Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

TRX.TO ·

TRX Gold Reports Robust PEA on Next Buckreef Gold Expansion Pre-tax NPV5% of US$701M at US$2,296/oz Increasing to US$1.2Bn at US$3,000/oz

Economic Studies

PRESS RELEASE

For immediate release

TRX Gold Reports Robust PEA on Next Buckreef Gold Expansion

Pre-tax NPV5% of US$701M at US$2,296/oz

Increasing to US$1.2Bn at US$3,000/oz

TORONTO, Ontario, April 22, 2025 – TRX Gold Corporation (TSX: TRX) (NYSE American: TRX) (the “Company”

or “TRX Gold”) is pleased to announce positive results of a Preliminary Economic Assessment (the “PEA”) on

the expansion of its Buckreef Gold Project (“Buckreef Gold”) in Tanzania. The PEA evaluated the following

scenario:

(i) an expansion and upgrade of the existing process plant at Buckreef Gold to 3,000 tonnes per day (“tpd”); and

(ii) a transition from open pit mining to underground mining over the next 2-3 years. The PEA will be filed under

the Company’s profile on SEDAR+ within 45 days of this announcement.

Stephen Mullowney, TRX Gold CEO commented: “We have taken what we have learned over the past couple of

years and have now provided a more in-depth roadmap of Buckreef Gold’s potential based on what is currently

known, with a keen focus on maximizing the economics of Buckreef Gold. This PEA yields positive results based

on a relatively straightforward expansion, similar to the expansions we have successfully completed previously.

The PEA and associated project economics can also be further enhanced by additional process plant capacity

and mining rate increases in the future, and the Company will now begin to evaluate these opportunities. The

PEA does not currently contemplate inclusion of any new exploration discoveries at Buckreef Gold. The Anfield

Zone has not been included and only a small portion of Stamford Bridge Zone has been reflected in this PEA.

This is our first insight into Stamford Bridge, and it is still early days there as we continue to execute our

exploration program across the entire Buckreef Gold concession . The future is looking bright , and we are well

on our way towards making Buckreef Gold an exceptional gold producing asset.”

The Key Outcomes of the PEA:

• Base case NPV5% of US$701.0 million pre-tax, or US$442.2 million after tax at consensus forecast case

gold prices (US$2,707/oz year 1, US$2,646/oz year 2, US$2,495/oz year 3, US$2,400/oz year 4,

US$2,245/oz thereafter) and NPV 5% of US$1,180.5 million pre -tax, or US$766.4 million after tax at a n

upside US$3,000/oz gold price;

• The PEA demonstrates the Company’s ability to potentially finance the expansion from internally

generated cash flow without an upfront capital requirement, thus there is no quoted Internal Rate of

Return;

• Over a 17.6 -year period, the total process plant throughput is expected to be 18.1 million tonnes

averaging 2.14 g/t Au with average recovered gold production of approximately 62 ,000 oz Au per

annum. During the first five years of the underground operation, average recovered production is

planned to be over 80,000 oz Au per annum;

• Life of Mine (“LOM”) cash costs average US$1,024/oz Au and all-in sustaining costs (“AISC”) average of

US$1,206/oz Au;

• Growth capital of US$89 million will be deployed over the next four-year period comprised of: (i) US$55

million in capital for the underground expansion; (ii) US$30 million for process improvements , process

plant throughput expansion, and camp upgrades; and (iii) US$3 million for tailings facility upgrades. LOM

growth capital is estimated to be US$175 million and is primarily for underground development. LOM

sustaining capital cost of US$87 million is estimated for site and process plant, and US$97 million for

underground mining;

• The PEA mine plan was developed from Measured and Indicated Mineral Resources of 10.8 million

tonnes (“Mt”) grading 2.57 grams per tonne (“g/t”) gold containing 893,000 ounces of gold and Inferred

Mineral Resources of 9.1 Mt grading 2.47 g/t gold containing 726,000 ounces of gold; and

• With the existing open pit mine operating, the underground expansion plan benefits from the existing

on-site process plant and mine infrastructure in place. The Company anticipates gold production from

the underground expansion could be achieved within 3 years.

The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative

geologically to enable them to be categorized as Mineral Reserves. Therefore, there is no certainty that the PEA

economics will be realized. Mineral Resources that are not Mineral Reserves may not have demonstrated

economic viability. The Company engaged P&E Mining Consultants Inc. (“P&E”) to complete an updated Mineral

Resource Estimate for Buckreef Gold (Table 8) which provides the Mineral Resource basis for the PEA , and

expansion of the mine to include underground production, and for the existing process plant to increase capacity

to approximately 3,000 tpd.

Stephen Mullowney, TRX Gold CEO, further states, “The results of the PEA , as summarised in Table 1, show an

extremely robust project capable of producing 1.1 million gold ounces over a 17.6-year life, with low cash costs

of only US$1,024/oz Au and AISC of US$1,206/oz Au. The PEA indicates an upside pre-tax NPV5% of US$1.2 billion

and after-tax NPV5% of US$766 million at US$3,000/oz gold. We will now start work on optimizing results further,

including evaluating an additional process plant expansion and increased mining rates. We believe that will help

to solidify a project which ultimately is capable of producing 100,000+ gold ounces per year for 10+ years, based

on what is currently known and excluding any new additional Mineral Resources. It should be noted that Mineral

Resources were also estimated at a US$1,900 per oz gold price and there is also the potential to add additional

economic material if gold prices remain at current levels.

The growth capital cost for the expansion is estimated at US$89 million over a four -year period, inclusive of a

process plant expansion, process improvements, and tailings facility upgrade s. The Company has already

commenced some preparatory work for this expansion, including capital expenditure for the process plant

upgrades and camp expansion.

In addition, TRX Gold has established a strong O perations team of mining professionals on the ground in

Tanzania, which has successfully managed Buckreef Gold’s three previous expansions on-time and on-budget,

in achieving the current 2,000 tpd throughput capacity. The Company has been further enhancing the skillset of

this team to ensure that the necessary personnel are in place to support the next step in the development of

Buckreef Gold.”

Based on the estimated production schedule, capital costs and operating costs, a cash flow model was prepared

by TRX Gold for the economic analysis of the Buckreef Project. The cash flow model was reviewed and approved

by P&E. All information used in this economic evaluation was derived from work completed by P&E, with support

by TRX Gold.

Project economics were evaluated using a discounted cash flow method that measures the before-tax and after-

tax Net Present Value (“NPV”) of future cash flow streams. The PEA economic model was based on the following

key assumptions in Table 1.

Table 1 – PEA Summary of LOM 25 Key Metrics and Project Economics

Summary of Project Economics Life of Mine

Base Case Gold Price US$

2,707/oz year 1;

2,646/oz year 2;

2,495/oz year 3;

2,400/oz year 4; and 2,245/oz

thereafter

Discount Rate % 5

Mining Parameters

Open Pit - Tonnes of Mineralization Mt 3.5

Open Pit - Avg Grade g/t Au 1.92

Open Pit - Strip Ratio w:o 6.0

Underground - Tonnes of Mineralization Mt 14.4

Underground - Avg Grade g/t Au 2.22

Mine life - Open Pit & Underground Years 17.6

Process Plant Parameters

Recovery % 87

Rate tpd 2,824

Total Tonnage Processed Mt 18.1

Average Annual Production oz/year 61,700

Average Annual Production (first five years of

underground) oz/year 80,100

Capital Expenditures

Initial Capital Expenditures US$M Nil

Growth Capital Expenditure US$M 174.5

Sustaining Capital Expenditure US$M 184.4

Closure Cost US$M 13.4

Operating Costs

Mining Cost - Open Pit US$/t mined 3.78

Mining Cost - Underground US$/t processed 33.09

Processing Cost US$/t processed 12.68

G&A cost US$/t processed 6.50

Cost per Ounce

LOM Cash Cost US$/oz 1,024

LOM All-in Sustaining Cost US$/oz 1,206

Financial Analysis

Pre-tax NPV 5% US$M 701.0

Post-tax NPV 5% US$M 442.2

Financial Analysis

Figure 1 – Annual After-Tax Free Cash Flow (US$ millions), Cash Cost and AISC (US$/oz)

Figure 2 – Annual EBITDA (US$ millions)

Sensitivities

Table 2 – PEA Sensitivity Analysis – Gold Price

Gold Price (US$/oz) Pre-tax NPV 5% (US$M) Post-tax NPV 5% (US$M)

$3,000 1,180.5 766.4

$2,800 1,040.9 672.0

Base Case (avg. $2,296) 701.0 442.2

$2,400 761.6 483.1

$2,200 622.0 388.7

$2,000 482.4 294.2

$1,800 342.8 199.3

Table 3 – PEA Sensitivity Analysis – Operating Costs

Pre-tax NPV 5% (US$M) Post-tax NPV 5% (US$M)

Operation Cost Base Case (avg.

US$2,296)

Upside Case

@ US$3,000

Base Case (avg.

US$2,296)

Upside Case

@ US$3,000

Base case -25% 858.9 1,338.3 552.6 876.9

Base case -10% 764.2 1,243.6 486.4 810.6

Base case 0% 701.0 1,180.5 442.2 766.4

Base case +10% 637.9 1,117.3 398.0 722.2

Base case +25% 543.2 1,022.6 331.6 656.0

Table 4 – PEA Sensitivity Analysis – Growth Capital Costs

Pre-tax NPV (US$M) Post-tax NPV (US$M)

Growth Capital Cost Base Case (avg.

US$2,296)

Upside Case

@ US$3,000

Base Case (avg.

US$2,296)

Upside Case

@ US$3,000

Base case -25% 735.9 1,215.4 468.7 792.9

Base case -10% 715.0 1,194.4 452.8 777.0

Base case 0% 701.0 1,180.5 442.2 766.4

Base case +10% 687.1 1,166.5 431.6 755.8

Base case +25% 666.2 1,145.6 415.6 739.9

Production

Annual production over LOM is expected to average approximately 62,000 ounces with peak production of

94,000 ounces in year 5 (Figure 3). Underground production commences in Year 3.

Figure 3 – Production Profile

Capital Expenditures

The growth capital expenditures are estimated at US$89 million in Years 1 to 4. LOM growth capital expenditures

are estimated at US$175 million and the sustaining capital expenditures are estimated at US$184 million (Tables

5 & 6). A contingency of US$23 million and US$19 million is included in growth and sustaining capital

expenditures, respectively.

Growth and sustaining capital expenditures were estimated based on current costs received from vendors as

well as developed from first principles, while some were estimated based on factored references and experience

from similar operating projects.

Figure 4 – Capital Expenditure Profile (US$ millions)

Table 5 – Growth Capital Expenditures (US$ millions)

Table 6 – Sustaining Capital Expenditures (US$ millions)

Cost Element LOM Total

Site and Process Plant - US$5M per year 87.5

Underground 96.9

Total Sustaining Capital 184.4

Total Cash Costs

The total unit cash costs are estimated at US$1, 024/oz. The AISC is estimated at US$1, 206/oz. Operating cost

estimates were developed using first principles methodology, vendor quotes, and based on historical actual

operating information at Buckreef Gold.

Table 7 – Total Cash Cost and AISC

Cost Element LOM Total (US$M)

Average LOM

(US$/tonne

processed)

Average LOM

(US$/oz)

Mining (Open Pit) 91.7 26.6 (1) 84.5

Mining (Underground) 475.0 33.1 (2) 437.7

Processing 229.2 12.7 211.2

General & Admin. 117.5 6.5 108.3

Royalty & Selling Cost 197.5 10.9 182.0

Total Cash Cost 1,110.8 61.4 1,023.7

Sustaining Capital 184.4 10.2 169.9

Reclamation 13.4 0.7 12.4

Total AISC 1,308.7 72.4 1,206.0

Notes:

(1) Per tonne of ore processed from open pit only.

(2) Per tonne of ore processed from underground only.

Mineral Resource Estimate

An updated Mineral Resource Estimate for Buckreef Gold including the Stamford Bridge domain is presented in

Table 8 and has an effective date of April 15, 2025.

Mineral Resource Estimate Methodology

The Buckreef Gold and Stamford Bridge Mineral Resource models were developed by P&E from 135 wireframes

and one respective wireframe, all created by P&E over respective 2.2 km and 155 m strike lengths . Buckreef

Gold utilized 884 drill holes while Stamford Bridge utilized eight. Wireframes were developed from an open pit

cut-off of 0.40 g/t Au while underground was 1.20 g/t Au. Both Mineral Resource models utilized 1.0 m capped

composites ranging from no capping to 60 g/t Au. Block models were set up with 2. 5 m x 5.0 m x 5.0 m blocks

rotated 30 degrees clockwise and used a bulk density of 2.70 t/m 3. Grade interpolation was done with inverse

distance cubed estimation. Based on variography, Measured Mineral Resources were those blocks classified

within 20 m of three drill holes while Indicated Mineral Resources were classified within 40 m of three drill holes.

All other wireframe constrained grade blocks were classified as Inferred Mineral Resources. Pit-constrained and

out-of-pit Mineral Resources were reported above respective 0.42 g/t and 1.31 g/t Au cut-offs. -------------------

----------------------

Table 8 - Mineral Resource Estimate (1-7)

Zone Cut-off Au g/t Tonnes (k) Au g/t Au ozs (k)

MAIN

Measured 0.42/1.31 2,982.8 2.36 226.4

Indicated 0.42/1.31 6,193.9 2.72 542.6

Meas + Ind 0.42/1.31 9,176.7 2.61 769.0

Inferred 0.42/1.31 7,549.3 2.37 576.0

SOUTH

Measured 0.42/1.31 23.6 1.68 1.3

Indicated 0.42/1.31 35.3 1.95 2.2

Meas + Ind 0.42/1.31 58.9 1.84 3.5

Inferred 0.42/1.31 53.8 1.70 2.9

WEST

Measured 0.42/1.31 40.3 3.27 4.3

Indicated 0.42/1.31 204.7 2.52 16.5

Meas + Ind 0.42/1.31 245.0 2.64 20.8

Inferred 0.42/1.31 73.9 2.37 5.6

EASTERN PORPHYRY

Measured 0.42/1.31 2.9 6.97 0.6

Indicated 0.42/1.31 1,306.4 2.35 98.8

Meas + Ind 0.42/1.31 1,309.3 2.36 99.4

Inferred 0.42/1.31 1,198.8 2.44 94.0

STAMFORD BRIDGE

Inferred 1.20 272 5.38 47.0

TOTAL

Measured 0.42/1.31 3,049.6 2.37 232.6

Indicated 0.42/1.31 7,740.3 2.65 660.1

Meas + Ind 0.42/1.31 10,789.9 2.57 892.7

Inferred 0.42/1.20/1.31 9,147.8 2.47 725.5