Resource Estimates

News Release

10758 W. Centennial Rd. Suite 200

Littleton, CO 80127

Phone: 720.981.4588

www.ur-energy.com

Ur-Energy Files Updated S-K 1300 Reports

for the Lost Creek ISR Uranium Property and the Shirley Basin ISR Uranium Project

Littleton, Colorado ( ACCESSWIRE – March 6 , 20 24) Ur-Energy Inc. ( NYSE American:URG) ( TSX:URE) ( the

“Company” or “Ur-Energy”) is pleased to announce that it has filed updated S-K 1300 Technical Report Summaries

for its Lost Creek Property and Shirley Basin Project. The reports are filed as exhibits to the Company’s Annual

Report on Form 10- K, filed March 6 , 202 4, with the U.S. Securities and Exchange Commission on EDGAR at

www.sec.gov/edgar.shtml. Both reports were prepared by Qualified Person, Western Water Consultants, Inc.,

d/b/a WWC Engineering (“WWC”).

Steve Hatten, Ur-Energy COO, “We are very pleased to provide update d Technical Report Summaries related to

our producing Lost Creek Property and our Shirley Basin Project. WWC’s review of the geologic and economic data

supports the continuing potential viability of both projects. While economic conditions have changed in the last

two years, both continue to provide excellent potential returns. The Lost Creek Report supports our decision in

2022 to bring the project back into production. Moreover, we have already begun shipping uranium from the

newest Lost Creek production areas. The Shirley Basin Report reinforces our belief that Shirley Basin will likely be

our second operating project. To that end, we have continued with detailed engineering and production designs

while waiting for that production opportunity. With these two properties, Ur -Energy will be ready to supply fuel

for clean energy solutions to America’s power needs.”

Initial Assessment of Lost Creek ISR Uranium Property, Sweetwater County, Wyoming, USA

We have filed an updated Initial Assessment Technical Report Summary on our Lost Creek Property, Sweetwater

County, Wyoming, USA (the “Lost Creek Report,” March 4, 2024), which was prepared by WWC. The resources

identified and evaluated have been included in the Lost Creek production plan and continue to support the

potential viability of the Property.

The mineral resource estimate for the Property is 12.682 million pounds eU 3O8 in the Measured and Indicated

categories, and 6.119 million pounds eU 3O8 in the Inferred category. The mineral resource has been reduced to

account for production at Lost Creek of 2.838 million pounds U3O8 at year-end 2023.

Measured Indicated Inferred

Project Avg Grade

% eU3O8

Short Tons

(X 1000)

Pounds

(X 1000)

Avg Grade

% eU3O8

Short Tons

(X 1000)

Pounds

(X 1000)

Avg Grade

% eU3O8

Short Tons

(X 1000)

Pounds

(X 1000)

LOST

CREEK 0.049 10,032 9,819 0.046 2,699 2,503 0.045 2,834 2,527

Production

through

12/31/2023

0.049 -2,896 -2,838

LC EAST 0.052 1,401 1,465 0.042 1,883 1,568 0.042 2,954 2,481

LC NORTH ----- ----- ----- ----- ----- ----- 0.045 644 581

LC SOUTH ----- ----- ----- 0.037 221 165 0.039 637 496

LC WEST ----- ----- ----- ----- ----- ----- 0.109 16 34

EN ----- ----- ----- ----- ----- ----- ----- ----- -----

GRAND

TOTAL 0.049 8,537 8,446 0.044 4,803 4,236 0.043 7,085 6,119

MEASURED + INDICATED = 13,340 12,682

- 2 -

1. Sum of Measured and Indicated tons and pounds may not add to the reported total due to rounding.

2. % eU3O8 is a measure of gamma intensity from a decay product of uranium and is not a direct measurement

of uranium. Numerous comparisons of eU3O8 and chemical assays of Lost Creek rock samples, as well as PFN

logging, indicate that eU3O8 is a reasonable indicator of the chemical concentration of uranium.

3. Table shows resources based on grade cutoff of 0.02 % eU3O8 and a grade x thickness cutoff of 0.20 GT.

4. Measured, Indicated, and Inferred Mineral Resources as defined in 17 CFR § 229.1300.

5. Resources are reported through December 31, 2023.

6. All reported resources occur below the static water table.

7. 2.838 million lbs. of U3O8 have been produced from the HJ Horizon in the Lost Creek Project as of December

31, 2023.

8. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

9. The point of reference for resources is in situ at the Property.

The economic analyses within the Lost Creek Report continue to support the potential viability of the Property .

Total future life of mine (LoM) production is modeled to be 11.7 million pounds from 2024 to 2036 with LoM

operating costs estimated to be $16.73 per pound. All in, the estimated total costs per pound, including royalties

and extraction taxes, is estimated at $39.72 per pound before income tax of $10.30 per pound. Pricing used in the

analysis ranged from $55.00 to $87.20 per pound.

Excluding sunk costs which occurred prior to December 31, 2023, the Property is estimated to generate LoM net

cash flow of $424.4 million before income taxes, and $ 303.6 million after income taxes. Payback of the initial

capital investments, including $18.2 million in sunk costs which occurred prior to the beginning of the analysis, is

estimated during the third quarter of 2026. The Property has a calculated before tax internal rate of return (IRR)

of 81.8 percent and a before tax net present value (NPV) of $225.5 million applying an eight percent discount rate.

When income taxes are included in the calculation, the after-tax IRR is 77.1 percent and the after tax NPV is $165.6

million.

Because inferred resources are mineral resources that are considered too speculative geologically to have

modifying factors applied to them that would enable them to be categorized as mineral reserves, under relevant

U.S. standards, there is no certainty that this economic assessment, which includes inferred resources, will be

realized. To account for the chance that the inferred resources are not upgraded as the Company collects

additional drilling data while mining progresses at Lost Creek, a second economic analysis was prepared which

excludes inferred resources, as required by S-K 1300.

The estimated LoM production excluding the inferred resources is modeled to be 8.8 million pounds from 2024

to early 2033. All in, the estimated total costs per pound, including royalties and extraction taxes, is estimated at

$42.30 per pound before income tax of $7.54 per pound. Excluding inferred resources, the Property is estimated

to generate net cash flow over its life of $ 271.7 million before income taxes, and $204.6 million after income

taxes. Excluding inferred resources, the Property has a calculated before tax IRR of 80.8 percent and a before tax

NPV of $162.2 million applying an eight percent discount rate. When income taxes are included in the calculation,

the after-tax IRR is 76.8 percent and the after tax NPV is $125.5 million.

Initial Assessment of Shirley Basin ISR Uranium Project, Carbon County, Wyoming, USA

We have filed an updated Initial Assessment Technical Report Summary on Shirley Basin ISR Uranium Project,

Carbon County, Wyoming, USA (the “Shirley Basin Report ,” March 4, 2024), which was prepared by WWC. The

report reaffirms the mineral resources as well as the economic analysis on the Shirley Basin Project from a prior

report prepared under S-K 1300.

Based upon data from the historical and confirmation drilling at the sit e, the Shirley Basin R eport confirms the

project’s mineral resource estimate of 8.8 million pounds eU 3O8 in the Measured and Indicated categories. Due

to the very high level of density in drilling at the project, all resources within the three proposed mine units are

classified as Measured or Indicated. There are no resources in the Inferred category.

- 3 -

RESOURCE

AREA

MEASURED INDICATED

AVG

GRADE

% eU3O8

SHORT TONS

(X 1000)

POUNDS U3O8

(X 1000)

AVG GRADE

% eU3O8

SHORT

TONS

(X 1000)

POUNDS

U3O8

(X 1000)

FAB

TREND 0.280 1,172 6,574 0.119 456 1,081

AREA 5 0.243 195 947 0.115 93 214

TOTAL 0.275 1,367 7,521 0.118 549 1,295

MEASURED & INDICATED 0.230 1,915 8,816

1. Sum of Measured and Indicated tons and pounds may not add to the reported total due to rounding.

2. Based on grade cutoff of 0.020 % eU3O8 and a grade x thickness (GT) cutoff of 0.25 GT.

3. Measured and Indicated mineral resources as defined in S-K 1300.

4. All reported resources occur below the historical, pre-mining static water table.

5. Average grades are calculated as weighted averages.

6. The point of reference for mineral resources is in-situ at the Project.

7. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Total LoM production is modeled to be 6. 0 million pounds over approximately nine years. LoM operating costs

estimated to be $24.40 per pound. All in, the estimated total costs per pound, including royalties, and extraction

and income taxes, is estimated at $54.89 per pound.

Using the estimated capital expenditures, operating expenditures and closure costs presented in the Shirley Basin

Report and projected variable long-term price ranging from $ 82.46 to $86.21 per pound, a cash flow statement

was generated in which the project is estimated to generate LoM net cash flow of $ 175.3 million before income

taxes and $119.0 million after tax. Payback is estimated during the third quarter of 2027. The project has a

calculated before tax IRR of 83.7 percent and NPV of $120.4 million applying an eight percent discount rate. When

income taxes are included in the calculation, the after-tax IRR is 69 percent and the after tax NPV is $83.2 million

applying an eight percent discount rate.

NOTE: We are required by applicable Canadian Securities Administrators to file in Canada a National Instrument

43-101 (“NI 43 -101”) compliant report at the same time we file an S -K 1300 technical report summary. The

NI 43-101 reports can be found on SEDAR at www.sedarplus.ca. The NI 43-101 and S-K 1300 reports (for each of

the Lost Creek Property and Shirley Basin Project) are substantively identical to one another except for internal

references to the regulations under which the report is made, and certain organizational differences.

Qualified Persons at WWC have reviewed and approved the technical disclosure contained in this news release.

The Initial Assessment Technical Report Summaries for each of the Lost Creek Property and Shirley Basin may also

be accessed on the Company’s website at www.ur-energy.com.

Cautionary statement: The Technical Report Summaries reported are preliminary in nature and, in the case of

the Lost Creek Report, includes inferred mineral resources that are considered too speculative geologically to

have the economic considerations applied to them that would enable them to be categorized as mineral

reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The

estimated mineral recovery used in these reports is based on recovery data from wellfield operations to date at

Lost Creek in the case of the Lost Creek Report , and Company personnel and industry experience at similar

- 4 -

facilities in the case of the Shirley Basin Report . There can be no assurance that recovery at this level will be

achieved.

FOR FURTHER INFORMATION, PLEASE CONTACT

John W. Cash, Chief Executive Officer

720-981-4588 (ext. 303)

[email protected]

About Ur-Energy

Ur-Energy is a uranium mining company operating the Lost Creek in-situ recovery uranium facility in south-central

Wyoming. We have produced, packaged, and shipped approximately 2. 8 million pounds U 3O8 from Lost Creek

since the commencement of operations. Ur -Energy now has all major permits and authorizations to begin

construction at Shirley Basin, the Company’s second in situ recovery uranium facility in Wyoming and is in the

process of obtaining remaining amendments to Lost Creek authorizations for expansion of Lost Creek. Ur-Energy

is engaged in uranium mining, recovery and processing activities, including the acquisition, e xploration,

development, and operation of uranium mineral properties in the United States. The primary trading market for

Ur-Energy’s common shares is on the NYSE American under the symbol “URG.” Ur -Energy’s common shares also

trade on the Toronto Stock Exchange under the symbol “URE.” Ur-Energy’s corporate office is located in Littleton,

Colorado and its registered office is located in Ottawa, Ontario.

Cautionary Note Regarding Forward-Looking Information

This release may contain “forward-looking statements” within the meaning of applicable securities laws regarding

events or conditions that may occur in the future ( e.g., the technical and economic viability, including mineral

resource estimates, life of mine, costs and production results for Lost Creek, including as set forth in the TRS Initial

Assessment for the project, and whether the report supports the decision to return to commercial production at

Lost Creek; the technical and economic viability, including mineral resource estimates, life of mine, costs and

production results for Shirley Basin, including as set forth in the TRS Initial Assessment for the project , including

whether Shirley Basin will be our second operating project) and are based on current expectations that, while

considered reasonable by management at this time, inherently involve a number of significant business,

economic, technical and competitive risks, uncertainties and contingencies. Generally, forward-looking

statements can be identified by the use of forward-looking terminology such as "plans," "expects," "does not

expect," "is expected," "is likely," "estimates," "intends," "anticipates," "does not anticipate," or "believes," or

variations of the foregoing, or statements that certain actions, events or results "may," "could," "might" or "will

be taken," "occur," "be achieved" or "have the potential to." All statements, other than statements of historical

fact, are considered to be forward-looking statements. Forward-looking statements involve known and unknown

risks, uncertainties and other factors which may cause the actual results, performance or achievements of the

Company to be materially different from any future results, performance or achievements express or implied by

the forward-looking statements. Factors that could cause actual results to differ materially from any forward -

looking statements include, but are not limited to, capital and other costs varying significantly from estimates;

fluctuations in commodity prices; failure to establish estimated resources; the grade and recovery of mineral

resources which are mined varying from estimates; production rates, methods and amounts varying from

estimates; delays in obtaining or failures to obtain required governmental, environmental or other project

approvals; changes in regulatory and legislative requirements; in flation; changes in exchan ge rates; delays in

development and other factors described in the public filings made by the Company at www.sedarplus.ca and

www.sec.gov. Readers should not place undue reliance on forward -looking statements. The forward -looking

statements contained herein are based on the beliefs, expectations and opinions of management as o f the date

hereof and Ur-Energy disclaims any intent or obligation to update them or revise them to reflect any change in

circumstances or in management’s beliefs, expectations or opinions that occur in the future.

- 5 -