Taranis Provides Comments on Thor Bulk Sample Permitting Amid Policy Uncertainty and Permitting Project Mismanagement
FOR IMMEDIATE RELEASE
Taranis Resources Inc.
681 Conifer Lane
Estes Park, Colorado
80517
www.taranisresources.com
Taranis Provides Comments on Thor Bulk Sample Permitting Amid Policy
Uncertainty and Permitting Project Mismanagement
Estes Park, Colorado, March 16, 2020 – Taranis Resources Inc. (“Taranis”) [TSX.V: TRO,
OTCQB: TNREF] is updating ongoing permitting activities for a 10,000 tonne bulk sample on
its 100%-owned Thor Project located in British Columbia. This follows a conference call with
the Executive Regional Director of Ministry of Energy, Mines and Petroleum Resources
(“MEMPR”), the Thor Mine Development Review Committee Chairperson, and the Executive
Director of “Major Mines” Permitting Office on March 12, 2020.
Background
Taranis began a 10,000 t onne Bulk Sample Application (“10KBSA”) via MEMPR on October
15, 2018 . The project is designed to test metallurgical recoveries using a novel gravity-based
concentration system, producing pre-concentrate that can be shipped offsite for further
upgrading, and to minimize onsite in frastructure. The process would remove Legacy acid-
generating/metal-leaching surface stockpiles left behind at Thor from more than a century of
historical mining activity , and most importantly would provide valuable data for a Preliminary
Economic Assessment for the much larger in -situ Thor deposit. Bulk samples are considered an
essential exploration/business activity and are routinely conducted to gather me tallurgical and
environmental data.
Barriers to the 10,000 Tonne Bulk Sample Permit
Taranis’ permitting team assented to MEMPR’s declaration in 2018 that the 10KBSA must be
processed under a full -scale Joint Environmental and Mines Act Application/Information
Requirements Table (“JEMA/IRT”) process, which until now was formulated specifically for
full-scale commercial mining application s. MEMPR indicated on numerous occasions that the
JEMA would be specifically tailored to fit the size of the 10KBSA and could include provisions
for conditional permit issuance . Taranis was notified that the s creening of the application was
completed by MEMPR Reviewers on September 16, 2019 and has since been in Technical
Review, which was previously estimated to take 60 days.
Taranis, being an exploration company, is in a unique position to experience every aspect of the
permitting process in B.C. During the course of the still ongoing Technical Review, twenty-eight
(28) individual Technical Reviewers from four sectors of the B.C. government were involved
and provided commentary on the JEMA/IRT . Input from these Technical Reviewers led to
modification of the original 10KBSA, including site layouts, water treatment, etc. During the
course of the Technical Review, Taranis notified MEMPR of multiple catastrophic deficiencies
and concerns with MEMPR’s management of the 10KBSA, its implementation, and “moving
goalposts”.
2
The “moving goalpost s” aspect was highlighted by MEMPR’s recent insistence that ‘Final’,
stamped engineering drawings must be provided before Technical Review can be concluded.
This undermines the spirit of Technical Review, which serves as iterative improvement on the
‘Draft’ designs that were completed by AllNorth Engineering – and leads to the ‘Final’
collaborative site engineering plan . Taranis indicated that it would be more than happy to
provide ‘Final’ engineering designs, only after Technical Reviewers had finished providing
comments in order to adher e to timely project management principles . Taranis also suggested it
was amenable to a review of the ‘Final’ site-engineering plans before permit issuance. Taranis
views this as an essential aspect of permitting the 10KBSA, so that the ‘Final’ site-engineering
plans aren’t modified multiple times based on whims of improperly managed Technical
Reviewers.
The March 12, 2020 phone call also highlighted generic misrepresentation of 10KBSA
applications in B.C. by MEMPR . Lowell Constable, Executive Director & Deputy Chief
Inspector of Mines - Major Mines Permitting Office in Victoria - stated “We want to make sure
that what companies are providing meets the code, and [Taranis’] planned tailings disposals
don’t meet anything described by the [ current B.C. Mining] code. The reason MEMPR is
applying major mine permitting to bulk samples is because of Mt. Polley ”. Whereas previously,
the B.C. Mining Code allowed for scaling of permitting requirements based on the size of the
mine, Mr. Constable continued to sa y, “What has come out of [removed from] the Code, is any
scaling of that [bulk sample allowance] . There are no minor tailings facilities anymore in the
code – So big or small, I’m not going to lie, there are a lot of pieces still moving around in the
tailings management code”. It is unreasonable that full -scale commercial mine permitting scope
and associated costs be applied cart-blanche to any and all test production scenarios.
From the outset of the 10KBSA application, Taranis operated under the belief that conditional
permitting was a tool MEMPR could use to fit the JEMA /IRT process to a small -scale bulk
sample. This is a cornerstone of the 10KBSA, even as a concept, since the sale of pre-
concentrate requires that a contract be negotiated with a third-party, permitted, processing
facility. On March 12, 2020, almost one and one -half years after Taranis filed the 10KBSA,
Heather Cullen, Executive Regional Director of MEMPR remarked “We are getting away from
issuing conditional permits – conditional permits are not the way we are going …”. This
comment underscores a major inconsistency, despite this being a component of the JEMA/IRT
accepted for Technical Review.
Conclusion
Taranis has made a substantial investment in exploring Thor, and permitting the Thor 10KBSA,
and this was done in good faith under the guidance of Cranbrook’s MEMPR, trusting that a
modified full-scale JEMA/IRT application is applicable to permitting requirements. Taranis was
clearly informed on March 12, 2020 that there are no clear, concise, reasonable permitting
allowances for exploration bulk sampling in B.C. – an essential exploration tool to the mining
business. Up until 2018, there was a well-defined permitting process for exploration bulk
sampling. The remarks made by MEMPR explain the frequently moving “goalposts” that Taranis
has encountered . Policy uncertainty coupled with a vast underlying foundation of project
mismanagement issues is anathema to success in B.C.’s mining economy.
Attempts made by Taranis to discuss and repair these issues have only met with resistance within
MEMPR and are met with further demands to deal with marginal issues of dubious intent. These
3
problems can be fixed – by providing clear, consistent, project management fundamentals
governing the application process, with regulations and policies that are scalable, effective, and
which address the needs of exploration companies and the public.
Board of Directors Analysis
The Taranis Board remarks “Sending conflicting and contradictory guidance to exploration and
mining companies creates unfairness and uncertainty that jeopardize any exploration or mining
investment in B .C. While MEMPR has recently adopted the slogan ‘Regulatory Excellence’ ,
Taranis has experienced failed project management , changing policies, moving goal posts, and
the inability by MEMPR to meet any credible timeline. It begs the question , ‘Why bother
exploring in B .C. for mineral deposits when the Permitting process is ill -defined and poorl y
implemented?’ Based on our experience, i t is easy to conclude that the current B.C. government
is intent on eliminating the mining industry in the province by instituting a barrage of vague and
ever-changing requirements for permitting and operation , with a compliment of inexperienced
and unqualified civil servants in positions of authority whos e obvious intention is nothing less
that making sure nothing gets done”.
About Taranis Resources Inc.
Taranis is an exploration company , developing its 100%-owned Thor project in southeast B.C..
Taranis owns 100% interest in 27 contiguous Crown Grant Mining Claims (all with mineral
rights, and many with surface rights) and 3,153 Ha of Mineral Tenures at Thor. Taranis has two
areas of Thor permitted/bonded for exploration drilling for 5 years, and a third approved permit
to drill the Ridge Target that requires bonding (C$52 .4K). Taranis will evaluate the benefit of
paying the remaining bond as permitting circumstances evolve.
Taranis currently has 71,074,500 shares issued and outstanding ( 82,733,266 shares on a fully -
diluted basis).
TARANIS RESOURCES INC.
Per: John J. Gardiner (P. Geol.),
President and CEO
For further information contact:
John J. Gardiner
681 Conifer Lane
Estes Park, Colorado
80517
Phone: (303) 716-5922
Cell: (720) 209-3049
NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS
DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE
ADEQUACY OR ACCURACY OF THIS NEWS RELEASE.
This News Release may contain forward looking statements based on assumptions and judgments of management
regarding future events or results that may prove to be inaccurate as a result of factors beyond its control, and
actual results may differ materially from expected results.