TOREX GOLD REPORTS SUCCESSFUL BREAKTHROUGH OF GUAJES TUNNEL THREE MONTHS AHEAD OF SCHEDULE Guajes Tunnel is the key conduit integrating the Media Luna Mine with the ELG Complex

Corporate Updates

For Immediate Release

TOREX GOLD REPORTS SUCCESSFUL BREAKTHROUGH OF GUAJES

TUNNEL THREE MONTHS AHEAD OF SCHEDULE

Guajes Tunnel is the key conduit integrating the Media Luna Mine with the ELG Complex

TORONTO, Ontario, December 22, 2023 – Torex Gold Resources Inc. (the “Company” or “Torex”) (TSX: TXG)

announces that the successful breakthrough of the Guajes Tunnel was completed last night. Breakthrough of

the Guajes Tunnel represents a key de- risking milestone in the development of the Media Luna Project as the

tunnel unifies the Morelos Complex by connecting the existing operations on the north side of the Balsas River

with the growing resource base of the Media Luna Cluster on the south side.

Jody Kuzenko, President and CEO of Torex, stated:

“Breakthrough of the Guajes Tunnel is a critical milestone in the development of the Media Luna Project, which

remains on track for first concentrate production in late 2024. The Guajes Tunnel will be the primary conduit for

transporting ore and waste from the Media Luna deposit on the south side of the Balsas River to the processing

plant on the north side and will materially improve efficiencies associated with the movement of employees,

contractors, equipment, services, and supplies between both locations.

“Breakthrough of the Guajes Tunnel was achieved three months earlier than scheduled in the March 2022

Technical Report, primarily driven by the world-class advance rates achieved by our team. Rates north to south

have averaged 7.1 metres per day since the start of the year , including a record average advance rate of 8.0

metres per day in November. The advance rates are truly impressive considering the dimensions of the tunnel

are 6.5 metres high by 6.0 metres wide and that secondary development and installation of services have kept

pace with overall tunnel progress.

“We expect to commence anchor bolting for the seven- kilometre overhead conveyor in early 2024, which will

pave the way for the installation and then commissioning of the conveyor in August 2024 well ahead of

completing the necessary upgrades to the processing plant.

“I would like to personally thank all employees, contractors and suppliers involved in driving the Guajes Tunnel

for achieving this significant milestone safely and ahead of schedule.”

ABOUT TOREX GOLD RESOURCES INC.

Torex is an intermediate gold producer based in Canada, engaged in the exploration, development and

operation of its 100% owned Morelos Property, an area of 29,000 hectares in the highly prospective Guerrero

Gold Belt located 180 kilometres southwest of Mexico City. The Company’s principal asset is the Morelos

Complex, which includes the El Limón Guajes (“ELG”) Mine Complex, the Media Luna Project, a processing

plant, and related infrastructure. Commercial production from the Morelos Complex commenced on April 1,

2016 and an updated Technical Report for the Morelos Complex was released in March 2022. Torex’s key

strategic objectives are to optimize and extend production from the ELG Mine Complex, de- risk and advance

Media Luna to commercial production, build on ESG excellence, and to grow through ongoing exploration

across the entire Morelos Property.

Page 2

Torex Gold Resources Inc.

FOR FURTHER INFORMATION, PLEASE CONTACT:

TOREX GOLD RESOURCES INC.

Jody Kuzenko Dan Rollins

President and CEO Senior Vice President, Corporate Development & Investor Relations

Direct: (647) 725-9982 Direct: (647) 260-1503

[email protected] [email protected]

CAUTIONARY NOTES ON FORWARD LOOKING STATEMENTS

This press release contains "forward- looking statements" and "forward- looking information" within the meaning of applicable Canadian

securities legislation. Forward-looking information also includes, but is not limited to, the Media Luna Project which remains on track for first

concentrate production in late 2024; the Guajes Tunnel will be the primary conduit for transporting ore and waste from the Media Luna

deposit on the south side of the Balsas River to the processing plant on the north side, and will m aterially improve efficiencies associated

with the movement of employees, contractors, equipment, services , and supplies between both locations ; the Company expects to

commence anchor bolting for the seven- kilometre overhead conveyor in early 2024 which will pave the way for the installation and then

commissioning of the conveyor in August 2024, well ahead of completing the necessary upgrades to the processing plant; and Torex’s key

strategic objectives to extend and optimize production from the ELG Min e Complex, de-risk and advance Media Luna to commercial

production, build on ESG excellence, and to grow through ongoing exploration across the entire Morelos Property . Generally, forward-

looking information and statements can be identified by the use of forward-looking terminology such as “expects,” “strategic”, “on track” or

variations of such words and phrases or statements that certain actions, events or results “will,” “may,” “could,” or “would” occur. Forward-

looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity,

performance or achievements of the Company to be materially different from those expressed or implied by such forward- looking

information, including, without limitation, risks and uncertainties regarding the Company’s ability to satisfy the conditions in the MIA Integral

and the risks and uncertainties identified in the technical report (the “Technical Report”) released on March 31, 2022, entitled “NI 43- 101

Technical Report ELG Mine Complex Life of Mine Plan and Media Luna Feasibility Study”, which has an effective date of March 16, 2022,

and the Compan y’s annual information form and management’s discussion and analysis or other unknown but potentially significant

impacts. Forward-looking information and statements are based on the assumptions discussed in the Technical Report and such other

reasonable assumptions, estimates, analysis and opinions of management made in light of its experience and perception of trends, current

conditions and expected developments, and other factors that management believes are relevant and reasonable in the circumstances at

the date such statements are made. Although the Company has attempted to identify important factors that could cause actual r esults to

differ materially from those contained in the forward- looking information, there may be other factors that cause result s not to be as

anticipated. There can be no assurance that such information will prove to be accurate, as actual results and future events c ould differ

materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information.

The Company does not undertake to update any forward- looking information, whether as a result of new information or future events or

otherwise, except as may be required by applicable securities laws.