Taranis Secures Permit to Drill Ridge Target, Advances 10,000 tonne Bulk Sample Mining Permit Application

Exploration Programs Permits & Approvals Metallurgy & Processing

FOR IMMEDIATE RELEASE

Taranis Resources Inc.

681 Conifer Lane

Estes Park, Colorado

80517

www.taranisresources.com

Taranis Secures Permit to Drill Ridge Target, Advances 10,000 tonne Bulk

Sample Mining Permit Application

Estes Park, Colorado, January 20, 2020 – Taranis Resources Inc. ( “Taranis”) [TSX.V: TRO ,

OTCQB: TNREF] is pleased to announce that it has received a permit to drill high-value

exploration targets associated with the polymetallic mineral resource at its 100%-owned Thor

property located near Trout Lake, British Columbia.

Ridge Drilling Target and Drilling Permit

Taranis has identifie d, modeled, and prioritized an area of known, outcropping mineralization

that extends at least 1.2 km to the north of the existing deposit. In March of 2019, Taranis’

permitting team filed a Notice of Work application to construct and drill relatively deep holes

from drill sites on a major topographic feature known as Thor’s Ridge. The program is designed

to follow t he Thor deposit to the northwest. The NOW also included a proposal to test several

targets towards the south end of the True Fissure portion of the deposit that are not presently

included in the substantial resource calculation.

With the gra nting of the N otice of Work permit, Taranis is poised to make major strides in

outlining the extent of the ore body at Thor. Mineralization under Thor’s Ridge has long been

theorized but has never been drill tested; Taranis’ drill permits cover the entire strike length (1.5

km) of the new target.

Thor 10,000 tonne Bulk Sample Metallurgical Application

Taranis has recently furnished the British Columbia Ministry of Energy, Mines and Petroleum

Resources (“MEMPR”) with several reports contributing to Technical Review of the 10,000

tonne bulk sample application including an independent engineering assessment of the proposed

water treatment plant, and an Archeological Overview Assessment . Later this week, a benthic

invertebrate fauna study of True Fissure, Broadview and Ferguson Creeks will also be submitted

that was performed in September 2019.

Technical Review for Joint Environmental/Mines Act “JEMA” permits are typically expected to

take 60 days per MEMPR; current review for the 10,000 tonne bulk sample has taken more than

120 days. Taranis’ Qualified Persons and permitting team are working diligently to ensure that

the review is completed punctually and with consideration to the scale of the project. Taranis and

its Qualified Persons are satisfied that these reports, in tandem with the Joint Application

document, create a compelling and well -supported rationale for the project . Mine permitting

standards in British Columbia have evolved to require extensive preliminary data, and execution

of the bulk sample is a major step forward in collecting important data to make Thor into a safe,

environmentally conscious commercial mining operation.

John Gardiner , CEO, remarks: “…this is an exciting project for Taranis and for this area of

British Columbia, as it tests gravity pre-concentration as a means of processing polymetallic ores

2

at Thor. The approach minimizes environmental impact, and in addition will clean -up the impact

of several pre-existing stockpiles that remain o n surface. Information from the operation of this

plant would be used in a mining feasibility study of mining the main deposit at Thor . It’s a win-

win for everyone”.

About Taranis Resources Inc.

Taranis is an exploration company focused on the development of its 100% -owned Thor project

in southeast British Columbia. The Company has a clear growth strategy that involves the

ongoing growth of the mineral Resource at Thor, and commercial mining of th e deposit . For

additional information on Taranis or its Thor project, please visit our website at

www.taranisresources.com.

Taranis currently has 71,074,500 shares issued and outstanding ( 82,733,266 shares on a fully -

diluted basis).

TARANIS RESOURCES INC.

Per: John J. Gardiner (P. Geol.),

President and CEO

For further information contact:

John J. Gardiner

681 Conifer Lane

Estes Park, Colorado

80517

Phone: (303) 716-5922

Cell: (720) 209-3049

[email protected]

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS

DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE

ADEQUACY OR ACCURACY OF THIS NEWS RELEASE.

This News Release may contain forward looking statements based on assumptions and judgments of management

regarding future events or results that may prove to be inaccurate as a result of factors beyond its control, and

actual results may differ materially from expected results.