Taranis Proves Bulk Grade of SIF Zone Pilot Plant Sample 600 mt at 6.5 g/t Gold

Drill Results Sampling & Geoscience Results Metallurgy & Processing

FOR IMMEDIATE RELEASE

Taranis Resources Inc.

681 Conifer Lane

Estes Park, Colorado

80517

www.taranisresources.com

Taranis Proves Bulk Grade of SIF Zone Pilot Plant Sample

600 mt at 6.5 g/t Gold

Estes Park , Colorado, November 20, 2018 – Taranis Resources Inc. (“Taranis” or the “Company ”)

[TSX.V: TRO] has completed analyses of a bulk sample produced from the SIF pilot gold plant in the

summer of 2017 at its 100% owned Thor project. Various production hypotheses were put to the test; new

and critical steps for economic production were identified and have been incorporated in the planning

stages for larger-scale mining activity, namely Phase II of a Joint Mining and Environmental Application

(Taranis News Release October 15, 2018). Because the Thor Resource primarily hosts silver and has

never produced gold from a monometallic zone in its 100+ year history, gaining a better understanding of

the gold zones is a major development which could drastically increase the already substantial value of

the deposit.

Data gathered in this early scoping study may also enable Taranis to better explore for the continuation of

SIF and has already yielded improved methodologies for more efficient extraction of precious metals

from the ore. Exploration work in the summer of 2018 identified adjacent areas of major quartz veining

bearing strong resemblance to the SIF zone . Further exploration, especially drilling, will be required to

determine these zones’ relevance to the high-grade gold found at SIF.

The following table details the gold content and recovery from the 600 tonnes of SIF ore:

SIF Pilot Gold Plant - Metallurgical Accounting

Grams Ounces

Recovered gold from processing 706.1 24.9

Gold lost in lab processing of Super-Concentrate 27.2 1.0

Gold lost in lab processing of Concentrate 248.8 8.8

Gold lost on shaker table in field ("Tails") 2,897.7 102.2

Total gold contained in ore processed 3,879.8 136.9

Recovery percentage (“field concentrates”) 25.3%

Recovery percentage after lab processing 18.2%

Total tonnes processed in field milling 600

Grams/tonne Ounces/tonne

Actual grade of processed ore 6.47 0.23

Although the permit allowed for the extraction and processing of 1,000 tonne s of ore, field conditions

limited the processing to 600 tonnes of ore. Despite this shortcoming, this was a large enough sample to

provide data to develop general knowledge related to this unique part of Tho r. I dentification and

incremental improvement of operating deficiencies could significantly improve recovery processes in the

upcoming Phase II Mining project.

2

Of note is the low recoveries exhibited using the Mt. Baker processing plant. In field operations, the plant

was only able to recover 25.3% of the gold from the ore, and this is attributable in large part to the use of

a hammer mill which could only grind the ore to -1.5 mm in size. The recoveries were further impacted

by the loss of gold in the laboratory processing (re -tabling of the concentrat es), particularly on the finer -

grained concentrate fraction where 35% of the available gold was lost upgrading the material. This

contrasts with only 4% of the gold lost re -tabling the super -concentrate fraction which contained much

coarser gold.

The crushed tailings from the pilot mill are accessible at Thor, and once optimal production efficiency has

been achieved in Phase 2, the crushed tailings c ould be reprocessed for recovery of the remaining gold in

the tailings pond. It is expected that a finer cru sh size will liberate substantially more gold than could be

retrieved using the hammer mill employed in 2017.

SIF Geology

Gold is confined to an area of quartz that is characterized by extensive vugging and iron -oxide alteration

that occurs within a tight anticline structure west of the main Thor deposit . SIF is truncated by a NNW-

trending fault (SIF Fault) that dips moderately to the WSW on the west side of the outcrop. The fault is

traceable on VLF surveys for a considerable distance to the NNW. The structural relationships

demonstrate that gold deposition occurred before the folding and faulting of the zone, making it very

likely that other pieces of SIF remain to be discovered.

Stratigraphically, SIF lies along the contact between underlying Sh aron Creek Formation (carbonaceous

argillite) and the overlying Broadview Formation (greywacke). During the excavation of the open pit,

distinct green sedimentary-tuffaceous rocks of the Jowett Formation were noted. The gold -bearing

horizon is a continuati on of the main Thor deposit, but lacks much of the base metal and silver

mineralization characteristic of the main deposit. In fact, the silver/gold ratio is 0.2:1 at SIF in contrast to

the main Thor deposit where it is 233:1, indicating a rapid and major metal transition in the Thor deposit.

Continuity of Gold at SIF

The SIF zone consists of both fine , disseminated and coarse nuggety gold (up to 4 mm) in quartz . One of

the objectives was to determine whether gold mineralization was restricted to narrow, high-grade

structures, or if the gold was disseminated in the quartz-bearing zone. The results of the pilot mill indicate

that the gold-bearing material was consistently spread out through the 68-day operating period, and from

day to day there was little variation in the gold content of the middlings and tails.

Launder No. Samples Au

Minimum

(g/t)

Au

Maximum

(g/t)

Standard

Deviation

Au Mean

(g/t)

#3 Middlings 62 1.9 34.8 5.8 6.9

#4 Waste 62 1.0 19.5 2.8 4.3

The occurrence of gold throughout the zone is reasonably consistent with the interpretation that the zone

is a stratabound gold occur rence and has the potential to be related to a much large r gold occurrence that

remains undiscovered.

Metallurgical Accounting & Methodology

During the daily operation of the mill, samples were taken from the #3 & #4 launders of the shaker table

and analyzed for gold and 32 element ICP. In addition to this, material was collected from the #1 & #2

3

launders (super-concentrate and concentrate respectively) which c ontained all recoverable gold from the

shaker table. The concentrates contained concentrated pyrite as well as trace levels of galena. These bags

were weighed daily and were sent for subsequent upgrading offsite at Met-Solve Laboratories Inc. (“Met-

Solve”).

During the operation of the plant, the volume of material (and gold content) that was discharged from the

#3 and #4 launders was measured. This was reconciled with the number of feed hoppers of ore put

through the mill as well as a volume calculation of the tailings pond to de duce that 600 tonnes of ore had

been processed. The following table shows th e amount of concentrate that was produced from the Mt.

Baker plant over the entire 68-day operating period.

Concentrate Product Kg

Super-concentrate (#4 launder) 91.2

Concentrate (#3 launder) 388.2

Total concentrate 479.4

Concentrate Upgrading (Met-Solve Laboratories Inc.)

The concentrates were upgrad ed by Met -Solve Laboratories in controlled laboratory conditions . This

consisted of two phases, the first being the tabling of the super-concentrates, and the second being tabling

of the concentrates. Gold mass balance charts were created for the super -concentrate and concentrate

products that showed the grade, recovery, and mass distribution for e ach of the products. For more

information, please visit the website www.taranisresources.com.

Magnetic Separation of Super-Concentrate and Concentrate products

Products from the tabling at Met -Solve were separated magnetically. The initial hypothesis was that this

process would have merit in removing tramp iron ablated from the hammer mill, but this early hypothesis

was disproven. In fact, the magnetic component h ad much higher gold grades than the non -magnetic

fraction and this is most probably due to retention of gold smeared on denuded metal from the hammers

in the hammer mill.

Roasting of Pyritic Concentrates

It was expected that gravity concentrates could be smelted in their raw state. After tabling of the products,

several batches of concentrate were smelted in a furnace to recover the gold, and it was found that high

levels of pyrite (up to 60%) caused gold splattering in the furnace. Roasting of the remaining concentrates

(Kingston Process Metallurgy Inc.) was thus required to reduce the amount of sulphur . The following

table shows the reduction in pyrite and sulphur before and after roasting of the ore.

Concentrate Product Estimated

pyrite

content

Sulphur

content

Mass

loss

Pre-Roasting (Non-Magnetic) 59.9% 32.0 % -

Post-Roasting (Non-Magnetic) 9.4% 3.5 % 31%

Pre-Roasting (Magnetic) 9.4 5.6 % -

Post Roasting (Magnetic) 6.0 5.0 % 16.4%

Future production using gravity methods will incorporate the relatively simple roasting processes that

greatly improves efficiency and cost of smelting.

4

Recoverable Gold

Final smelting of the concentrates and recovery of gold was undertaken at Northern Mining Analytical

Laboratory Inc. in Timmins, Ontario. The final products were sold at spot metal prices.

Conclusion and Analyses

The pilot plant generally confirmed the effectiveness of the principle of gravity separation on the SIF

Zone, but most importantly w as useful as a method to accurately ascertain the gold content of the SIF

Zone. Diamond drilling and panel sampling provide effective methods to ascertain tenors of gold

mineralization at Thor, but they are not definitive indicators of gold grade. Other factors such as

continuity, nugget effect and recovery can affect the ability of these commonly used exploration methods

when interpreting gold content.

Using the information from the gold pilot plant, minor changes to processing has the potential to improve

recoveries, namely by replacing the hammer mill with a ball mill that will produce finer grinding size and

liberate much more of the gold. The 10,000 tonne bulk sample application (currently under review by the

British Columbia Ministry of Energy and Mines) contains provisions for the application of a ball mill at

Thor on the remaining gold ore to test this concept.

Qualified Person

Exploration activities at Thor were overseen by John Gardiner (P. Geol.), who is a Qualified Person under

the meaning of Canadian National Instrument 43 -101. Met-Solve Laboratories (Langley, B.C.) completed

the metallurgical processing of the concentrates, and MS-Analytical (ISO 9001:2015) performed the

analytical work using 1 assay tonne samples to determine the gold content, and 32 element ICP for the

geochemistry. Kingston Process Metallurgy Inc. completed roasting of the concentrates and sulphur

analyses, and Northern Mining Analytical Laboratory (Timmins) completed the recovery of the gold.

About Taranis Resources Inc.

Taranis is an exploration company focused on the development of its 100% -owned Thor project in

southeast British Columbia . The Company’s mandate is to recognize mineral deposits early in the

exploration cycle that can be developed through intelligent exploration and business alliances. For

additional information on Taranis or its Thor project, please visit our website at

www.taranisresources.com.

Taranis currently has 64,113,067 shares is sued and outstanding ( 77,946,733 shares on a fully -diluted

basis).

TARANIS RESOURCES INC.

Per: John J. Gardiner (P. Geol.),

President and CEO

5

For further information contact:

John J. Gardiner

681 Conifer Lane

Estes Park, Colorado

80517

Phone: (303) 716-5922

Cell: (720) 209-3049

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS

DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY

OR ACCURACY OF THIS NEWS RELEASE.

This News Release may contain forward looking statements based on assumptions and judgments of manageme nt regarding

future events or results that may prove to be inaccurate as a result of factors beyond its control, and actual results may di ffer

materially from expected results.