Ur‐Energy Provides 2018 Q4 Operational Results

Production Results

10758 W. Centennial Rd. Suite 200

Littleton, CO 80127

Phone: 720.981.4588

Fax: 720.981.5643

www.ur-energy.com

News Release

Ur‐Energy Provides 2018 Q4 Operational Results  

Littleton, Colorado (PR Newswire – January 14, 2019) Ur‐Energy Inc. (NYSE American:URG)(TSX:URE) (the 

“Company” or “Ur‐Energy”) is pleased to provide the following operational results for fourth quarter 2018. 

Highlights 

   Lost Creek Operations 

  Units  2018 Q1    2018 Q2    2018 Q3    2018 Q4    2018 

U3O8 Captured  (‘000 lbs)  84.0    89.2    80.6    48.4    302.2 

U3O8 Dried & 

Drummed  (‘000 lbs)  80.0    74.3    78.4    53.7    286.4 

U3O8 Sold  

(from production)  (‘000 lbs)  10.0    0    0    0    10.0 

U3O8 Sold (from 

purchased lbs)  (‘000 lbs)  370.0    100.0    0    0    470.0 

Average Flow Rate  (gpm)  2,432    2,517    2,247    2,019    2,303 

U3O8 Head Grade  (mg/l)  33    34    34    23    31 

Lost Creek Uranium Production and Sales 

For the quarter, 48,304 pounds of U3O8 were captured within the Lost Creek plant, 53,654 pounds of U3O8 

were packaged in drums and 67,040 pounds of U3O8 drummed inventory were shipped out of the Lost 

Creek  processing  plant.  At  December  31,  2018,  inventory  at  the  conversion  facility  was  approximately 

375,803 pounds U3O8. 

In 2018, sales totaled $23.5 million from 480,000 pounds sold. Our overall price per pound sold averaged 

$48.86. There was one small, tax driven, spot sale of 10,000 pounds in 2018 from Lost Creek production. 

We  delivered  470,000  purchased  pounds  into  contractual  obligations  at  an  average  price  of  $49.40. 

Purchases  for  these  deliveries  averaged  $24.42  per  pound.  Gross  profits  from  contractual  sales  were 

$11.7 million, which represents a gross profit margin in excess of 50%. 

Lost Creek Operations 

Lost  Creek  celebrated  its  fifth  anniversary  in  August  and  after  more  than  five  continuous  years  of 

operation, our production now stands at approximately 2.7 million pounds captured through the end of 

2018. During this time, we delivered approximately 2.2 million pounds of Lost Creek production to our 

customers as well as another 1.2 million of purchased pounds for a total of 3.4 million pounds sold.  

2 

To date, our first mine unit (“MU1”) has recovered over 91% of the estimated under‐pattern resource, 

based upon the revised and updated Lost Creek Preliminary Economic Assessment (as amended, February 

2016, the “PEA”). This is compared to an accepted industry standard of 70% to 80% recovery of under‐

pattern resource. As well, project economics in the PEA were based on an 80% recovery. In addition, the 

operating patterns in our second mine unit (“MU2”) have recovered nearly 65% of their estimated under‐

pattern resources with the bulk of those operating less than a year. 

Guidance for 2019 

Spot uranium prices recovered approximately 17% in 2018.  Should uranium pricing continue to improve, 

or following a successful outcome of the ongoing Section 232 uranium investigation in the United States, 

the Company stands ready to ramp up production to full capacity at Lost Creek and initiate development 

activities at Shirley Basin. 

It should be noted that the only reason the Company reduced production levels beginning in 2016 was in 

response to a persistently weak uranium market. Nevertheless, we have remained operationally ready to 

increase  production  to  pre‐2016  levels,  or  higher,  when  market  conditions  warrant  the  futher 

development of our fully‐permitted MU2 at Lost Creek. Lost Creek operations could increase production 

rates in as little as six months following a go decision simply by developing additional header houses within 

MU2. Development expenses during this time are estimated to be less than $14 million and are almost 

entirely  related  to  MU2  drilling  and  header  house  construction  costs.  Lost  Creek  does  not  require  any 

significant capital expeditures in order to increase production. The Lost Creek plant has been very well 

maintained and is fully ready to receive additional flows for increased production when warranted. 

Meanwhile, we continue to pursue the permitting and licensure of our second operation at the Shirley 

Basin project, also in Wyoming. The preliminary economic assessment for this project was completed in 

2015 and, since then, we monitored with great interest the State of Wyoming’s pursuit and development 

of its Uranium Recovery Program and were delighted when the program was stood up in September 2018. 

Currently, we are working with the State to advance the process for our Shirley Basin project to secure the 

licenses and permits necessary to begin staged construction and development of the project in 2019, with 

full operation as early as mid‐2020. Again, in response to an improving uranium market, or following the 

successful  outcome  of  the  Section  232  uranium  investigation,  we  plan  to  initiate  construction  and 

development activities at Shirley Basin following the ramp up of the Lost Creek operation. 

In 2019, we expect to deliver 500,000 pounds into our term contracts at an average price of approximately 

$49 per pound. We have corresponding purchase contracts in place for 500,000 pounds at an average cost 

of $26 per pound. Gross profits are expected to generate approximately $11.5 million from the sale of 

purchased product. 97,500 pounds are scheduled to be sold in Q1 2019. 

We  currently  have  over  375,000  pounds  of  finished,  ready‐to‐sell,  product  inventory  in  storage  at  the 

conversion facility. The value of the product at today’s spot price is approximately $10.7 million.  However, 

we  intend  to  hold  and  modestly  build  this  inventory  during  the  year  in  order  to  satisfy  our  remaining 

contractual sales obligations of 415,000 pounds at an average sales price of $47 per pound, the majority 

of  which  will  be  sold  in  2020.  The  inventoried  pounds,  or  the  in‐the‐money  contracts  themselves,  can 

readily be converted to cash on an as‐needed basis. 

3 

Regarding the Section 232 trade action, the Department of Commerce (“DOC”) continues it investigation 

into the impact of uranium imports on national security. DOC investigators toured Lost Creek and projects 

operated by our co‐Petitioner, Energy Fuels, during Q4 2018. DOC will submit its report to the President 

containing  the  Secretary’s  findings  and  recommendations  of  a  proposed  remedy,  if  any,  in  Q2  2019.  

Following receipt of the report, the President has up to 90 days to act on the Secretary’s report. 

We will provide further guidance for 2019 production and other operational matters in our Annual Report 

on Form 10‐K, which is currently anticipated to be filed on Friday, March 1, 2019, and throughout the year 

as matters progress. 

About Ur‐Energy 

Ur‐Energy is a uranium mining company operating the Lost Creek in‐situ recovery uranium facility in south‐

central Wyoming. We have produced, packaged and shipped approximately 2.5 million pounds from Lost Creek 

since the commencement of operations. Applications are under review by various agencies to incorporate our 

LC East project area into the Lost Creek permits, and to construct and operate at our Shirley Basin Project. Ur‐

Energy is engaged in uranium mining, recovery and processing activities, including the acquisition, exploration, 

development and operation of uranium mineral properties in the United States.  Shares of Ur‐Energy trade on 

NYSE  American  under  the  symbol  “URG”  and  on the  Toronto  Stock  Exchange  under  the  symbol  “URE.”  Ur‐

Energy’s corporate office is in Littleton, Colorado; its registered office is in Ottawa, Ontario. Ur‐Energy’s website 

is www.ur‐energy.com. 

FOR FURTHER INFORMATION, PLEASE CONTACT 

Jeffrey Klenda, Chair and CEO

+1 720‐981‐4588

Jeff.Klenda@ur‐energy.com

Cautionary Note Regarding Forward‐Looking Information 

This  release  may  contain  “forward‐looking  statements”  within  the  meaning  of  applicable  securities  laws 

regarding events or conditions that may occur in the future (e.g., continuing results of Lost Creek operations 

and the timing and ability to ramp up operations; timing and outcome for resolution of the Section 232 trade 

action or other changes to the uranium market; timing and outcome for all permitting and licensure of the 

Shirley Basin project and for the subsequent buildout of the project; and whether adjustments of production 

rates at Lost Creek will be necessary or appropriate during 2019) and are based on current expectations that, 

while considered reasonable by management at this time, inherently involve a number of significant business, 

economic and competitive risks, uncertainties and contingencies. Factors that could cause actual results to 

differ  materially  from  any  forward‐looking  statements  include,  but  are  not  limited  to,  fluctuations  in 

commodity prices; capital and other costs varying significantly from estimates; failure to establish estimated 

resources and reserves; the grade and recovery of uranium which is mined varying from estimates; production 

rates,  methods  and  amounts  varying  from  estimates;  delays  in  obtaining  or  failures  to  obtain  required 

governmental, environmental or other project approvals; inflation; delays in development and other factors 

described in the public filings made by the Company at www.sedar.com and www.sec.gov. Readers should not 

place undue reliance on forward‐looking statements. The forward‐looking statements contained herein are 

based on the beliefs, expectations and opinions of management as of the date hereof and Ur‐Energy disclaims 

any  intent  or  obligation  to  update  them  or  revise  them  to  reflect  any  change  in  circumstances  or  in 

management’s beliefs, expectations or opinions that occur in the future.