TVIRD Group Reports Steady Q1 and Q2 2026 Production

Production Results

TVIRD Group Reports Steady Q1 and Q2 2026

Production

TSX-V: TVI

TVI Pacific Investee TVIRD Reports First Half 2026 Production of 37,528 Ounces of Gold and

221,952 Ounces of Silver

CALGARY, AB and MAKATI CITY, Philippines

,

July 9, 2026

/CNW/ - TVI Pacific Inc. ("

TVI

" or the

"

Company

") is pleased to provide an operational update from

TVI Resource Development

(Philippines), Inc. ("TVIRD")

, in which the Company holds a

30.66% interest

, covering operating

and development activities for the six months ended June 30, 2026.

During the first half of 2026, TVIRD's

Balabag Gold-Silver Project

and

Siana Gold Project

produced and shipped a combined

37,528 ounces of gold

and

221,952 ounces of silver

in doré

form. In addition to steady production, TVIRD continued advancing exploration, infrastructure

upgrades and development initiatives designed to extend mine life, improve operating efficiency and

support future growth across its Philippine portfolio.

First Half 2026 Highlights

Combined production of

37,528 ounces of gold

and

221,952 ounces of silver

.

Balabag

completed

15 doré shipments

, producing

17,781 ounces of gold

and

209,550

ounces of silver

.

Siana

completed

13 doré shipments

, producing

19,747 ounces of gold

and

12,402 ounces

of silver

.

Phase 13 drilling at the Lalab prospect was completed, totaling approximately

10,000 metres

,

while Phase 14A drilling is nearing completion.

Construction of Greenstone's second crushing circuit is approximately

90% complete

and

scheduled for commissioning during the third quarter.

Greenstone also continued permitting for the raising of TSF6, increasing long-term tailings

capacity, while geotechnical investigations commenced for the design of TSF7.

Greenstone continued development of its solar power facility, which is designed to be

expandable to

9.9 MWp

.

Exploration and permitting activities progressed at the Mapawa Project.

Pre-development planning advanced at the Mabilo Copper-Gold Project.

Balabag Gold-Silver Project

Balabag continued to deliver consistent operating performance during the first six months of 2026.

Between January 1 and June 30, 2026, Balabag completed

15 doré shipments

, producing

17,781

ounces of gold

and

209,550 ounces of silver

. Since commercial production commenced in July

2021, the mine has completed

190 shipments

, producing

172,512 ounces of gold

and

3,233,874

ounces of silver

.

Exploration activities also continued at the nearby Lalab prospect, which is being evaluated as a

potential source of additional mill feed to support future mine-life extension. The Phase 13 drilling

program has been completed, while Phase 14A drilling is nearing completion with only a limited

number of holes remaining. Geological interpretation and planning for the next exploration phase are

currently underway.

Siana Gold Project

The Siana Gold Project continued its operational ramp-up during soft commissioning. During the first

half of 2026, Siana completed

13 doré shipments

, producing

19,747 ounces of gold

and

12,402

ounces of silver

. Since commencement of soft commissioning, the operation has completed

85

shipments

, producing

89,130 ounces of gold

and

94,644 ounces of silver

.

Operational improvements continued during the period. Construction of the second crushing circuit

reached approximately

90% completion

, while upgrades to the gravity circuit and oxygen generation

system are expected to be completed during the third quarter.

Greenstone also continued permitting and expansion activities for Tailings Storage Facility No. 6

(TSF6) to support future operating capacity and increase long-term tailings storage, while advancing

planning for TSF7 through geotechnical investigations and design work. Development of the site's

solar power facility continued and is expected to provide up to

9.9 MWp

of installed generating

capacity upon full expansion.

Following completion of rehabilitation activities relating to the 2024 tailings storage facility incident,

regulatory matters associated with the event have now been resolved. The rehabilitated area has

been restored, and community relocation commitments have been completed.

Exploration and Development Projects

Mapawa Project

Exploration activities continued at the Mapawa Project during the reporting period, including UAV

magnetic geophysical surveys, geological mapping, soil sampling and diamond drilling.

Twenty-seven drill holes totaling approximately

3,013 metres

were completed at the San Jose and

Sto. Niño prospects. Preliminary work at San Jose has outlined an initial inferred mineral resource

that management intends to further evaluate and upgrade through additional drilling.

Greenstone also continued permitting activities, including submission of the project's Declaration of

Mine Project Feasibility application to the Mines and Geosciences Bureau and completion of field

investigations by the National Commission on Indigenous Peoples.

Mapawa continues to be evaluated as a potential future source of mill feed for the Siana processing

plant.

Mabilo Project

TVIRD continued advancing preparations for development of the Mabilo Copper-Gold Project.

Activities included planning for site facilities, camp construction and other pre-development works.

Major permits are already in place, with the remaining approvals progressing according to schedule.

Pan de Azucar Project

Work also continued at the Pan de Azucar Project, where TVIRD is evaluating potential processing

options while completing regulatory requirements for renewal of the Mineral Production Sharing

Agreement. Environmental monitoring and community engagement activities remain ongoing.

About TVI Resource Development (Philippines), Inc.

TVI Resource Development (Philippines), Inc. ("TVIRD") is a Philippine resource company in which

TVI Pacific Inc. holds a 30.66% interest. TVIRD is engaged in the exploration, development and

production of precious and base metals in the Philippines through its producing operations and

development-stage projects, including Balabag, Siana, Mabilo, Pan de Azucar and other exploration

properties.

Website:

www.tvipacific.com

Forward-Looking Information

This news release contains certain forward-looking information within the meaning of applicable

Canadian securities legislation. Forward-looking statements include, but are not limited to,

statements regarding exploration activities, mineral resource potential, mine-life extension,

development plans, construction schedules, permitting activities, infrastructure projects and future

operating performance. Forward-looking statements are based on management's current

expectations and assumptions and involve known and unknown risks, uncertainties and other factors

that may cause actual results to differ materially from those expressed or implied by such

statements. Readers are cautioned not to place undue reliance on forward-looking statements. The

Company undertakes no obligation to update forward-looking statements except as required by

applicable securities laws.

SOURCE TVI Pacific Inc.

View original content:

http://www.newswire.ca/en/releases/archive/July2026/09/c1891.html

%SEDAR: 00001837E