Torex Gold Declares Commercial Production at Media Luna Milestone marks the Company's official transition to become both a gold and copper producer

Production Results Mine Development & Operations

Torex Gold Declares Commercial Production

at Media Luna

Milestone marks the Company's official transition to become

both a gold and copper producer

(All amounts expressed in U.S. dollars unless otherwise stated)

Toronto, Ontario--(Newsfile Corp. - May 1, 2025) -

Torex Gold Resources Inc. (the "Company" or

"Torex") (TSX: TXG) is pleased to announce it has achieved commercial production at the Media Luna

mine, concluding the development phase of the Media Luna Project. Amongst other criteria, commercial

production is declared when construction is substantially complete, mine and mill throughput have

averaged over 40% and 60% of design rates for 30 days, respectively, product is saleable, and

metallurgical recoveries have averaged at least 60% of the design recovery levels. Unless otherwise

stated, progress and milestones referenced in this press release are as of March 31, 2025.

Jody Kuzenko, President & CEO of Torex, stated:

"I'm proud to announce that we have accomplished one of the last key milestones associated with the

Media Luna Project by achieving commercial production. The delivery of Media Luna and our transition

to become both a gold and copper producer, substantially within budget and schedule, demonstrates

Torex as not only a consistent and reliable operator, but also a company capable of achieving excellence

in the execution of major and complex projects.

"Notably, our strong operational performance through the build period, supported by a backdrop of

record gold prices, allowed us to accomplish what is largely unheard of in the industry - funding the

project almost entirely through the generation of cash from our existing operations at ELG. The modest

level of net debt accumulated through the build period will be repaid quickly as the Company pivots to

positive free cash flow generation in the middle of 2025.

"Following the safe, successful tie-in of the flotation circuits to the processing plant, the project team is

now focused on ramping up the underground mine to the design level of 7,500 tonnes per day ("tpd") by

mid-2026, six months ahead of the schedule set out in the Feasibility Study. With underground

development ahead of schedule and close to a year of stopes now drilled off, mining rates will steadily

increase upon successful completion and commissioning of the paste plant and paste distribution

system later this quarter.

"With the Media Luna Project now substantially complete and ramping up to full operations, this will be

our last quarterly project update to the market. I want to extend my sincere gratitude to our shareholders

for your continued trust in Torex to deliver on this massive project as we committed, and to our

employees and contractors at Morelos for their unwavering dedication to deliver excellence as we set

the foundation for continued growth in Mexico and beyond."

CAPITAL EXPENDITURES

As a result of rescheduling the processing plant tie-ins to February 2025 (originally November 2024),

expenditures on Media Luna continued to be classed as non-sustaining prior to the declaration of

commercial production on April 26, 2025. For accounting purposes, the transition to the production

phase will be reflected commencing May 1, 2025. During Q1 2025, $55.5 million was spent on Media

Luna. A modest level of non-sustaining capital expenditures will be incurred post the declaration of

commercial production, primarily related to completion and commissioning of the paste plant and paste

distribution system.

PROJECT COMPLETION

As of the end of Q1 2025, overall construction of Media Luna was 98% complete, up from 94% at the

start of the quarter. Underground development/construction sat at 98% complete with the largest

outstanding component being the finalization of the tailings and paste distribution lines within the mine.

Surface construction was 96% complete at the end of the quarter, with commissioning of the paste plant

on track for completion in Q2. First concentrate was produced on March 24

th

and commercial production

has now been achieved.

Table 1: Media Luna Project - Project Completion (April 1, 2022 through March 31, 2025)

Project To Date

Q1 2025

Procurement

100%

Engineering

100%

Underground development/construction

98%

Surface construction (including paste plant)

96%

Total Project

98%

Notes to Table

1)

Physical progress measured starting as of April 1, 2022; excludes progress made prior to Board

approval on March 31, 2022.

2)

Project period is defined as April 1, 2022 through declaration of commercial production.

3)

Total Project is weighted average based on activity levels.

Underground Development and Construction

Underground development and construction are essentially complete, sitting at 98% at the end of the

quarter. Importantly, the Guajes Tunnel conveyor was commissioned during the quarter and has been

steadily transporting ore to the processing plant on the north side of the Balsas River (Figure 1).

Significant progress continues to be made on definition drilling, with 51 of the 60 stopes planned to be

mined in the 2025 mine plan drilled off, 40 from 2026, and 14 from 2027. Development rates remain

above budget with 1,304 metres completed in March compared to a budget of 1,200 metres per month.

With paste plant commissioning scheduled to be completed in the second quarter, mining rates are

expected to steadily increase through the year and remain on track to achieve the designed rate of

7,500 tpd by mid-2026.

Other notable areas that were completed in the quarter included the electrical connection and

commissioning of rock breaker #4 and development of waste pass #2. Key areas that remain

outstanding include the installation of the underground paste distribution piping and the remaining

underground material handling systems, that will support both Media Luna and EPO.

Figure 1: Commissioning of the Guajes Tunnel conveyor was completed during the quarter. Ore is being

transported through the tunnel out of the Guajes Portal for processing on the north side of the Balsas

River.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/250452_179374079473cbc7_001full.jpg

Surface Construction

At the end of March, surface construction sat at 96% complete, up from 85% at the start of the quarter.

Through close coordination between the project and operation teams, the tie-in of the copper and iron

sulphide flotation circuits at the processing plant were completed safely and on time. In total, 83 tie-ins

were completed and 136 separate systems commissioned. The completion of the tie-in period marked

the handover of the new processing facilities to the operations team, resulting in first concentrate

production delivered to the on-site storage facility on March 24

th

(Figure 2) and concentrate shipments

from site to the port commencing the first week of April.

The largest components of surface construction that remain outstanding are commissioning of the paste

plant and connection of the updated power infrastructure to the national grid. Paste plant construction

and commissioning are progressing well. The paste plant filter presses were assembled during the

quarter and water testing commenced on the paste plant thickener (Figures 3 and 4). Pipe and

instrumentation installation remains a key area for completion ahead of commissioning which is on track

to commence over the next several weeks.

Installation of power infrastructure is complete and the energy regulator, Comisión Federal de

Electricidad ("CFE"), is on site to complete their final checks and commissioning process before the

230 kV transmission line can be tied into the national grid. The tie-in is expected to be completed over

the coming weeks, aligned with commissioning of the paste plant.

Other notable surface construction achievements during the quarter included preparation of the base of

the Guajes Pit for in-situ tailings disposal, testing of tailings pumping systems to the Guajes thickener,

and commissioning of the underground control room for remote operation of the new rock breakers,

Guajes conveyor and associated infrastructure.

Figure 2: First concentrate production marked a significant milestone in the completion of the Media

Luna Project.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/250452_179374079473cbc7_002full.jpg

Figure 3: Paste plant filter installation.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/250452_179374079473cbc7_003full.jpg

Figure 4: Paste plant thickener ready for water testing.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/1863/250452_179374079473cbc7_004full.jpg

Operational Readiness

In parallel with development and construction activities, the surface and underground operational

readiness plan is nearing completion. Commissioning and operational readiness activities for the

underground infrastructure, water treatment plant, and flotation circuits were delivered and as the paste

plant nears mechanical completion, commissioning and operational readiness deliverables have been

finalized to support startup. The operational readiness team continues to develop and advance Standard

Operating and Maintenance procedures for the remaining new assets and is tracking to plan at over

91% complete.

The Human Resources, Safety, and Operational teams coordinated the recruitment and training of the

final group of employees required to operate the Media Luna mine and the modified process plant. From

January 2024 to the end of March 2025, approximately 200 employees were transferred from the ELG

Open Pits to the underground mine and more than 160 employees were recruited. The teams also

coordinated the redeployment, hiring, and training of just over 110 positions in the processing plant to

meet the new operating requirements, all with a key focus on local recruitment.

ABOUT TOREX GOLD RESOURCES INC.

Torex Gold Resources Inc. is an intermediate gold producer based in Canada, engaged in the

exploration, development, and operation of its 100% owned Morelos Property (the "Morelos Property"),

an area of 29,000 hectares in the highly prospective Guerrero Gold Belt located 180 kilometres

southwest of Mexico City.

The Company's principal asset is the Morelos Complex, which includes the producing Media Luna

Underground, ELG Underground, and ELG Open Pit mines, the development stage EPO Underground

Project, a processing plant, and related infrastructure. Commercial production from the Morelos

Complex commenced on April 1, 2016 and an updated Technical Report for the Morelos Complex was

released in March 2022.

Torex's key strategic objectives are: deliver Media Luna to full production and build EPO; optimize

Morelos production and costs; grow reserves and resources; disciplined growth and capital allocation;

retain and attract best industry talent; and industry leader in responsible mining. In addition to realizing

the full potential of the Morelos Property, the Company is seeking opportunities to acquire assets that

enable diversification and deliver value to shareholders.

FOR FURTHER INFORMATION, PLEASE CONTACT:

TOREX GOLD RESOURCES INC.

Jody Kuzenko

President and CEO

Direct: (647) 725-9982

[email protected]

Dan Rollins

Senior Vice President, Corporate Development & Investor Relations

Direct: (647) 260-1503

[email protected]

QUALIFIED PERSON

The technical and scientific information in this press release has been reviewed and approved by Dave

Stefanuto, P. Eng, Executive Vice President, Technical Services and Capital Projects of the Company,

and a qualified person under National Instrument 43-101.

CAUTIONARY NOTES ON FORWARD-LOOKING STATEMENTS

This press release contains "forward-looking statements" and "forward-looking information" within the

meaning of applicable Canadian securities legislation. Forward-looking information includes, but is not

limited to, statements that: the modest level of net debt accumulated through the build period will be

repaid quickly as the Company pivots to positive free cash flow generation in the middle of 2025; with

underground development ahead of schedule and close to a year of stopes now drilled off, mining rates

will steadily increase upon successful completion and commissioning of the paste plant and paste

distribution system later this quarter; a modest level of non-sustaining capital expenditures will be

incurred post the declaration of commercial production; with paste plant commissioning expected to be

completed in the second quarter, mining rates are expected to steadily increase through the year and

remain on track to achieve the designed rate of 7,500 tpd by mid-2026 and key strategic objectives are:

deliver Media Luna to full production and build EPO; optimize Morelos production and costs; grow

reserves and resources; disciplined growth and capital allocation; retain and attract best industry talent;

and industry leader in responsible mining. Generally, forward-looking information can be identified by the

use of forward-looking terminology such as "expect", "plan", "strategy", "schedule", "guide", "continue",

"future" or variations of such words and phrases or statements that certain actions, events or results "will"

occur or are "on track" to occur. Forward-looking information is subject to known and unknown risks,

uncertainties and other factors that may cause the actual results, level of activity, performance or

achievements of the Company to be materially different from those expressed or implied by such

forward-looking information, including, without limitation, risks and uncertainties identified in the technical

report ("Technical Report") titled ELG Mine Complex Life of Mine Plan and Media Luna Feasibility

Study, with an effective date of March 16, 2022, and a filing date of March 31, 2022 and in the

Company's annual information form ("AIF") and management's discussion and analysis ("MD&A") or

other unknown but potentially significant impacts. Forward-looking information is based on the

reasonable assumptions, estimates, analyses and opinions of management made in light of its

experience and perception of trends, current conditions and expected developments as set out in the

Technical Report, AIF and MD&A, and other factors that management believes are relevant and

reasonable in the circumstances at the date such statements are made. Although the Company has

attempted to identify important factors that could cause actual results to differ materially from those

contained in the forward-looking information, there may be other factors that cause results not to be as

anticipated. There can be no assurance that such information will prove to be accurate, as actual results

and future events could differ materially from those anticipated in such information. Accordingly, readers

should not place undue reliance on forward-looking information. The Company does not undertake to

update any forward-looking information, whether as a result of new information or future events or

otherwise, except as may be required by applicable securities laws. The Technical Report, AIF and

MD&A are filed on SEDAR+ at

www.sedarplus.ca

and available on the Company's website at

www.torexgold.com

.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/250452