Mining and Projects Update at TVI Pacific's 30.66% owned TVIRD

Corporate Updates

Mining and Projects Update at TVI Pacific's

30.66% owned TVIRD

CALGARY, AB

,

Nov. 7, 2022

/CNW/ - TVI Pacific Inc. (TSXV: TVI) (OTC-Pink: TVIPF) ("

TVI

" or

"

the Company

") is pleased to provide an update with respect to the various mines and projects held

and operated by TVI Resource Development Phils., Inc. ("

TVIRD

"), a

Philippines

corporation in

which TVI holds a 30.66% interest.

HIGHLIGHTS

:

Balabag Gold Mine

Since start-up, twenty-nine doré shipments have been completed containing 35,486 ounces of

gold (

"Au"

) and 923,981 ounces of silver (

"Ag"

) for 46,154 gold equivalent ounces.

In the current year, twenty-one doré shipments containing 27,752 ounces of Au and 697,201

ounces of Ag for 35,489 gold equivalent ounces have been completed.

Plant throughput continues to improve to an average of 2,191 tonnes per day (

"tpd"

) for

October 2022

.

Resource drilling continues with planned Phase 7 adding an approximate 4,000 meters

commencing 2023.

Bank loan repayments total

US$13.3 million

to date of the

US$28.5 million

, 5-year term loan

with China Banking Corporation (

"Facility"

).

Siana Gold Mine

Rehabilitation of the crushing and processing plant is proceeding along with mine development

and construction of tailings storage facility #6 (

"TSF6"

).

Agata Mining Ventures

Project-to-date, 371 shipments of 20.20 million wet metric tonnes of nickel laterite have been

shipped through to

October 31, 2022

.

Final shipments are planned in late

November 2022

and will thereafter cease operations.

"TVIRD continues to make good progress at both Balabag and Siana. The continuing focus at

Balabag to optimize operations is proving successful and we are confident that more improvements

will be introduced to further increase the amount of gold equivalent ounces produced and the

frequency of shipments", said Mr.

Cliff James

, Chairman and CEO of TVI and Chairman of TVIRD,

"Combined with the progress being made at the Siana Gold Mine with the rehabilitation of some key

areas of the processing plant already complete, we continue to be very excited about the future of

TVIRD and the potential value this may also bring to TVI Pacific."

TVIRD Mining Update

:

Balabag Gold Mine

TVIRD owns 100% of the Balabag Gold Mine (

"Balabag"

) which covers a 4,779-hectare Mineral

Production Sharing Agreement ("

MPSA

", MPSA No. 086-97-IX with expiry date

November 20, 2047

)

located within the Municipality of Bayog, Province of Zamboanga del Sur and Municipalities of

Diplahan and Kabasalan, Province of Zamboanga Sibugay, Mindanao, Philippines.

TVI announced on

November 22, 2019

that TVIRD had determined to advance Balabag towards

commercial production and continuous milling operations commenced in July, 2021 with the first

shipment of gold doré completed on

September 30

, 2021. Commercial production was achieved at

Balabag effective

November 1

, 2021. As at the date of this news release, Balabag has completed

29 shipments since start-up of production and 21 shipments in the current year, as indicated

below:

Since Start-up of Production:

July 2021 to Oct.31.2022

Current Year:

Jan.31.2022 to Oct.31.2022

Number of Shipments

29

21

Gold doré

(kg)

30,464

23,020

Gold

(oz)

35,486

27,752

Silver

(oz)

923,981

697,201

Gold Equivalent

(oz)

46,154

35,489

A focus to optimize the operation has continued and has thus far resulted in a significant increase in

mill throughput and plant availability, as reflected in the following table:

December 2021

Year-to-date 2021

(average)

October 2022

10 months ended

October 31, 2022

(average)

Gold

Silver

Gold

Silver

Gold

Silver

Gold

Silver

Head Grade

2.25 g/t

93.40 g/t

1.91 g/t

69.58 g/t

2.21 g/t

61.69 g/t

1.94 g/t

68.46 g/t

Recoveries

90 %

70 %

88 %

69 %

88 %

67 %

86 %

61 %

Mill throughput

1,100 tonnes per day

1,151 tonnes per day

2,191 tonnes per day

1,751 tonnes per day

Plant

Availability

70 %

76 %

92 %

86 %

Optimization works to improve plant efficiency have included:

The fabrication, installation and commissioning of a column flotation cell to upgrade the quality of

feed to the Merrill Crowe to result in improved metal recoveries.

The introduction of a lead acetate dosing regime to improve the dissolution of both gold and

silver. An oxygen generator is expected to also be installed to further increase the efficiency of

the cyanidation process.

Improvements in the powerhouse ventilation and insulation to prevent damage to the electronics

and alternator windings of the gensets from moist air flowing through from the smelting room

and assay laboratory.

The testing of polyurethane screens to further increase the capacity of the carbon-in leach

(

"CIL"

) circuit's carbon interstage screens.

The tailings storage facility (

"TSF"

) is being constructed in stages to accommodate both the

increased throughput and progressively increasing resources as they may be defined. Ongoing

placement of Zone 3 is proceeding together with construction of the Stage 3 spillway.

TVIRD is continuing also to finalize a Phase 7 exploration program that includes additional in-fill,

step-out and vein extension resource drilling and follow-up mapping of Balabag and its immediately

surrounding area. This program is expected to commence in 2023 and is currently estimated to

include 27 drillholes for a total meterage of 3,975 meters. The primary focus of this program will be

to more thoroughly explore and further define resources within an expanded ultimate pit and is to

include lateral and down dip continuity of the West Tinago vein system, the southeast extension of

South Tinago stockwork zones and the down dip continuity of the East Miswi and Lalab vein system.

Phase 5A, Phase

5B

and Phase 6 drilling results, which have included 11,094 meters drilled over

101 drillholes, have not yet been included in the most recent Mineral Resource estimate presented in

the NI 43-101 Technical Report entitled "NI 43-101 Exploration Results and Mineral Resource

Update Report on the Balabag Gold-Silver Project" and filed under the Company profile on SEDAR

on

July 20

, 2021. That Technical Report, dated

July 19, 2021

, has been based only on drill results

collected through to completion of the Phase 4 drilling program in December 2020.

TVIRD has thus far made seven (7) payments against the Facility, each in the amount of US

$2.2

million

and each including an approximate US

$0.2 million

of interest, bringing the total principal

repaid to date against the US

$28.5 million

Facility to US

$13.3 million

. The purpose of the Facility

has been to finance development activities at Balabag.

Siana Gold Mine:

TVIRD owns 100% of Siana through its 100%-owned subsidiary, Greenstone Resources

Corporation (

"GRC"

). The mine covers a 3,289-hectare MPSA (MPSA No. 184-2002-XIII) in

addition to 100% of the neighboring 1,482-hectare MPSA No. 280-2009-XIII for the Mapawa Project

and the Ferrer Claim (as covered by the Application for Mineral Production Sharing Agreement No.

A000046 and comprising of one Block of 595 hectares).

With all required permits in place for re-commencement of operations, rehabilitation of the

processing plant at Siana is proceeding and includes the restoration and repair of the plant

equipment. To date, rehabilitation works have been completed as they relate to the crushing plant

and the reagent circuit while work continues with the grinding circuit, the CIL and detoxification area,

the elution and electrowinning area, and the power plant. The crushing plant is now undergoing early

testing and commissioning using the ore stockpile and the filling of the CIL and detox tanks with

water has also already commenced in preparation for the tank hydrotesting and air compressor

pressure testing. Air and water supply commissioning is already ongoing.

Dewatering and waste stripping of the Siana pit are proceeding together with TSF6 road

construction, excavation and embankment placement works. Construction of TSF6 forms part of the

critical path to the restart of operations. The ore stockpile currently approximates 350 thousand

tonnes.

The TVIRD Exploration team has also commenced a review of past drilling data of GRC that

includes a total of 558 drillholes with an aggregate of 80,705.33 meters total meterage. Of the total

drillholes included in the drill database file, only 504 drillholes have complete log data in the database

which equates to 77,789.71 meters.

Agata Direct Shipping Nickel/Iron Mine:

Further to the Company's announcement of

May 18, 2022

, that the Agata direct shipping nickel/iron

mine is currently expected to cease operations in

October 2022

, TVIRD, the operator of Agata

Mining Ventures Inc. (

"AMVI"

), a joint venture company in which TVIRD holds a 60% interest, has

confirmed that the final shipments are to be completed through mid to late November 2022. TVIRD

is continuing to review several potential nickel laterite projects, near to AMVI, for possible acquisition

and the Assay Laboratory at site is being used for the purpose of analyzing samples gathered from

these properties but as at the current date the expectation is that AMVI will cease operations

following completion of its final shipments in

November 2022

.

Through to

October 31, 2022

, AMVI has completed a total project-to-date of 371 shipments of

20.20 million wet metric tonnes of nickel laterite. This has included 165 shipments of high iron ore,

202 shipments of saprolite, 1 shipment of low iron ore and 3 shipments of low saprolite. Completed

shipments exceed by more than two times the proven and probable reserves of 9.7 million wet

metric tonnes of nickel laterite ore with a grade of 48% Fe and 0.9% Ni that had been reported in

the National Instrument 43-101 compliant Feasibility Study entitled "Technical Report for the Agata

North Nickel Laterite DSO Project, Mindanao,

Philippines

" (

"Feasibility Study"

), dated

August 30

,

2013 and filed under the Company's SEDAR profile on

September 10

, 2013. The Feasibility Study

was prepared under the direction of

Dallas Cox

, an independent qualified person, with contributions

from

Mark Gifford

and

Michael Conan-Davies

; independent qualified persons as defined by National

Instrument 43-101 (

Canada

).

The term of the 4,995 hectare MPSA (MPSA No. 134-99-XIII) held by AMVI is valid through to

May

26

, 2049.

TVIRD's Mabilo Project:

On

January 31, 2022

, TVIRD obtained control of SageCapital through the acquisition of all of its

outstanding capital stock. This acquisition has further provided TVIRD an indirect 60% equity

interest in Mt. Labo Exploration and Development Corporation (

"MLEDC"

), as held by SageCapital.

MLEDC is a

Philippines

mining and minerals exploration development company and the owner and

operator of Mabilo.

Mabilo is located in Camarines Norte Province, Eastern Luzon,

Philippines

, one of the major

traditional gold mining centers in

the Philippines

and is covered by Philippines MPSA MLC-MRD V-

459 Amended (Renewal) and two (2) additional blocks with an existing Exploration Permit (EP-019-

202-V), covering 3,484.2 hectares and 165.9 hectares. With a near-surface deposit, Mabilo has

potential for direct shipping ore (

"DSO"

) and it is contemplated that mining will use an open-pit

mining method prior to moving to a primary concentrate production through construction of a plant.

Both the Declaration of Mining Project Feasibility for initial DSO operations and the Environmental

Compliance Certificate were approved in 2020. The Mabilo mineralized deposit is classified as a

copper-gold-iron skarn deposit that offers potential for multi-metal products, namely copper, gold

and silver, with by-products magnetite (Fe

3

O

4

) and pyrite (FeS

2

).

TVIRD is currently proceeding with various organizational, community-related, permitting and site

clean-up matters while considering next steps at Mabilo.

Agata Limestone Project:

The Agata Limestone project is also held by AMVI and is located in the same MPSA as the Agata

Direct Shipping Nickel/Iron Mine that has been extended to

May 26

, 2049. The Environmental

Compliance Certificate for the Agata Limestone project was received on

June 1, 2021

and is valid

through to

May 31

, 2026. Endorsements from the required local government have been received for

the project and the balance of the permitting process is continuing.

As at the current date there is no change in status of the Agata Limestone project and it continues to

be judged currently of lesser importance to TVIRD, given its size and potential value, when

compared relative to the growing number of important projects now held by TVIRD, including the

operating gold and silver mine at Balabag, the restart of the Siana gold mine and the development of

the Mabilo project.

As announced previously it is expected that, if the Agata Limestone project is to proceed, it will

benefit from the use of the same infrastructure that has been developed to operate the Agata

nickel/iron mine, including all administration buildings and offices, the laboratory, maintenance

facilities, site roads and the port.

Other Projects Update:

As reported earlier, TVIRD owns the rights to an additional 26 tenements that it has prioritized for

purposes of further exploration. These additional tenements are located primarily in the regions of

Zamboanga and Caraga in the Philippines.

Various activities planned in the current year for those tenements identified as a key priority have

commenced, including scout and definition drilling, ground verification of anomalies and grid soil

sampling, geological and tunnel mapping and sampling.

One area of key focus has been the Main Malusok prospect where reconnaissance mapping and

sampling is proceeding in the north-eastern side of the prospect. To date, forty-three (43)

abandoned tunnels have been identified in Main Malusok. Detailed underground mapping has also

being performed on the identified mine-workings at southeast Malusok Areas 3 & 4 where a further

sixty-two (62) tunnels have been located, fifteen (15) of which have been mapped in detail to date.

Qualified Persons

The Qualified Person responsible for the scientific and technical content of this press release is Mr.

Michael James Bue, Bsc.

Eng, M.Eng, P.Eng. Mr. Bue has acted as the Qualified Person in

compliance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("

NI 43-

101

") reporting requirements by virtue of his membership in the Professional Engineers of

Ontario

and Canadian Institute of Mining and Metallurgy and has confirmed compliance of this press release

with NI 43-101 requirements.

About TVI Resource Development Phils., Inc.

TVIRD, a Philippine corporation in which TVI holds a 30.66% interest, is a diversified mining

company that focuses on the acquisition, exploration, development and production of resource

projects in the Philippines. TVIRD owns 100% of the Balabag gold/silver mine, 100% of the Siana

gold mine and Mapawa project, a 60% indirect interest in the Mabilo project, and a 60% interest in

Agata Mining Ventures Inc. Balabag has shipped 46,154 gold equivalent ounces through 29

shipments to the date of this news release and AMVI has shipped a total of 20.20 million wet metric

tonnes of nickel laterite ore through 371 shipments through to

October 31

, 2022.

About TVI Pacific Inc.

TVI Pacific Inc. is a Canadian resource company focused on mining projects in

the Philippines

, one

of the most prolifically mineralized countries in the world. TVI currently holds a 30.66% equity

interest in TVIRD, a

Philippines

corporation. Through TVIRD, TVI has ownership in a currently

producing gold mine and a nickel/iron mine. Funded by these producing mines, two recent corporate

acquisitions by TVIRD have provided potential for many additional immediate opportunities. The first

of these opportunities expected to come onstream is the Siana gold mine at which equipment is

currently being rehabilitated with a plan to restart operations. TVI has a long history of being able to

successfully bring on mines in

the Philippines

at much lower than standard industry capital costs.

IMPORTANT INFORMATION REGARDING FORWARD-LOOKING STATEMENTS

Certain information set out in this News Release constitutes forward-looking information. Forward-

looking statements are often, but not always, identified by the use of words such as "seek",

"anticipate", "plan", "continue", "estimate", "expect", "may", "will", "intend", "could", "might",

"should", "believe", "scheduled", "to be", "will be" and similar expressions. Forward-looking

statements in this News Release are based upon the opinions and expectations of management of

the Company as at the effective date of such statements. Although the Company believes that the

expectations reflected in such forward-looking statements are based upon reasonable

assumptions, it can give no assurance that those expectations will prove to have been correct.

Forward-looking statements are subject to certain risks and uncertainties (known and unknown)

that could cause actual outcomes to differ materially from those anticipated or implied by such

forward-looking statements.

Forward-looking statements are based upon the opinions and expectations of management of the

Company as at the effective date of such statements and, in certain cases, information supplied by

third parties. Although the Company believes the expectations reflected in such forward-looking

statements are based upon reasonable assumptions and that information received from third

parties is reliable, it can give no assurance that those expectations will prove to have been

correct.

Forward-looking statements are subject to certain risks and uncertainties (known and

unknown) that could cause actual outcomes to differ materially from those anticipated or

implied and should not be read as guarantees of future performance or results.

These

factors include, but are not limited to, such things as: (i) general economic conditions in

Canada

,

the Philippines

and elsewhere; (ii) volatility of prices for precious metals, base metals, and other

commodities; (iii) commodity supply and demand; (iv) fluctuations in currency and interest rates;

(v) inherent risks associated with the exploration and development of mining properties, including

but not limited to geological characteristics, metallurgical characteristics of the mineralization, the

availability of equipment and facilities necessary to complete development and the ability to

develop adequate processing capacity; (vi) the cost of consumables and mining and processing

equipment; (vii) unforeseen technological and engineering problems; (viii) ultimate recoverability

of reserves; (ix) production, timing, results and costs of exploration and development activities; *

political factors, political stability or civil unrest, including but not limited to acts of sabotage or

terrorism; (xi) availability of financial resources or third-party financing; (xii) changes in laws or

regulations (domestic or foreign); (xiii) changes in administrative practices; (xiv) changes in

exploration plans or budgets; (xv) the availability of skilled labour; (xvi) the failure of parties to

contracts with the Company and TVIRD to perform as agreed, including its joint venture partners;

(xvii) the impact of the COVID-19 pandemic; and (xviii) extreme weather conditions and forces of

nature (i.e. typhoons, heavy rains, earthquakes, and the like) that may disrupt operations and

explorations.

Forward-looking statements regarding TVIRD's Balabag operations, ongoing construction of

additional stages of the Balabag TSF, the results of completed and possible future exploration

activities, and forward-looking statements regarding rehabilitation and construction works at Siana,

are based upon, but are not limited to, TVIRD's past exploration, operations, construction and

project development experience in the region and in such terrain, current and previous exploration

activities, discussions with third parties, the availability of financing and TVIRD's overall plans,

budget and strategy for Balabag and Siana (which are all subject to change).

The Company wishes to clarify that in making the decision to put Balabag into production, TVIRD,

a Philippine corporation that the Company does not control, relied exclusively on technical and

economic analysis prepared under Philippine regulations and did not rely on any feasibility study

classifying mineral reserves prepared in accordance with NI 43-101. Historically such projects

have a much higher risk of economic and technical failure.

The Company does not have control over TVIRD nor does it have any involvement in the

management or decisions of TVIRD or control over financial reporting and internal controls of

TVIRD. The Company relies on the internal controls and financial reporting controls of TVIRD and

their failure to maintain effectiveness or comply with applicable standards may adversely affect

TVI.

Accordingly, readers should not place undue reliance upon the forward-looking statements

contained in this material change report and such forward-looking statements should not be

interpreted or regarded as guarantees of future outcomes.

Various risks to which the Company is exposed in the conduct of its business (including mining

activities) are described in detail in the Company's Annual Information Form for the year ended

December 31, 2021

, which was filed on SEDAR on

April 28, 2022

and is available under the

Company's profile at

www.SEDAR.com

.

The forward-looking statements contained in this News Release are made as of the date hereof

and the Company does not undertake any obligation to update or to revise any of the included

forward-looking statements, except as required by applicable securities laws in force in Canada.

The forward-looking statements contained herein are expressly qualified by this cautionary

statement.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

SOURCE

TVI Pacific Inc.

View original content:

http://www.newswire.ca/en/releases/archive/November2022/07/c9787.html

%SEDAR: 00001837E

For further information:

Patrick Hanna, Chief Financial Officer, TVI Pacific Inc., Phone: 403-265-

4356, E-mail: [email protected]

CO: TVI Pacific Inc.

CNW 07:00e 07-NOV-22