Ombudsperson Outlines Plan and Timeline to Complete Bulk Sample Application at Thor
FOR IMMEDIATE RELEASE
Taranis Resources Inc.
681 Conifer Lane
Estes Park, Colorado
80517
www.taranisresources.com
Ombudsperson Outlines Plan and Timeline to Complete Bulk Sample
Application at Thor
Estes Park, Colorado, July 2, 2020 – Taranis Resources Inc. (“Taranis”) [TSX.V: TRO, OTCQB:
TNREF] is pleased to provide an update on its plan to process a 10,000 tonne bulk sample
application (“10KBSA”) on its 100% owned Thor property in British Columbia.
The B.C. Ombudsperson’s office has completed an investigation of the permitting process for
Taranis’ bulk 10KBSA. Taranis’ permitting team had identified numerous deficiencies that
affected and slowed the review of the 10KBSA application (News Release - March 16, 2020) and
filed a complaint to the office of the Ombudsperson that these deficiencies made the permitting
process fundamentally unfair and extreme, given the small size and exploratory nature of the bulk
sample. The Ombudsperson has concluded its investigation and has provided a comprehensive
summary therof, The Ombudsperson has outlined a series of steps to resolve the main complaint
issues, to which Energy, Mines and Petroleum Resources (“EMPR”) has agreed. Both EMPR and
Taranis are amenable to the specific pathway and timeline moving forward set forth in the
agreement (“the Resolution”).
Synopsis of Investigation & Resolution
As outlined in the Resolution, AllNorth Engineering will finalize the draft engineering site
drawings in close collaboration with EMPR (estimated 3 -4 weeks) that includes a water
management plan and tailings storage facility design . During this period, a designated EMPR
specialist will review the site plan, and propose any modifications in consultation wit h AllNorth.
Once this is completed, A llNorth will sign and seal the documents, and the site plan will be
submitted to the MDRC for comments. Low -risk changes will be dealt with through permit
conditions, and given adherence to the timetable, Taranis expect s the permit recommendation to
be sent from EMPR to the Statutory Decision Maker (“SDM”) this year . EMPR will try to
complete this work by August 31, 2020 in order to mitigate further delay.
Resultant EMPR Policy Changes
As a direct result of the Ombudperson’s Review and Analyses, EMPR will also make the following
Policy changes:
EMPR will finalize a draft policy and information bulletin “Permitting Custom and Pilot
Mill Operations” prepared June 20, 2016 and publish it to EMPR’s website.
EMPR will finalize the new Fact Sheet for bulk samples and publish it to EMPR’s website.
This Fact Sheet is currently in policy review and EMPR estimates that it will be finalized
by December 2020.
Taranis is pleased to have helped set the trend towards more transp arent, accessible, and fair
proceedings for bulk-sampling projects. Taranis believes that a better-defined process for moving
serious exploration projects closer to production will benefit British Columbia’s economy in this
2
difficult time. Furthermore, the added transparency will benefit all stakeholders who want to have
their input recognized throughout the development process. The oversight process will be
simplified at no expense to rigorous oversight, and so we are happy to see EMPR taking these
actions to improve the permitting process.
2020 Exploration at Thor
Taranis is currently investigating options for exploration of its Ridge Target at Thor. This target
was permitted in early February 2020, but has remained un-bonded until a Resolution was found
on the 10KBSA. This is an exciting exploration target developed based on years of exploration
work; Taranis believes there is potential to double the size of the existing deposit if the target
proves to have merit. Under the NoW Permit, a new road system needs to be constructed to the
area.
CEO Statement
John Gardiner, CEO of Taranis Resources Inc. comments “We wish to thank the Ombudsperson’s
office and EMPR for their efforts reviewing the Thor 10KBSA, and for formulating a number of
positive measures that pertain not only to Taranis, but to B.C.’s exploration and mining sector as
a whole.
Bulk samples are an industry mainstay which help to transition exploration projects into producing
mines that provide jobs a nd prosperity. The Thor 10KBSA will provide valuable hard scientific
data that is integral for completion of a Feasibility Study.
About Taranis Resources Inc.
For additional information on Taranis or its 100%-owned Thor project in British Columbia, visit
www.taranisresources.com
Taranis currently has 71,074,500 shares issued and outstanding ( 82,733,266 shares on a fully -
diluted basis).
TARANIS RESOURCES INC.
Per: John J. Gardiner (P. Geol.),
President and CEO
For further information contact:
John J. Gardiner
681 Conifer Lane
Estes Park, Colorado
80517
Phone: (303) 716-5922
Cell: (720) 209-3049
NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS
DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE
ADEQUACY OR ACCURACY OF THIS NEWS RELEASE.
3
This News Release may contain forward looking statements based on assumptions and judgments of management
regarding future events or results that may prove to be inaccurate as a result of factors beyond its control, and actual
results may differ materially from expected results.