Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

TXG.TO ·

Torex Gold Provides Q3 2024 Update on Media Luna Project and Increases 2024 Production Guidance Project 87% complete; plant tie-in schedule moves to February; first copper concentrate expected in Q1

Production Results Mine Development & Operations

Torex Gold Provides Q3 2024 Update on Media

Luna Project and Increases 2024 Production

Guidance

Project 87% complete; plant tie-in schedule moves to

February; first copper concentrate expected in Q1

(All amounts expressed in U.S. dollars unless otherwise stated)

Toronto, Ontario--(Newsfile Corp. - October 30, 2024) - Torex Gold Resources Inc. (the "Company" or

"Torex") (TSX: TXG) provides a Q3 2024 update on the development of its Media Luna Project ("Media

Luna") and increases 2024 production guidance with a decision to undertake the tie-ins and upgrades to

the processing plant in February 2025. Unless otherwise stated, progress and milestones referenced in

this press release are as of September 30, 2024.

Jody Kuzenko, President & CEO of Torex, stated:

"Development and construction of Media Luna now stands at 87% complete and continues to progress

well - with engineering concluded, procurement down to final deliveries, underground development

ahead of schedule, and underground and surface construction advancing. Notably, installation of the

Guajes conveyor is almost complete, with commissioning expected imminently.

"With the overall project construction period nearing completion, our focus has shifted to refining the plan

and schedule for the plant tie-in period. As a result of modestly longer delivery windows for critical

electrical equipment (primarily switchgear) due in part to recent hurricane activity in the Gulf region, we

have rescheduled the start of the plant tie-in period from November 2024 to February 2025, with first

copper concentrate production expected in Q1 and commercial production shortly thereafter. With the

additional production associated with the pushback in the open pit, a clear contingency plan has long

been established for the possibility of a Q1 2025 tie-in period. The overriding business priority has

always been centered around readiness to execute the tie-in period and containing this period to no

longer than four weeks.

"The refined schedule comes with several benefits - most notably increased gold production in 2024 with

another four weeks of production. Importantly, the project team will have the opportunity to conduct

advance testing on key processing plant systems, thereby potentially reducing the time required to

complete the tie-ins and upgrades to less than four weeks as originally scheduled. Ore production from

the ELG Open Pits, ELG Underground, and Media Luna Underground will continue uninterrupted, with

ore from Media Luna stockpiled ahead of commissioning the flotation circuits.

"As at quarter end, $840 million of project period expenditures had been incurred on Media Luna

(including $114 million during Q3) with just over $110 million of expenditures remaining. The remaining

spend compares favourably to available liquidity of more than $345 million at quarter end, implying a

funding buffer of $235 million. The step-change improvement in the Company's funding buffer quarter-

over-quarter reflects the robust cash generation of the underlying business and places the Company in a

solid position to conclude Media Luna with only a modest level of debt."

INCREASED 2024 PRODUCTION GUIDANCE

With the tie-in period for the processing plant now scheduled to begin in February 2025, gold production

in 2024 is forecast to be 450,000 to 470,000 ounces versus original guidance of 400,000 to 450,000

ounces, given the benefit of an additional four weeks of production than was assumed within initial

guidance.

Table 1: Updated operational guidance for 2024

Initial 2024 Guidance

Updated 2024

Guidance

Production

Gold

oz

400,000 to 450,000

450,000 to 470,000

Gold equivalent

oz AuEq

410,000 to 460,000

460,000 to 480,000

Per the contingency plan established, the processing plant will continue to process ore from ELG Open

Pit and ELG Underground operations through to the tie-in period for the processing plant in February,

while the ramp-up of Media Luna Underground will continue unabated with ore stockpiled ahead of

commissioning the new copper ("Cu") and iron sulphide ("FeS") flotation circuits.

Total cash costs ($860 to $910 per ounce gold sold) and all-in sustaining costs ($1,100 to $1,160 per

ounce gold sold) guidance for 2024 remains unchanged and is still expected to be near the upper end of

the respective ranges, with the key pressure being the impact of the higher gold price on royalties and

profit sharing.

On a gold equivalent basis, full year production is now estimated at 460,000 to 480,000 ounces from

original guidance of 410,000 to 460,000 ounces. Gold equivalent total cash costs and all-in sustaining

costs guidance is unchanged.

CAPITAL EXPENDITURES

During Q3 2024, $114 million was spent on Media Luna, bringing the year-to-date total to $349 million.

The Company still expects full-year project spending to be within the guidance range of $430 to $450

million. Expenditures in Q4 2024 are expected to be lower than Q3 2024 and decline further in 2025 as

the project winds down, first copper concentrate production occurs in Q1, and commercial production is

declared shortly thereafter.

Table 2: Media Luna Project - Project Expenditures (April 1, 2022 through September 30, 2024)

Millions of U.S. dollars

Project To Date

Q3 2024

Project expenditures per 2022 Technical Report

$848.4

Adjustment for Q1 2022 underspend

$26.1

Total budgeted spend post March 31, 2022

$874.5

Final adjustments for stronger Mexican peso / out-of-scope items (June 30,

2024)

$75.5

Revised budgeted spend

$950.0

Expenditures incurred post March 31, 2022

($839.5)

Remaining spend

$110.5

Committed expenditures (inclusive of total project expenditures incurred to

date)

$950.0

Uncommitted expenditures

$0.0

Notes to Table

1)

Project period commenced on April 1, 2022; excludes capital expenditures incurred prior to Board approval on March 31, 2022.

2)

Project period is defined as April 1, 2022 through declaration of commercial production.

3)

Excludes borrowing costs capitalized.

The capital expenditure impact of the schedule adjustment is expected to be modest, with the project

team at site now looking at opportunities to offset the costs associated with the extended project period.

Of note, given the longer pre-commercial period with the rescheduled tie-ins, capital expenditures

related to accelerated underground development will be classified as non-sustaining for that period,

versus sustaining had the prior plant tie-in schedule been maintained.

PROJECT COMPLETION

As at quarter end, development of Media Luna was tracking largely to plan with the project 87%

complete, up from 78% at the start of the quarter. Detailed engineering is now complete, and

procurement is nearing completion at 97%. Underground development/construction and surface

construction are advancing, with completion levels at 77% and 70%, respectively.

Based on the current schedule related to critical electrical equipment delivery, the tie-in period for the

processing plant has been rescheduled to commence in February, with first copper concentrate

production in Q1. The updated schedule enables the project team to undertake advance testing on key

processing systems outside of the plant tie-in, with a view to potentially reducing the downtime period to

less than four weeks.

As previously guided, just in time deliveries of critical electrical equipment was anticipated to be a key

risk given little float in the schedule. After reviewing the risks around the tie-in period pushing into the

December holiday season, weighed against the existing contingency plan associated with the extension

of open pit production into Q2 2025 via the layback in the El Limón pit last year, the greater overall

benefit to the business mitigated in favour of rescheduling the processing plant tie-in schedule to

February 2025.

Table 3: Media Luna Project - Project Completion (April 1, 2022 through September 30, 2024)

Project To Date

Q3 2024

Procurement

97%

Engineering

100%

Underground development/construction

77%

Surface construction

70%

Total Project

87%

Notes to Table

1)

Physical progress measured starting as of April 1, 2022; excludes progress made prior to Board approval on March 31, 2022.

2)

Project period is defined as April 1, 2022 through declaration of commercial production.

3)

Total Project is weighted average based on activity levels.

It should be noted that the ramp-up of the Media Luna underground mine is separate from the completion

and commissioning of the processing plant. As such, the revised plant tie-in schedule will have no impact

on ore production from Media Luna, which will be stockpiled ahead of wet commissioning of the Cu and

FeS flotation circuits.

Engineering

Engineering over the quarter focused primarily on finalization of electrical deliverables and incorporation

of vendor information. Engineering work for the project is now complete and will continue to support in

the field as necessary to address any installation issues.

Procurement

Procurement for Media Luna is substantially complete, sitting at 97% as of the end of Q3 up from 89% at

the end of Q2. The level of procurement remaining represents final deliveries of equipment and materials

to site as purchase orders, contracts, and detailing are now more than 99% complete. Six of the eight

electrical houses ("e-houses") required for the project have now been delivered, with related switchgear

being the most critical delivery outstanding.

Notable orders completed during the quarter included electrical cable, network cabinets and LTE

infrastructure for the underground, flotation switchgear, water and slurry pumps, geotextiles for the

Guajes pit, fiber optic cable, and carbon steel pipe and fittings. Four battery electric loaders were also

delivered to site and have now been commissioned.

Underground Development and Construction

Steady progress was made underground at Media Luna during the quarter. Installation of the Guajes

conveyor is nearing completion and commissioning is expected imminently. The breakthrough between

Media Luna Upper and Media Luna Lower was achieved at the mine internal ramp, opening up access

to three additional mining blocks to support production. The feed chute and chute liner plates were

installed at ore pass #8 and tailings feed pipe installation continues to progress in anticipation of the

paste plant completion. Vibratory feeders and arch gates below both ore bins 1 and 2 at the 690 level

are also substantially complete and commissioning will take place in coordination with the Guajes

conveyor (Figure 1).

Following completion of definition drilling for the first seven stopes planned to be taken in the 2024 mine

plan, steady progress has been made on definition drilling of stopes in the 2025 mine plan. Drilling to

date has yielded positive results with tonnes and grade in line with expectations, aside from some minor

spatial variations as is typical with new underground areas. Underground development rates have been

strong, with monthly lateral development rates in excess of 1,300 metres over the last few months

(including over 1,400 metres in October) relative to the original budget of 1,200 metres per month. As a

result, underground development is now slightly ahead of plan.

The Company will continue with aggressive definition drilling and underground development programs in

2025 with the target of having all stopes to be mined in 2026 drilled off by the end of the year and the aim

of accelerating underground development. Both programs are expected to de-risk the ramp-up of

underground operations to the design rate of 7,500 tonnes per day.

Figure 1: Ore bins feed chutes have been assembled at the 690 level

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/228339_ore%20bin.jpg

Surface Construction

Significant progress was made on surface construction, now at 70% complete up from 56% at the start

of the quarter. On the north side of the Balsas River, the two e-houses required for the flotation circuit

were delivered and installed during the quarter, with electrical cables being run in preparation for the

switchgear delivery (Figure 2). Assembly of the FeS regrind mill is now complete, as is the installation of

the Cu rougher flotation cells and the thickeners. Steel was erected for the Cu concentrate storage and

blending building (8 of 8 bays completed). At the water treatment plant, detox tanks for the first phase of

water testing were installed (Figure 3) and commissioning activities are expected to start early in Q4.

Progress was also made on the installation of power infrastructure. At the 230 kV switchyard,

transmission towers have been erected and the grounding grid has been installed (Figure 4). Block work

was also completed on the electrical building while electrical trenches and duct banks were put in place.

At the 230 kV substation, the two primary transformers have been installed (Figure 5). The transmission

line between the switchyard and substation was hung during the quarter with connection to the substation

now complete and switchyard expected to be completed in Q4 2024.

On the south side of the Balsas River, construction of the paste plant is also progressing well with

installation of the thickener, binder silo, and building steel all having noticeably advanced (Figure 6). The

paste plant remains on track to be completed in Q1 2025, with commissioning sequenced to occur after

the processing plant infrastructure is commissioned.

Figure 2: Construction of the flotation area is advancing, with both e-houses and associated cables now

installed. Progress was also made on the installation of the regrind mill and cleaner cells.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_002full.jpg

Figure 3: Construction of the water treatment plant is ongoing, with detox tanks for the first phase of

water testing installed during the quarter

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_003full.jpg

Figure 4: Galvanized towers have been installed at the 230 kV switchyard to support the transmission

line between the yard and the substation

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_004full.jpg

Figure 5: The 230 kV substation is substantially complete with main transformers in place

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_005full.jpg

Figure 6: Construction of the binder silo, thickener, and building steel at the paste plant

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_006full.jpg

Operational Readiness

In parallel with development and construction activities, the surface and underground operational

readiness strategy continues to advance as planned. Operational readiness teams are accountable for

ensuring that processes and systems for all new work areas are established and ready in advance of the

handover from the project team to operations. This includes workforce transition planning and training,

developing the operating strategy (including all standard operating procedures) and maintenance plans

for all fixed and mobile equipment, blend and feed strategies, commissioning plans, first fills,

concentrate shipment logistics, and all other requirements for a smooth ramp up.

Recruitment of personnel for both the underground and new process areas is well advanced. Of the new

Media Luna recruits, 55% transferred from previous ELG operations. The transition training program

from open pit to underground operations is now 40% complete and is expected to ramp up as

production from the ELG Open Pits winds down. On surface, training for water treatment plant operators

began, marking a significant milestone in upskilling the workforce for the upcoming transition. In addition,

the operational readiness team continues to develop and advance Standard Operating and

Maintenance procedures for the new assets and is tracking to plan at over 70% complete. Spare parts

cataloging has been completed with the main original equipment manufacturers (FLSmidth, Metso,

Siemens, Sandvik, TAKRAF, and Tramac), which identified approximately 2,300 items deemed

necessary to have in stock for ongoing operations. Additionally, the readiness audit for the BEV fleet has

been completed ensuring all processes required for safe operation of the fleet are in place.

Negotiations with the various haulage companies for Cu concentrate transport to port distribution

facilities are complete and contracts are being finalized. The Company is also in the final stages of

settling contracts for the sale of Cu concentrate to a mix of traders and smelters. Metal payables are in

line with that which was incorporated into the most recent Technical Report dated effective March 16,

2022, and filed on March 31, 2022 ("Technical Report").

PROJECT EXECUTION PLAN

Based on the updated schedule for the tie-in and upgrades of the processing plant as well as other

deliverables, the project execution plan for Media Luna has been updated accordingly (Figure 7).

Figure 7: Project execution plan for the Media Luna Project

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_007full.jpg

More detail on the Media Luna Project, including the Feasibility Study results, can be found in the

Technical Report.

ABOUT TOREX GOLD RESOURCES INC.

Torex is an intermediate gold producer based in Canada, engaged in the exploration, development, and

operation of its 100% owned Morelos Property, an area of 29,000 hectares in the highly prospective

Guerrero Gold Belt located 180 kilometres southwest of Mexico City. The Company's principal asset is

the Morelos Complex, which includes the El Limón Guajes ("ELG") Mine Complex, the Media Luna

Project, a processing plant, and related infrastructure. Commercial production from the Morelos

Complex commenced on April 1, 2016 and an updated Technical Report for the Morelos Complex was

released in March 2022. Torex's key strategic objectives are: integrate and optimize the Morelos