TORONTO, ONTARIO - Tsodilo Resources Limited (“Tsodilo” or the “Company”) (TSX - Venture Exchange: (TSD)) is pleased to announce that it has completed its pilot hole drill program on its wholly owned BK16 kimberlite project . The purpose of this drilling program was to drill pilot holes on the sites

Exploration Programs

TSODILO RESOURCES LIMITED

BK16 UPDATE

FOR IMMEDIATE RELEASE June 26, 2017

TORONTO, ONTARIO - Tsodilo Resources Limited (“Tsodilo” or the “Company”) (TSX - Venture Exchange:

(TSD)) is pleased to announce that it has completed its pilot hole drill program on its wholly owned BK16

kimberlite project . The purpose of this drilling program was to drill pilot holes on the sites which have b een

earmarked for the Large Diameter Drill (LDD) drilling program.

BK16

The BK16 kimberlite project is located within the Orapa Kimberlite Fie ld (“OKF”) in Botswana. The diamond

mines in Botswana have produced an average of 27 million carats annually in the last 10 years and Botswana is the

world’s largest producer of diamonds by value. In 201 6, the OKF area produced 8.85 million carats. Of the 83

known kimberlite bodies, eleven have been or are currently being mined. These are AK01, AK02 and AK07 (Orapa,

Debswana), AK06 (Karowe, Lucara Diamond Corporation), BK01, BK09, BK12 and BK15 (Damtshaa, Debswana),

DK01 and DK02 (Letlhakane, Debswana) and BK11 (Firestone Diamonds). The Karowe mine has produced such

notable diamonds as the 1,109 carat `Lesedi La Rona` and the 813 carat `Constellation`.

The diamondiferous BK16 kimberlite pipe is approximately 6 hectares in size at surface, and is known to contain

rare and valuable Type I Ia diamonds (see press release dated May 31, 2016 ). The following phases of kimberlite

were identified during the 2015 drilling program: Red volcaniclastic kimberlite VK1, Black VK2, Grey VK3 and

VKxxx also referred to as the basalt breccia, country rock breccia (CB) and coherent kimberlite (CK1). A geological

model based on the 3,050 meters of core recover in 2015 was completed in 2016.

Pilot Hole Drill (‘PHD’) Program

Kimberlite phases VK2 and VK3 are volumetrically the most important and will be the focus of the Large Diameter

Drilling (“LDD”) program. The positioning of the initial 14 LDD holes was designed to provide grade estimates for

the main kimberlite phases as well as initial grade distribution across the kimberlite. Z Star Mineral Resource

Consultants (Cape Town, South Africa) were retained to optimize these objectives. The hole diameter of the LDD

holes will be 24-inch and the planned 14 holes will provide some 2,000 tons of kimberlite.

In order to correlate the diamond recoveries directly to the geological model and to ensure that the intersection of the

LDD holes are maximized it was necessary to probe all LDD sites with NQ size diamond core holes. The PHD

program as well as the earlier delineation drilling was conducted utilizing the Company’s Atlas Copco CT14

diamond core drill rigs. All bits used were of a Wuxi -Tsodilo design and contained only synthetic industrial

diamond. All pilot and delineati on core holes were logged in the field in detail according to a standard operating

procedure, describing each kimberlitic unit, measuring contacts between various units as well as kimberlite/country

rock contacts and brief descriptions of country rock. Mag netic susceptibility measurements were taken every 20

centimeters and the country rock dilution content was logged using the line point count method along the entire

kimberlite intersection. Core recovery and depth data were recorded as per standard operat ing procedure. Core

recovered from the pilot hole drilling is stored at the Company’s Letlhakane exploration camp. The core has been

labelled, photographed and the information captured in the Company’s database. Density (specific gravity)

measurements were done on the delineation core samples by taking a 20 to 30-centimeter length of core every 2

meters. The core was then coated in a thin film of varnish and the density was established using the Archimedes

method of weighing in air and in water. Additional samples for density measurements will be taken from the PHD

cores where the delineation drilling had not sufficient coverage.

The PHD program has now been completed and in total 3,220 meters were drilled and intersections were as follows:

PHD Program Meters Drilled Meters planned for

LDD drilling

Approximate kimberlite tonnage

recovered from LDD sampling

Kalahari Overburden 354 354 -

Kimberlite Phase

VK2 915 965 705

VK3 1,654 1,654 1,224

VKxxx 76 76 56

Country Rock Breccia 156 50 34

Country Rock 65 - -

Totals 3,220 3,099 2,019

Two holes in the center of the pipe will be extended by 25 m eters each to increase the sample size for VK2. A small

section of the country rock breccia will also be sampled to test its grade. The LDD contractor commenced operations

in May. In itial work consisted of collaring the 14 LDD holes immediately adjacent to the PHD holes to a depth of

22 meters using 30-inch casing. It is expected that this program will be completed in the second w eek of July after

which the contractor’s LDD Elephant rig will be deployed to drill and recover the kimberlite below the Kalahari

overburden using 24-inch holes.

About Tsodilo Resources Limited: Tsodilo Resources Limited is an international diamond and metals exploration

company engaged in the search for economic diamond and metal deposits at its Bosoto (Pty) Limited (“Bosoto”) and

Gcwihaba Resources (Pty) Limited ("Gcwihaba") projects in Botswa na and its Idada 361 (Pty) Limited (“Idada”)

project in Barberton, South Africa. The Company has a 100% stake in Bosoto (Pty) Ltd. which holds the BK16

kimberlite project in the Orapa Kimberlite Field in Botswana. The Company has a 100% stake in its Gcwiha ba

project area consisting of twenty-one (21) metal (base, precious, platinum group, and rare earth) prospecting licenses

and eight (8) radioactive mineral licenses all located in the North -West district of Botswana. Additionally, Tsodilo

has a 70% stake i n Idada Trading 361 (Pty) Limited which holds the gold and silver exploration license in the

Barberton area of South Africa. Tsodilo manages the exploration of the Gcwihaba, Bosoto and Idada projects.

Overall supervision of the Company's exploration progra m is the responsibility of Dr. Mike de Wit, President and

COO of the Company and a "qualified person" as such term is defined in National Instrument 43-101.

The Company has offices in Toronto, Canada and Gaborone and Maun, Botswana. Please visit the Compan y's

website, www.TsodiloResources.com, for additional information and background on our projects.

This press release may contain forward -looking statements. All statements, other than statements of historical fact,

that address activities, events or develo pments that the Company believes, expects or anticipates will or may occur

in the future (including, without limitation, statements pertaining to the use of proceeds, the impact of strategic

partnerships and statements that describe the Company’s future pl ans, objectives or goals) are forward -looking

statements. These forward -looking statements reflect the current expectations or beliefs of the Company based on

information currently available to the Company. Forward -looking statements are subject to a numbe r of risks and

uncertainties that may cause the actual results of the Company to differ materially from those discussed in the

forward-looking statements, and even if such actual results are realized or substantially realized, there can be no

assurance that they will have the expected consequences to, or effects on the Company. Factors that could cause

actual results or events to differ materially from current expectations include, among other things, changes in equity

markets, changes in general economic c onditions, political developments in Botswana and surrounding countries,

changes to regulations affecting the Company's activities, uncertainties relating to the availability and costs of

financing needed in the future, exploration and development risks, t he uncertainties involved in interpreting

exploration results and the other risks involved in the mineral exploration business. Any forward -looking statement

speaks only as of the date on which it is made and, except as may be required by applicable securi ties laws, the

Company disclaims any intent or obligation to update any forward -looking statement, whether as a result of new

information, future events or results or otherwise. Although the Company believes that the assumptions inherent in

the forward -looking statements are reasonable, forward -looking statements are not guarantees of future

performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty

therein.

Neither the TSX Venture Exchange (“TSXV”) nor i ts Regulation Services Provider (as that term is defined in the

policies of the TSXV) accepts responsibility for the adequacy or accuracy of this news release. This news release

may contain assumptions, estimates, and other forward -looking statements regar ding future events. Such forward -

looking statements involve inherent risks and uncertainties and are subject to factors, many of which are beyond the

Company's -control, which may cause actual results or performance to differ materially from those currentl y

anticipated in such statements.

FOR FURTHER INFORMATION PLEASE CONTACT:

James M. Bruchs Chairman and Chief Executive Officer [email protected]

Dr. Mike de Wit President and Chief Operating Officer [email protected]

Head Office Telephone +1 416 572 2033 Facsimile + 1 416 987 4369

Website http://www.TsodiloResources.com