respect to “inferred mineral resource” there is a great amount of uncertainty as to their existence and a 

great uncertainty as to their economic and legal feasibility.  It cannot be assumed that all or any part of an 

“inferred mineral resource” will ever be upgraded to a higher category.   Investors are cautioned not to 

assume that any part or all of the mineral deposits in these categories will ever be converted into reserves. 

1 The Company’s profitability was negatively impacted in 2019 by non‐reoccurring and non‐cash charges, specifically transaction 

costs associated with the Pershing Gold acquisition ($3.5 million), incremental interest and financing costs related to the 

convertible loans payable and convertible debenture ($1.2 million), net loss on derivative instruments ($2.5 million), and non‐

cash share‐based payments ($3.7 million). Adjusting for the non‐reoccurring and non‐cash charges, the net loss would have been 

approximately $23.3 million. Other variances, such as non‐cash items in depletion and amortization ($13.3 million) and increased 

concentrate treatment charges and related costs ($10.3 million).

2 Throughout this press release, 2019 production results exclude Q4‐2019 from the Galena Complex due to commencement of the 

Recapitalization Plan. 

3 Silver equivalent production throughout this press release was calculated based on silver, zinc, and lead realized prices during 

each respective period.

4 Cash cost per ounce and all‐in sustaining cost per ounce are non‐IFRS performance measures with no standardized definition.  

For further information and detailed reconciliations, please refer to the Company’s 2019 year‐end and quarterly MD&A.

5 Gold equivalent production was calculated based on an 80:1 silver to gold ratio