Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

TSG.V ·

TRISTAR DISCOVERS SIGNIFICANT NEW GOLD REEFS AT CASTELO DE SONHOS (Scottsdale, AZ) Assay results from reverse circulation (RC) drilling at the Castelo de Sonhos (CDS) gold project of TriStar Gold Inc. (the “Company” or “TriStar”) continue to show significant intervals in new

Drill Results

August 1, 2017 Trading Symbol: TSG - TSX.V

TRISTAR DISCOVERS SIGNIFICANT NEW GOLD REEFS AT CASTELO DE SONHOS

(Scottsdale, AZ) Assay results from reverse circulation (RC) drilling at the Castelo de Sonhos (CDS) gold

project of TriStar Gold Inc. (the “Company” or “TriStar”) continue to show significant intervals in new

holes. “We’re glad that the new drilling is consistent with our exploration target concept ,” says Nick

Appleyard, TriStar’s President and CEO . “We’ve known since last year that we’ve got considerable

potential for growing the resources along the strike of the mineralized conglomerate. But the July results

from in-fill holes in the heart of Esperança South now demonstrate significant upside potential even in

areas where indicated resources were previously reported. Thick intervals running well above the deposit

average point to potential additional resources beyond the pit shell that constrained the 2014 resource.”

Drilling will continue through August into early Septemb er, reaching a planned 120 to 150 RC holes, at

which time a new min eral resource will be estimated, followed by the completion of an initial scoping

study (PEA). The PEA is scheduled to be completed before year end.

Figure 1. Cross-section through Esper ança South, showing previous drilling (dark green hole) and new drilling

(lighter green) that has identified new gold reefs beyond the pit shell previously used to constrain resources.

New reefs identified in heart of the deposit

Figure 1 shows a cros s-section through an area where indicated resources were reported in 2014. On this

section only one drill hole (CSH-12-083) was previously available for resource estimation ; one thick

mineralized interval in this hole controlled the location of the pit she ll within which resources were

reported. New holes within ±50m of this section now make it apparent that the pit shell used for the next

resource update will be larger, and will include thick reefs ( with true thickness >10m) that lie outside the

previous p it shell, with gold grades above the project average. In particular, CSH -17-191 encountered

14m running at an average of 3.2 g/t, with several shorter intervals above 5 g/t.

Grades and thicknesses remain strong in extensions

Figure 2 shows the location of the 93 RC holes that have been completed in the Esperança South and

Center regions of the project. All RC holes are vertical, and drilled to a target depth of 120m. A few holes

were terminated short of their 120m target due to local conditions; any hole th at reaches less than half of

its target length is deemed to be abandoned prematurely, and will be redrilled. Table 1 summarizes the

significant intervals (using a 0.4 g/t cutoff) not previously reported in holes for which assays were

available for more than half of the sample intervals.

Several individual intervals in these new holes run above 10 g/t, with CSH -17-188 reaching 27.8 g/t .

Some of the individual reefs in these new holes are considerably thicker than the deposit average, which

has historically been approximately 4m. With all of the new drilling being vertical, to a target depth of

120m, all of the reported significant intervals are within reach of an open pit. Although diamond drilling

has identified strong mineralization below 120m , the upcomin g PEA will focus only on a stand -alone

open pit mine, and will not address possible longer term potential from underground mining.

Figure 2. Location of new RC drilling at Castelo de Sonhos. RC holes whose significant intervals have been

previously reported are shown in dark green. All the RC holes whose significant intervals are summarized in Table 1

are shown in light green and lie in Esperança South. RC holes with assays pending are shown in blue ; black circles

mark old diamond drill hole locations.

Table 1. Significant intervals for RC holes not previously reported.

Hole From To Au Hole From To Length1 and Au grade

RC17-177 No significant intervals RC17-178 23 25 2m @ 1.3 g/t

RC17-179 59 60 1m @ 0.4 g/t

78 79 1m @ 0.7 g/t

RC17-1802 21 24 3m @ 1.8 g/t

45 46 1m @ 0.5 g/t

110 111 1m @ 0.6 g/t

115 116 1m @ 0.5 g/t

118 120 2m @ 0.5 g/t

RC17-182 32 34 2m @ 0.4 g/t

RC17-183 45 46 1m @ 1.2 g/t

98 100 2m @ 2.8 g/t

RC17-184 No significant intervals

RC17-185 28 30 2m @ 2.0 g/t

66 68 2m @ 10.6 g/t

Including 66 67 1m @ 18.1 g/t

109 110 1m @ 9.1 g/t

RC17-186 42 43 1m @ 6.5 g/t

RC17-187 31 35 4m @ 1.5 g/t

RC17-188 27 31 4m @ 8.3 g/t

Including 30 31 1m @ 27.8 g/t

RC17-190 47 52 5m @ 3.4 g/t

Including 47 48 1m @ 7.6 g/t

Including 51 52 1m @ 5.1 g/t

114 115 1m @ 2.5 g/t

RC17-191 20 21 1m @ 0.5 g/t

27 29 2m @ 2.4 g/t

35 38 3m @ 1.2 g/t

50 64 14m @ 3.2 g/t

Including 50 51 1m @ 5.3 g/t

Including 54 55 1m @ 5.5 g/t

Including 58 59 1m @ 14.6 g/t

Including 62 63 1m @ 5.1 g/t

RC17-192 24 25 1m @ 1.4 g/t

98 99 1m @ 1.5 g/t

105 107 2m @ 4.1 g/t

Including 106 107 1m @ 7.1 g/t

RC17-193 <50% of assays available

RC17-195 No significant intervals (53% of assays available)

RC17-196 80 84 4m @ 0.6 g/t

98 100 2m @ 2.2 g/t

RC17-202 60 67 7m @ 4.8 g/t

Including 65 67 2m @ 11.0 g/t

1All new holes are vertical, through reefs that dip at 25-30°, making the

down-hole thicknesses reported here 10-15% longer than true thickness.

2Assays were previously available for the bottom half of Hole 180, where

significant intervals were previously reported. The 21-24m and 45-46m

intervals in this hole are reported here for the first time.

Sample analysis procedures and QA/QC protocols

Sample preparation and analytical work for all of the results reported here were carried out by ALS

laboratories, with sample preparation done at its lab in Goiania, Goias and 1Kg Leachwell assays at its

lab in Lima, Peru; both of these ALS facilities are ISO 9001:2008 and 14001:2004 certified. ALS uses

industry-standard analytical methods and have internal QA/QC programs to monitor the reliability of their

work. Independently of the labs, TriStar runs its own external QA/QC program, using standards, blanks

and duplicates inserted into the sample processing stream at a rate of one per 10 samples.

Update on new Brazilian mining law

On July 25, 2017, Brazilian President Michel Temer signed into law three provisional measures, referred

to as MP 789, MP 790 and MP 791, that a ffect mining projects throughout the country. They take effect

immediately, with Congress being allowed a reasonable period of time to review and amend them.

MP 789 addresses taxation and royalty issues; its principal effect on the Castelo de Sonhos projec t is to

increase the government royalty on gold production from 1% to 2%.

MP 790 modernized the country’s mining code, parts of which had become inconsistent with other

regulations since it was last updated, more than 20 years ago. These changes include: an initiative to align

Brazil’s reporting codes with international reporting codes such as NI 43 -101; the ability to extend the

period during which geology and engineering studies can be done; ending the possibility of a mineral

concession being claimed if the holder of the rights is late in filing certain reports; specific guidance on

mine closure; and changes to the schedule of reporting deadlines. All of these are helpful to TriStar as it

works to advance the Castelo de Sonhos project.

“We welcome all of these changes,” says Nick Appleyard. “They improve transparency in the regulatory

framework, and are designed to relieve companies and the regulators from political pressure. All of this

should make it easier and quicker for us to bring Castelo de Sonhos through the feasibility and permitting

process, and to construct a successful and profitable mine”.

TriStar's Vice-President, R. Mohan Srivastava (P.Geo.), is the QP for this press release and has prepared

or supervised the preparation of the scientific or technical information in this press release.

About TriStar:

TriStar Gold is an exploration and development company focused on precious metals properties in the

Americas that have potential to become significant producing mines. The Company’s current flag ship

property is Castelo de Sonhos in Pará State, Brazil. The Company’s shares are listed on the TSX Venture

Exchange under the symbol TSG. Further information is available at www.tristargold.com.

For further information, please contact:

TriStar Gold Inc.

Nick Appleyard

President and CEO

480-794-1244

[email protected]

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the po licies of the TSX

Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. No stock exchange, securities commissi on

or other regulatory authority has approved or disapproved the information contained herein.

Forward-Looking Statements

Certain statements contained in this press release may constitute forward -looking statements under Canadian securities

legislation which are not historical facts and are made pursuant to the "safe harbour" provisions under the United States Pri vate

Securities Litigation Reform Act of 1995. Generally, forward -looking information can be identified by the use of forward -looking

terminology such as “expects” or “it is expected”, or variations of such words and phrases or statements that certain actions ,

events or results “will” occur. Forward looking statements in this press release include, the scope and success of the planned

exploration program at the Castelo de Sonhos project and the Company's opinion that it has clear title to the Castelo de Sonh os

property Such forward-looking statements are based upon the Company's reasonable expectations and business plan at the date

hereof, which are subject to change depending on economic, political and competitive circumstances and contingencies. Readers

are cautioned that such forward -looking statements involve known and unknown risks, uncertainties and other factors that may

cause a change in such assumptions and the actual outcomes and estimates to be materially different from those estimated or

anticipated future results, achievements or position expressed or implied by those forward -looking statements. Risks,

uncertainties and other factors that could cause the Company's plans to change include changes in demand for and price of gol d

and other commodities (such as fuel and electricity) and currencies; changes or disruptions in the securities markets; legislative,

political or economic developments in Brazil; the need to obtain permits and comply with laws and regulations and other

regulatory requirements; th e possibility that actual results of work may differ from projections/expectations or may not realize

the perceived potential of the Company’s projects; risks of accidents, equipment breakdowns and labour disputes or other

unanticipated difficulties or int erruptions; the possibility of cost overruns or unanticipated expenses in development programs;

operating or technical difficulties in connection with exploration, mining or development activities; the speculative nature of gold

exploration and development , including the risks of diminishing quantities of grades of reserves and resources; and the risks

involved in the exploration, development and mining business. Although management of the Company has attempted to identify

important factors that could cause actual results to differ materially from those contained in forward -looking statements or

forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. The

Company disclaims any intention or ob ligation to update or revise any forward -looking statements whether as a result of new

information, future events or otherwise, except as required by applicable securities laws.