Americas GOLD and Silver Corporation Provides Operations Update

Mine Development & Operations

1 

AMERICAS GOLD AND SILVER CORPORATION PROVIDES OPERATIONS UPDATE 

TORONTO, ONTARIO—May  4, 2020—Americas  Gold and Silver Corporation (TSX: USA) (NYSE American: 

USAS)  (“Americas”  or  the  “Company”),  a  growing  North  American  precious  metals  producer,  today 

provided an operations update. 

Summary

● Relief Canyon poured first gold in  mid‐February 2020 and the Company remains confident that 

commercial  production  can  be  achieved  towards  the  end  of  Q2‐2020  or  beginning  of  Q3‐2020 

despite the challenges presented by COVID‐19. 

● While  Relief  Canyon  has  been  operating  through  the  COVID‐19  pandemic,  ramp‐up  has  been 

slower  than  anticipated  due  to  an  inability  to  get  key  management  and  consultants  to  site  to 

troubleshoot common start up challenges.  

● All  operating  aspects  of  Relief  Canyon  have  now  started  to  meet  budget  parameters.   Waste 

movement is ahead of budget and there is an ore stockpile of over 0.2 million tonnes.  As of April 

30,  2020,  approximately  3.3  million  tonnes  of  material  have  been  mined,  including  2.5  million 

tonnes of waste and 0.8 million tonnes of ore.   

● Ore gold grade mined and early grade reconciliation are in‐line with the mine plan. 

● Ore  leaching  has  been  slower  than  planned,  a  common  issue  when  commissioning  heap  leach 

operations.   Pregnant solution grade and solution application rate are now nearing design levels 

following improvements to agglomeration, solution application and stacking practices.  

● The Galena recapitalization plan (“Recapitalization Plan”) is proceeding better than expectations 

with  the  Company  seeing  benefits  in  both  production  and  exploration.   The  Company  plans  to 

update the market on this asset on a more regular basis moving forward. 

● The Mexican government issued a national decree to suspend non‐essential businesses in relation 

to the COVID‐19 pandemic until the end of May.  This order affects all mining operations. 

● Due to the rapidly changing and on‐going uncertainty caused by the COVID‐19 pandemic, which 

has resulted in the reduced ability to adequately meet the normal commissioning challenges at 

Relief  Canyon  with  the  COVID‐19  limitations  in  place  and  impact  to  the  Cosalá  Operations,  the 

Company has decided to withdraw its full‐year 2020 guidance.  

● Outlook for 2021 continues to be 90,000 to 110,000 gold equivalent ounces which assumes Relief 

Canyon  is  fully  ramped  up  to  commercial  production  and  the  Cosalá  Operations  has  resumed 

normal operations and expected production. 

● As of March 31, 2020, the Company had cash and cash equivalents of $16.3 million which includes 

funds under the Galena Recapitalization Plan.  

“All aspects of the Relief Canyon mine are starting to perform near design capacity following some initial 

teething pains common to commissioning a new operation.  These start‐up challenges took slightly longer 

to remediate due to travel and operational restrictions caused by the COVID‐19 pandemic.  However, Relief 

Canyon is now well on its way to a successful ramp‐up.   Americas Gold and Silver is closely monitoring 

2 

developments regarding the outbreak of COVID‐19 and our priority is to protect the health and safety of 

our employees by providing a safe work environment,” said Americas President & CEO Darren Blasutti. 

Relief Canyon 

Relief Canyon successfully poured its first gold in mid‐February 2020 with initial construction completed 

nine months after construction formally commenced in mid‐May 2019.   The initial capital spend to first 

production was within the guidance range the Company provided of US$28 to US$30 million.   

The Company is targeting commercial production by the end of Q2‐2020 or beginning of Q3‐2020, which 

represents  a  potential  delay  of  approximately  one  month  from  the  previous  expectations.   While 

operations  continue  during  the  COVID‐19  pandemic,  the  Company  has  been  limited  in  its  ability  to 

promptly troubleshoot ramp‐up issues often present when commissioning a new mine. 

Mining rates have steadily increased and total tonnes mined are close to budget.   As of April 30, 2020, 

approximately 3.3 million tonnes of material have been mined, including 2.5 million tonnes of waste and 

0.8 million tonnes of ore.   Waste movement is ahead of budget and the operation currently has an ore 

stockpile of approximately 0.2 million tonnes ahead of the crusher waiting to be placed on the leach pad.  

To‐date, approximately 0.6 million tonnes of ore have been stacked on the leach pad. 

Mined ore grade is reconciling well to the block model.   Ore grade from these early phases of the mine 

plan are lower than the life of mine average grade and the Company expects mined ore grade to increase 

towards the end of the year and into 2021.  Ore crushing and stacking rates are steadily increasing. 

Following the first gold pour in February, solution flow rates to the leach pad increased at a slower rate 

than anticipated.  The Company is confident that measures taken in the past five weeks, including improved 

agglomeration and stacking practices, will allow the operation to continue its ramp‐up to feasibility study 

targets.   Solution  and  grade  are  now  on‐track  to  meet  expectations  and  any  placed  ounces  will  be 

recovered through the leach cycle.  

Galena Complex 

The Galena Complex is benefiting from the previously announced Recapitalization Plan that commenced 

in October 2019.  The Recapitalization Plan improves productivity in the short term with the purchase and 

refurbishment of underground mining equipment.  Underground development improvements, additional 

equipment procurements, and an exploration drilling program will benefit the operation longer term by 

further  improving  mining  efficiency  and  lowering  cash  costs.   Exploration  is  aimed  at  adding  mineral 

resources with exploration success already realized in Q1‐2020. 

Production 

The Recapitalization Plan is still in the early stages of implementation but the Company is already starting 

to see the benefits in terms of production and a reduction in cash operating costs.  The Galena Complex 

increased production and lowered cash costs in Q1‐2020 compared to Q4‐2019; silver and lead production 

increased  by  44%  and  67%  respectively.   During  the  Recapitalization  Plan,  the  Company  has  chosen  to 

exclude production and cost figures from the outlook but feel that it is important to provide an update to 

the significant improvements already demonstrated by the operation. 

3 

Development 

Redevelopment of existing infrastructure is progressing on the 4300 and 5500 Levels which includes drift 

rehabilitation and rail replacement.  On the 4300 Level, drift rehabilitation is over 70% complete, with new 

rail placement over 60% complete.  The 4300 Level rehabilitation is expected to be finished by the end of 

May 2020.  A recently developed drill station on the 4300 Level will facilitate testing of up‐dip extensions 

of silver/lead‐rich zones starting in mid‐May 2020.  The 5500 Level drift rehabilitation is complete and rail 

installation  is  well  underway.   Additionally,  ramp  development  between  the  5200  and  5500  Levels  is 

proceeding according to plan.  This ramp development provides access to two mining fronts, which when 

complete, will allow more efficient movement of equipment and workers between levels.   Repair of the 

lowest loading pocket is also proceeding, which when finished, will allow material to be hoisted from the 

5500 Level. 

Equipment 

With  the  Recapitalization  Plan,  the  operation  has  acquired  several  new  pieces  of  equipment  to  help 

improve productivity.  A 4‐yard scoop and a single boom jumbo are now in service.  Two 3.5‐yard scoops 

are on‐site, being disassembled for shipment and reassembly underground. 

Exploration 

The Recapitalization Plan has budgeted approximately 39,000 meters of exploration drilling with over 9,000 

meters (or over 20%) complete.  Based on the current drill plan, the Company expects drilling to finish in 

approximately 15 months with two drills in operation.  Targets include up‐dip and down‐dip extensions of 

known veins, with emphasis on untested zones below the 5500 Level, which is the deepest working level 

of the mine.  Additionally, a new geologic model is partially complete.  The geologic model will be used for 

target improvements in the near term and exploration for new orebodies longer term.   

Drilling on the 3200 Level extended the strike and dip length of several veins with widths and grades the 

Company expects to be economic in the future.  Five veins in the Upper Country Lead Zone (UCLZ) were 

extended between 37 and 61 meters to the east.  These veins are adjacent to current production areas on 

the level.  The 133 vein was extended 107 meters along strike and 70 meters up‐dip and down‐dip.  A 9.1‐

meter siderite vein zone was crossed 500 meters north of the 3200 Level in an area previously untested on 

the South Argentine fault.  This zone has the potential to be a new orebody and will be explored from the 

4300 and 5500 Levels as drilling continues.  The current 3200 Level drill program will be completed in early 

May, followed by drilling on the 4300 Level targeting upper extensions of the 360 vein system. 

Drilling from the 5200 Level has focused on deep extensions of mineralization centred around the 291 and 

360 vein systems with encouraging results.   The two deepest holes project‐to‐date include the highest‐

grade values.  Hole 52‐493 crossed the 291 vein more than 60 meters below the current mineral resource 

with an interval grading 3,020 grams per tonne silver over a true width of 1.4 meters.  In drill hole 52‐501, 

a new vein was crossed in the footwall of the 360 vein approximately 85 meters below the 5200 Level.  The 

unnamed vein assayed 2,123 grams per tonne silver over 0.8 meters and has the potential to become a 

new mining front with additional drilling.   

The 16‐hole drill program on 5200 Level is nearing completion.  Drilling will commence from the 5500 Level 

in mid‐May, targeting what the Company’s geologists believe to be some of the most prospective targets 

in the mine.  This includes the down‐dip projection of the 72 vein, which was the main source of ore during 

the peak silver production years of 2000‐2004.  Drilling will focus on areas to the east and below historical 

workings, which produced average grades of over 680 grams per tonne silver.  In addition to targeting the 

4 

72 vein, exploration will focus on what has been described as the “triple point”, where the high‐grade 175, 

185 and Silver veins are projected to converge.  This area has never been explored and is projected to be 

100 meters below historical workings.  Follow‐up drilling in the 291 and 360 vein systems is also planned 

from 5500 Level and is designed to extend these zones down‐dip. 

The following table summarizes the most significant intercepts of the program to date: 

Hole  Vein  Zone  From 

(m) 

To  

(m) 

True Width 

(m) 

Ag 

(g/t) 

Pb 

(%) 

Cu 

(%) 

AgEq1 

(g/t) 

32‐091  4  UCLZ  29.8  30.9  0.9  467  5.9 ‐   704 

  3  UCLZ  52.3  54.4  1.8  283  9.8 ‐   675 

32‐092  4  UCLZ  26.6  27.5  0.9  250  9.7 ‐   638 

32‐093  5  UCLZ  32.6  34.4  0.8  447  16.9 ‐   1,122 

  133  UCLZ  153.0  153.9  0.7  306  9.9 ‐   704 

32‐096  Fuller  UCLZ  49.1  50.1  1.0  251  15.9 ‐   887 

  133  UCLZ  86.9  87.2  0.3  343  15.2 ‐   951 

32‐097  4B  UCLZ  30.0  31.4  1.1  301  12.3 ‐   793 

  133  UCLZ  140.5  141.3  0.7  593  19.9 ‐   1,390 

32‐099  5  UCLZ  59.4  61.1  1.0  159  11.8 ‐   632 

  3  UCLZ  84.4  85.2  0.6  331  11.4 ‐   787 

52‐487  242  291 System  124.5  125.9  1.0  312  12.4 ‐   809 

including  242   124.5  125.0  0.3  837  32.6 ‐   2,141 

52‐488  348  360 System  75.9  78.7  2.6  271  12.6 ‐   777 

52‐490      89.4  90.1  0.4  1,295  5.5  0.5  1,572 

52‐491  291  291 System  99.5  100.7  1.2  1,430 ‐   0.9  1,531 

including      100.5  100.7  0.2  7,544 ‐   4.7  8,083 

52‐493  291  291 System  154.9  156.7  1.4  3,020 ‐   2.3  3,284 

including     155.4  156.7  1.0  4,252 ‐   3.2  4,623 

52‐494  291  291 System  122.3  124.8  2.1  430 ‐   0.5  489 

52‐495  291  291 System  132.7  133.7  0.8  473 ‐   0.4  518 

52‐496  291  291 System  206.3  207.6  0.9  892 ‐   2.9  1,221 

52‐499  370  360 System  252.7  254.1  0.7  378  9.2 ‐   750 

  360  360 System  257.5  258.4  0.4  1,737  25.9  0.3  2,803 

52‐501  239  291 System  147.0  148.3  0.7  373  12.3 ‐   867 

including     147.3  147.4  0.1  1,156  38.5 ‐   2,696 

including     147.8  148.0  0.1  1,101  34.2 ‐   2,469 

52‐501  368  360 System  229.4  230.6  0.6  800  26.6 ‐   1,863 

52‐501  370  360 System  232.9  234.1  0.7  422  16.1 ‐   1,066 

52‐501  360  360 System  256.4  258.9  1.3  364  5.8 ‐   596 

including      257.2  257.4  0.1  2,428  39.1 ‐   3,992 

52‐501    360 System  321.2  323.2  0.8  2,123 ‐   0.9  2,232 

including      321.2  321.9  0.3  4,595 ‐   1.9  4,817 

A full table of all drill results is available on our website at: 

https://www.americas‐gold.com/site/assets/files/5450/dr20200504.pdf 

Cosalá Operations 

On  March  31,  2020,  the  Government  of  Mexico  issued  a  national  COVID‐19  related  decree  for  the 

temporary suspension of all non‐essential businesses in the country, including all mining operations, until 

at least the end of May.  At this time, the Company’s Cosalá Operations continue to be illegally occupied 

(see Company news release dated February 3, 2020).  While the Company cannot negotiate with the self‐

interested  representatives  of  this  illegal  action,  it  is  optimistic  that  a  legal  and  legitimate  labour 

representative for its workers will be identified, and the mine will be in a position to re‐open after any 

COVID‐19 restrictions are lifted.  The Company’s priority continues to be the safety of its workers and the 

5 

community of Cosalá that have been negatively impacted – first by the illegal blockade and now by the 

COVID‐19 pandemic. 

2020 Guidance Withdrawal and Q1 2020 Quarterly Results Update 

The Company continues to assess the potential impacts of the COVID‐19 pandemic on operations during 

this unprecedented period.  Due to the rapidly changing and on‐going uncertainty caused by the COVID‐19 

pandemic, which has resulted in a reduced ability to efficiently meet normal commissioning challenges at 

Relief Canyon with the COVID‐19 limitations in place and impact to the Cosalá Operations, the Company 

has decided to withdraw the full‐year 2020 guidance.  The Company believes it is prudent to take this step 

as the global COVID‐19 pandemic continues to develop, particularly given the significant risk related to the 

potential for additional government laws, regulations or other measures that might be required that could 

impact its ability to operate, such as business disruptions in supply chains, disruptions in the markets for 

our products, commodity prices generally as well as global health and economic impacts.   The Company 

will continue to target safe and effective execution of its operation and production plans.  The Company 

does  not  expect  that  these  factors  will  materially  impact  its  growth  plans  and  the  previously  provided 

outlook for 2021 and beyond, as applicable, to the extent that commercial production is achieved at Relief 

Canyon  on  the  currently  expected  timing  in  2020  and  resumption  at  the  Cosalá  Operations  of  normal 

operations and production occurs by the end of 2020. 

The  Company  expects  to  provide  updated  financial  and  quarterly  production  results  with  its  Q1‐2020 

release.  The Company will provide updated timing and details of our quarterly conference call in advance. 

Technical Information 

The diamond drilling program used NQ‐size drilling.  Americas Gold and Silver’s standard QA/QC practices 

were utilized to ensure the integrity of the core and sample preparation at the Galena Complex through 

delivery of the samples to the assay lab.  The drill core was stored in a secure facility, photographed, logged 

and  sampled  based  on  lithologic  and  mineralogical  interpretations.   Standards  of  certified  reference 

materials, field duplicates and blanks were inserted as samples shipped with the core samples to the lab.   

Analytical work was carried out by American Analytical Services Inc. (“AAS”) located in Osburn, Idaho.  AAS 

is an independent, ISO‐17025 accredited laboratory.  Sample preparation includes a 30‐gram pulp sample 

analyzed by atomic absorption spectrometry (“AA”) techniques to determine silver, copper, and lead, using 

aqua regia for pulp  digestion.   Samples returning values over 514g/t Ag are re‐assayed using fire‐assay 

techniques for silver.   Additionally, samples returning values over 23% Pb are re‐assayed using titration 

techniques.  

Duplicate  pulp  samples  were  sent  out  quarterly  to  ALS  Global,  an  independent,  ISO‐17025  accredited 

laboratory based in Reno, Nevada to perform an independent check analysis.  A conventional AA technique 

was  used  for  the  analysis  of  silver,  copper  and  lead  at  ALS  Global  with  the  same  industry  standard 

procedures  as  those  used  by  AAS.   The  assay  results  listed  in  this  report  did  not  show  any  significant 

contamination during sample preparation or sample bias of analysis. 

6 

About Americas Gold and Silver Corporation 

Americas  Gold  and  Silver  Corporation  is  a  high‐growth  precious  metals  mining  company  with  multiple 

assets in North America.  The Company’s newest asset, Relief Canyon in Nevada, USA, has poured first gold 

and  is  expected  to  ramp  up  to  full  production  over  the  course  of  2020.   The  Company  also  owns  and 

operates the Cosalá Operations in Sinaloa, Mexico and manages the 60%‐owned Galena Complex in Idaho, 

USA.   The Company also holds an option on the San Felipe development project in Sonora, Mexico.   For 

further information, please see SEDAR or www.americas‐gold.com. 

For more information: 

Stefan Axell        Darren Blasutti 

VP, Corporate Development & Communications   President and CEO 

Americas Gold and Silver Corporation     Americas Gold and Silver Corporation 

416‐874‐1708        416‐848‐9503 

Qualified Persons 

Niel  de  Bruin,  Director  of  Geology  and  a  Qualified  Person  under  Canadian  Securities  Administrators 

guidelines, has approved the applicable contents of this news release. 

Cautionary Statement on Forward‐Looking Information: 

This news release contains “forward‐looking information” within the meaning of applicable securities laws.  

Forward‐looking  information  includes,  but  is  not  limited  to,  Americas  Gold  and  Silver’s  expectations, 

intentions, plans, assumptions and beliefs with respect to, among other things, estimated production rates 

and results for gold, silver and other precious metals, as well as the related costs, expenses and capital 

expenditures, the Company’s construction, production, development plans and performance expectations 

at the Relief Canyon Mine, including the anticipated timing of commercial production at Relief Canyon, the 

resolution and removal of the illegal blockade at the Company’s Cosalá Operations and the resumption of 

mining and processing operations.   Often, but not always, forward‐looking information can be identified 

by forward‐looking words such as “anticipate”, “believe”, “expect”, “goal”, “plan”, “intend”, “potential’, 

“estimate”,  “may”,  “assume”  and  “will”  or  similar  words  suggesting  future  outcomes,  or  other 

expectations,  beliefs,  plans,  objectives,  assumptions,  intentions,  or  statements  about  future  events  or 

performance.  Forward‐looking information is based on the opinions and estimates of Americas Gold and 

Silver as of the date such information is provided and is subject to known and unknown risks, uncertainties, 

and  other  factors  that  may  cause  the  actual  results,  level  of  activity,  performance,  or  achievements  of 

Americas  Gold  and  Silver  to  be  materially  different  from  those  expressed  or  implied  by  such  forward‐

looking information.  With respect to the business of Americas Gold and Silver, these risks and uncertainties 

include risks relating to widespread epidemics or pandemic outbreak including the COVID‐19 pandemic; 

the impact of COVID‐19 on our workforce, suppliers and other essential resources and what effect those 

impacts, if they occur, would have on our business, including our ability to access goods and supplies, the 

ability to transport our products and impacts on employee productivity, the risks in connection with the 

operations,  cash  flow  and  results  of  the  Company  relating  to  the  unknown  duration  and  impact  of  the 

COVID‐19 pandemic; interpretations or reinterpretations of geologic information; unfavorable exploration 

results; inability  to obtain  permits required for future exploration, development or production; general 

economic  conditions  and  conditions  affecting  the  industries  in  which  the  Company  operates;  the 

uncertainty  of  regulatory  requirements  and  approvals;  fluctuating  mineral  and  commodity  prices;  the 

ability to obtain necessary future financing on acceptable terms or at all; the ability to develop, complete 

7 

construction,  bring  to  production  and  operate  the  Relief  Canyon  Project;  and  risks  associated  with  the 

mining industry such as economic factors (including future commodity prices, currency fluctuations and 

energy  prices),  ground  conditions  and  other  factors  limiting  mine  access,  failure  of  plant,  equipment, 

processes  and  transportation  services  to  operate  as  anticipated,  environmental  risks,  government 

regulation, actual results of current exploration and production activities, possible variations in ore grade 

or recovery rates, permitting timelines, capital and construction expenditures, reclamation activities, labor 

relations  or  disruptions,  social  and  political  developments  and  other  risks  of  the  mining  industry.   The 

potential  effects  of  the  COVID‐19  pandemic  on  our  business  and  operations  are  unknown  at  this  time, 

including  the  Company’s  ability  to  manage  challenges  and  restrictions  arising  from  COVID‐19  in  the 

communities in which the Company operates and our ability to continue to safely operate and to safely 

return our business to normal operations.   The impact of COVID‐19 on the Company is dependent on a 

number of factors outside of its control and knowledge, including the effectiveness of the measures taken 

by  public  health  and  governmental  authorities  to  combat  the  spread  of  the  disease,  global  economic 

uncertainties and outlook due to the disease, and the evolving restrictions relating to mining activities and 

to  travel  in  certain  jurisdictions  in  which  it  operate.   Although  the  Company  has  attempted  to  identify 

important  factors  that  could  cause  actual  results  to  differ  materially  from  those  contained  in  forward‐

looking information, there may be other factors that cause results not to be as anticipated, estimated, or 

intended.  Readers are cautioned not to place undue reliance on such information.  Additional information 

regarding  the  factors  that  may  cause  actual  results  to  differ  materially  from  this  forward‐looking 

information is available in Americas filings with the Canadian Securities Administrators on SEDAR and with 

the SEC.  Americas does not undertake any obligation to update publicly or otherwise revise any forward‐

looking  information  whether  as  a  result  of  new  information,  future  events  or  other  such  factors  which 

affect this information, except as required by law.  Americas does not give any assurance (1) that Americas 

will achieve its expectations, or (2) concerning the result or timing thereof.  All subsequent written and oral 

forward‐looking information concerning Americas are expressly qualified in their entirety by the cautionary 

statements above. 

Cautionary Note to U.S. Investors: 

The terms “proven and probable reserve”, “resource”, “measured resource”,  “indicated resource”, and 

“inferred resource” used in the press release are mining terms used in accordance with Canadian National 

Instrument  43‐101 ‐   Standards  of  Disclosure  for  Mineral  Projects  under  the  guidelines  set  out  in  the 

Canadian  Institute  of  Mining,  Metallurgy  and  Petroleum  Standards.   Mineral  resources  which  are  not 

mineral reserves do not have demonstrated economic viability. 

While  the  terms  “mineral  resource”,  “measured  mineral  resource”,  “indicated  mineral  resource”,  and 

“inferred mineral resource” are recognized and required by Canadian regulations, they are not defined 

terms  under  standards  in  the  United  States  and  normally  are  not  permitted  to  be  used  in  reports  and 

registration  statements  filed  with  the  Securities  &  Exchange  Commission  (“SEC”).   Moreover,  the 

definitions of proven and probable reserves used in NI 43‐101 differ from the definitions in the United 

States  Securities  and  Exchange  Commission's  Industry  Guide  7.   As  such,  information  contained  in  the 

Company's disclosure concerning descriptions of mineralization, reserves and resources under Canadian 

standards may not be comparable to similar information made public by U.S companies in SEC filings.  With 

respect to “inferred mineral resource” there is a great amount of uncertainty as to their existence and a 

great uncertainty as to their economic and legal feasibility.  It cannot be assumed that all or any part of an 

“inferred mineral resource” will ever be upgraded to a higher category.   Investors are cautioned not to 

assume that any part or all of the mineral deposits in these categories will ever be converted into reserves. 

8 

1 AgEq was calculated using metal prices of $18.00/oz silver, $3.00/lb copper and $1.05/lb lead