Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

TNR.V ·

TNR Gold Update on NSR Royalty - Los Azules Copper, Gold & Silver Project – McEwen Mining Preliminary Economic Assessment

Royalties & Streams

NEWS RELEASE

TNR Gold Update on NSR Royalty - Los Azules Copper, Gold &

Silver Project – McEwen Mining Preliminary Economic

Assessment

Vancouver, British Columbia – June 26, 2023: TNR Gold Corp. (TSX-V: TNR) (“TNR”, “TNR Gold”

or the “Company”) is pleased to announce that McEwen Mining Inc. (“McEwen Mining”) has provided

an update on the Los Azules copper, gold and silver project in San Juan, Argentina. TNR holds a 0.4%

net smelter returns royalty (“NSR Royalty”) (of which 0.04% of the 0.4% NSR Royalty is held on behalf

of a shareholder) on the Los Azules Copper Project. The Los Azules project is held by McEwen Copper

Inc. (“McEwen Copper”), a subsidiary of McEwen Mining.

The news release issued by McEwen Mining stated:

“McEwen Mining Inc. (NYSE: MUX) (TSX: MUX) is pleased to provide results of the updated Preliminary Economic

Assessment (the “2023 PEA”) on the Los Azules Copper Project in San Juan Argentina (the “ Project”). Los Azules

is 100% owned by McEwen Copper Inc., which is 52% owned by McEwen Mining.

The PEA includes an updated independent mi neral resource estimate, which increased to 10.9 billion (B) lbs. Cu

(Indicated, grade 0.40%) and 26.7 B lbs. Cu (Inferred, grade 0.31%)

Base Case Highlights (Open-pit, Heap Leach, SX/EW, Nameplate capacity of 175 ktpa Cu Cathodes):

• Average annual copper ( Cu) cathode production of 401 million lbs. (182,100 tonnes) during the first 5

years of operation, and 322 million lbs. (145,850 tonnes) over the 27-year life of the mine (LOM)

• Total Cu recoverable to cathode of 8.68 billion lbs. (3.94 million tonnes), based on the LOM extraction of

mineralized material containing approximately 11.90 billion lbs. of total Cu (5.40 million tonnes), and

average copper recovery of 72.8%

• After-tax net present value ( NPV8%) of $2.659 billion (1), internal rate of return (IRR) of 21.2%, and a

payback period of 3.2 years – at $3.75 per lb. Cu.

• Initial capital expenditure of $2.462 billion, and a project capital intensity of $7.66 per lb. Cu ($16,880 per

tonne Cu)(2)

• Average C1 (2) cash costs of $1.07 per lb. Cu and all -in sustaining costs (2) of $1.64 per lb. Cu (AISC Margin

of 56%)(2)

• Average EBITDA(3) per year of $1.101 billion (Years 1-5) and $692 million (Years 6-27)

• Estimated carbon intensity of 670 kg CO2 equivalent per tonne of Cu (CO2-e/t Cu) (4) for Scope 1&2 GHG

Emissions, well below the industry average of 1,980kg CO2-e/t Cu (5). McEwen Copper’s goal at Los Azules

is to be carbon neutral by 2038, a target which is achievable through the use of emerging technologies and

offsets

#1120, 789 West Pender Street,

Vancouver, B.C.

V6C 1H2 , Canada

T: +1 (604) 229-8129

E-mail: [email protected]

Website: http://www.tnrgoldcorp.com

2

• Estimated site-wide water consumption of 137 liters per second (L/s) from years 1 to 10, increasing to 163

L/s from years 11 to 27, this compares to approximately 600 L/s (6) for a conventional mill producing copper

concentrate

• 1.182 billion tonnes of mineralized material placed on heap leach pad with in -situ total copper grade

of 0.46% and in-situ soluble copper grade of 0.31% (7)

The 2023 PEA Technical Report is prepared in accordance with the requirements set forth by Canadian National

Instrument 43 -101 (“ NI 43-101”) for the disclosure of material information and is intended to meet the

requirements of a Preliminary Economic Assessmen t (PEA) level of study and disclosure as defined in the

regulations and supporting reference documents. The effective date of the report is May 9, 2023. All currency

shown in this report is expressed in Q1 2023 United States Dollars unless otherwise noted.

This study is preliminary in nature and includes 26% inferred mineral resources in the conceptual mine plan.

Inferred mineral resources are considered too speculative geologically and in other technical aspects to enable

them to be categorized as mineral reserves under the standards set forth in NI 43 -101. There is no certainty that

the estimates in this PEA will be realized.

Study Contributors

The 2023 PEA technical report was prepared by Samuel Engineering Inc., with contributions from Knight Piésold

Consulting, Stantec Consulting International Ltd, McLennan Design, Whittle Consulting Pty Ltd, and SRK

Consulting UK Limited under the supervision of David Tyler, McEwen Copper Project Director. The 2023 PEA

technical report has been filed on SEDAR and on the Company’s website.

2023 PEA vs 2017 PEA

The base case development strategy selected in the 2023 PEA is distinctly different from that presented in the

prior PEA published in 2017. In 2017, the strategy was to construct a mine with a conventional mill and flotation

concentrator producing a concentrate for export to international smelters. The 2023 PEA proposes a heap leach

(leach) project using solvent extraction -electrowinning (SX/EW) to produce copper cathodes (LME Grade A) for

sale in Argentina or international markets. There are three principal reasons why the implementation strategy

was changed to leach in the 2023 PEA:

1. Environmental Footprint: Fresh water consumption is reduced by approximately 75% (150 vs. 600 L/s).

Electricity consumption is reduced by approximately 75% (57 vs. 230 MW). GHG emissions are reduced by

approximately 57% (670 vs. 1,560 CO2-e/t Cu Scope 1&2), with paths to further reductions by implementing

new technologies, with the goal of reaching net -zero carbon by 2038 with some offsets. Los Azules copper

cathodes will thus be attractive to end -users seeking to measurably reduce their u pstream environmental

impacts.

2. Reduced Permitting Risk: When proposing any mega -project development, it is vital to understand the local

standards and sensitivities around permitting. The Project uses technology (heap leach) that is in operation

in San Juan today. It also eliminates tailings and tailings dams, conserves scarce water resources, and reduces

the overall complexity of the mine, optimizing the permitting process.

3. Producing Cathodes: The leach process produces LME Grade A copper cathodes, which c an be directly used in

industry, including within Argentina reducing export taxes. This eliminates reliance on 3 rd party foreign

smelters for the processing of concentrates into refined copper products. It also eliminates significant GHG

emissions associated with transportation, and pollution associated with smelting. Counterparty and pricing

risks are also reduced.

McEwen views the progress made with the 2023 PEA towards reducing our environmental footprint and greater

environmental and social stewardship sets the Project apart from other potential mine developments, which

appropriately justifies certain economic trade -offs. The primary trade -offs to achieve these environmental

2

benefits is lower overall copper recovery, slightly higher unit costs, and less immediate cashflow due to extended

leach cycles. Nevertheless, the leach project remains very robust. Furthermore, McEwen believes that some of

these drawbacks can be mitigated by implementing developing technologies such as Nuton ™, discussed below.

Property Description

The Los Azules deposit is a classic Andean -style porphyry copper deposit. The large hydrothermal alteration

system is at least 5 kilometers (km) long and 4 km wide and is elongated in a north -northwest direction along a

major structural corridor. The Los Azules deposit area is approximately 4 km long by 2.2 km wide and lies within

the alteration zone. The limits of the mineralization along strike to the North and at depth have not yet been

defined. Primary or hypogene copper mineralization extends to at least 1,000 meters (m) below the surface. Near

surface, leached primary sulfides (mainly pyrite and chalcopyrite) were redeposited below the water table in a

sub-horizontal zone of supergene enrichment as secondary chalcocite and covellite. Hypogene bornite appears at

deeper levels together with chalcopyrite. Gold, silver, and molybdenum are present in small amounts, but copper

is the economic driver at Los Azules.

A New Vision and Approach

We developed regenerative guiding principles to reframe the approach to sustainable innovation and set forth

high-reaching goals that explore all facets of the mining processes considered for Los Azules. The project

development seeks to significantly reduce the environmental footprint of mining opera tions and their associated

GHG emissions by integrating the latest renewable and environmentally responsible technologies and processes.

The Project aims to obtain 100% of its energy from renewable sources (wind, hydro, and solar) in a combination

of offsite and onsite installations. The Project is also seeking to have long-term net positive impacts on the greater

Andean ecosystem, local flora and fauna, the lives of miners, and of the other citizens of nearby communities,

while contributing positively to the local and national economy of Argentina. Refer to the full 2023 PEA Technical

Report for more information about our regenerative approach.

Metal Price Assumption

The copper price use in the 2023 PEA was $3.75 per pound (except for the mineral resource estimate), in line with

analysts’ consensus projections for long-term copper prices that range between $3.25 and $4.25 per pound, with

a mean price of $3.75 per pound.

Study Highlights

This 2023 PEA development strategy begins with processing of resources associated with the oxide and supergene

copper mineralization in the near surface portion of the deposit using heap leaching methods. This approach

results in low average C1 costs of $1.07 per lb. Cu ( $0.88 per lb. in the first 8 years) and an attractive 3.2-

yearpayback period. Copper cathode production during the first 5 years of operation averages 401 million lbs.

per year (182 ktpa), and average over the 27-year LOM is 322 million lbs. per year (146 ktpa).

A nominal copper cathode production capacity of 385 million lbs. per year ( 175 ktpa) is met or exceeded during

the first 11 years of mining and was selected as the Base Case, with a smaller Alternative Case presented at 275

million lbs. per year (125 ktpa) of copper cathodes. The 2023 PEA financial model does not include potential future

development phases focused on primary copper mineralization found beneath the supergene copper layer but

some of these opportunities are discussed in the report, including the potential of deploying Nuton™ technologies.

The processing facility will function through to the completion of mining in Year 23 with stockpile reprocessing

and residual leaching operations to Year 27. Mining operations ramp up over the proposed mine life from

approximately 80 million total tonnes per year to 150 million tonnes per year through the life of the project as

copper grades decrease, and material movements increase.

2

Summary results for the Base Case and Alternative Case are provided in Table 1.

Table 1: Summary Results

Project Metric Units Base Case

175 ktpa

Alternative Case

125 ktpa

Mine Life Years 27 32

Tonnes Processed Billion tonnes 1.182 1.182

Tonnes Waste Mined Billion tonnes 1.366 1.366

Strip Ratio 1.16 1.16

Total Copper Grade % Cu 0.457% 0.457%

Soluble Copper Grade (CuSOL) % CuSOL 0.311% 0.311%

Copper Recovery (Total Copper) % 72.8% 72.8%

Soluble Copper Recovery(8) % 107% 107%

Copper Production (LOM avg.) tonnes/yr 145,820 123,060

Copper Production (Yr 1-5) tonnes/yr 182,100 136,100

Copper Production – cathode Cu ktonnes 3,938 3,938

Initial Capital Cost USD Millions $2,462 $2,153

Sustaining Capital Cost USD Millions $2,243 $2,351

Closure Costs USD Millions $180 $180

C1 Cost (Life of Mine) USD/lb Cu $1.07 $1.11

All-in Sustaining Costs (AISC) USD/lb Cu $1.64 $1.67

Before Taxes

Net Cumulative Cashflow USD Millions $15,820 $15,679

Internal Rate of Return (IRR) % 26.5% 22.9%

Net Present Value (NPV) @ 8% USD Millions $4,436 $3,278

After Taxes

Net Cumulative Cashflow USD Millions $10,240 $10,159

Internal Rate of Return (IRR) % 21.2% 18.4%

Net Present Value (NPV) @ 8% USD Millions $2,659 $1,929

Pay Back Period Years 3.2 3.4

Sensitivity Analysis

The Base Case project economics are reasonably robust (>15% post -tax IRR) at a copper price above $3.00 per

pound and are similarly resistant to an increase in LOM capital expenditure of up to 30% and an increase in

operating expenses of up to 60%. Table 2 below shows the sensitivity of the Base Case project economics to the

Copper Price (+/- 20%) on a post-tax basis. The project NPV8% is breakeven at a copper price of $2.34 per pound.

Tables 2: Base Case (175 ktpa) Copper Price Sensitivity

Sensitivity (%)

Metal Pricing Post-Tax

Copper Price NPV IRR Payback

$ Cu/lb $M % Years

-20% $3.00 $1,277 15% 5.48

-15% $3.19 $1,624 17% 4.84

-10% $3.38 $1,969 18% 4.24

-5% $3.56 $2,314 20% 3.68

0% $3.75 $2,659 21% 3.18

5% $3.94 $3,003 23% 2.90

2

10% $4.13 $3,346 24% 2.75

15% $4.31 $3,689 25% 2.61

20% $4.50 $4,032 27% 2.49

Table 3 below show the sensitivity of the Base Case project economics to initial and sustaining capital

expenditure escalation on a post-tax basis.

Table 3: Base Case (175 ktpa) Initial & Sustaining CAPEX Sensitivity

Sensitivity

(%)

Post-Tax

NPV IRR Payback

$M % Years

0 $2,597 21% 3.18

5% $2,484 20% 3.54

10% $2,372 19% 3.94

15% $2,260 18% 4.25

20% $2,148 17% 4.56

25% $2,036 17% 4.88

Table 4 below show the sensitivity of the Base Case project economics to operating expenditure escalation on a

post-tax basis.

Table 4: Base Case (175 ktpa) OPEX Sensitivity

Sensitivity

(%)

Post-Tax

NPV IRR Payback

$M % Years

0 $2,597 21% 3.18

5% $2,496 21% 3.28

10% $2,396 20% 3.38

15% $2,295 20% 3.49

20% $2,195 19% 3.62

25% $2,095 19% 3.75

Capital Costs Estimates

The Project includes the development of an open pit mine with muti -stage crushing and screening, a heap leach

pad, and a copper solvent extraction -electrowinning (SX/EW) facility with a nominal production capacity of 175

ktpa copper cathodes. There is also a sulfuric acid plant and other associated infrastructure to support the

operations. Initial capital infrastructure for the Base Case includes the following facilities:

• Mine development and associated infrastructure

• Coarse rock storage and handling (crushing, conveying, agglomeration)

• Heap leach pads and conveyor stacking systems

• SX/EW facility

• Sulfuric acid plant

• On-site utilities and ancillary facilities including a construction camp

• Off-site infrastructure: power transmission line (outsourced), access roads, and permanent camp

2

The project initial capital costs are based on budgetary quotes for major equipment, recent in -house cost

information and installation factors, and regional contractor inputs and facilities obtained between Q4 2022 and

Q1 2023. T he capital costs for the project are summarized in Table 5 and should be viewed with the level of

accuracy expected for a preliminary analysis.

The approximate construction cost of the 132 kV power supply line to site is $155 million and has not been

included in the capital estimate because it is assumed that YPF Luz, a large Argentinean power utility company,

will be constructing the line at their expenses pursuant to a long -term renewable power purchase agreement.

Table 5: Initial Capital Costs by Case

Capital Cost Base Case Alternative Case

175k tpa Cu ($) 125k tpa Cu ($)

Mining $65,600,000 $65,600,000

Ore Storage & Handling $234,500,000 $192,500,000

Heap Leaching $158,500,000 $142,100,000

SX/EW Facilities $250,400,000 $167,700,000

Acid Plant $94,900,000 $79,900,000

Ancillary Facilities $23,300,000 $23,300,000

Site Development & Yard Utilities $126,300,000 $112,200,000

Off-Sites $167,400,000 $167,400,000

Total Direct Costs $ 1,120,900,000 $ 950,700,000

Common Indirect Costs $ 379,200,000 $ 323,800,000

Owners Costs $ 466,700,000 $ 455,900,000

Subtotal $ 1,966,800,000 $ 1,730,400,000

Contingency $495,000,000 $423,100,000

Total Capital Cost $ 2,461,800,000 $ 2,153,500,000

Operating Costs Estimates

Table 6 summarizes the LOM project operating costs per tonne of material processed and per pound of copper

produced.

Table 6: LOM Cash Costs

Base Case

175 ktpa

Alternative Case

125 ktpa

Description LOM

Cost/tonne ($)

LOM

Cost/lb. ($)

LOM

Cost/tonne ($)

LOM

Cost/lb. ($)

Mining 4.14 0.56 4.27 0.57

Processing 2.73 0.37 2.74 0.37

General & Administrative 0.94 0.13 1.11 0.15

Selling Expenses 0.15 0.02 0.15 0.02

LOM C1 Costs 7.96 1.07 8.27 1.11

Royalties and Taxes

The 2023 PEA includes all government and private royalties on production, export taxes, as well as income taxes

and banking taxes. Royalty calculations vary, however royalties and retentions based on net smelter return (NSR)

total approximately 9.2%. In the financial model it was assumed that 10,000 tonnes per year of copper cathodes

are sold within Argentina and consequently they are not subject to export taxes. 95% of VAT is assumed to be

recoverable after two years. A 0.2% portion of the bank tax is recoverable in the following year.

2

Table 7: Royalties and Taxes (All Cases)

Income Tax Argentine Corporate Income % Profit 35 %

VAT Taxes Argentine Value Added Tax % on Capital 10.5 %

% on Operating 21 %

Royalties

San Juan Province % “Mine Mouth” 3 %

TNR Royalty % NSR 0.4 %

McEwen Mining Royalty % NSR 1.25 %

Export Retentions Argentine Export Retention % NSR 4.5 %

Bank Tax Debit and Credit Bank Tax % on Operating 1.2 %

Nuton Opportunity

Nuton LLC is a copper heap leaching technology venture of Rio Tinto that became a strategic partner in 2022. Its

Nuton™ suite of proprietary technologies provide opportunities to leach both primary and secondary copper

sulfides, providing significant opportunity to optimize the mine plan and the overall mining and processing

operations. In addition, Nuton ™ provides significant other benefits, such as lower overall energy consumption,

allowing earlier conversion to renewable energy sources, and lower water consumption than conventional sulfide

mineralization treatment processes.

Based on preliminary scoping testing, Nuton™ technologies offer the potential for copper recoveries of more than

80% from predominantly chalcopyrite, depending on the specific mineralogy make-up of the mineral resource. At

Los Azules, Nuton ™ has the potential to economically process the large primary sulfide copper resource as an

alternative to a concentrator, with low incremental capital following the oxide and supe rgene leach, no tailings

requirement, and a smaller environmental footprint. Producing copper cathode with Nuton™ on-site also has the

advantage of simplifying outbound logistics for copper concentrates and offers a finished product to the domestic

and international market.

The outcomes modelled using the Nuton proprietary computational fluid dynamics model, are very encouraging

and indicate that unoptimized copper recovery to cathode from primary material should range from 73% to 79%.

Furthermore, Nuton r ecovery from secondary material is high, ranging from 80% to 86%. This could provide a

significant opportunity to optimize the mine plan and the need for selective mining, as simultaneous stacking of

both secondary and primary mineralization will not impac t on the copper recovery from either material type.

Based on the current resource estimate, this could have a significant positive impact on the expected life of the

mine, without significantly increasing the initial capital investment required.

Nuton is currently validating modelled data with column leach tests. Column leaching of the composite samples

at their facilities is underway and expected to be completed in Q1 2024. Validation of the modelled results could

be obtained much sooner, depending on the trends provided by the actual column leach results.

McEwen Copper does not currently have a commercial arrangement with Nuton that enables it to deploy their

technologies at Los Azules , and there is no guarantee that such an agreement will come to fruition, however

McEwen Copper and Nuton intend to work in good faith toward such an arrangement. The results in Table 8

below assume that Nuton ™ technologies are implemented without includin g costs associated with technology

licensing or some other commercial cost structure.

Table 8: Nuton™ Opportunity Economic Summaries

Project Metric Units Base Case-Nuton

175 ktpa

Mine Life Yr 39

Strip Ratio 1.43

Tonnes Processed Billion tonnes 1.737

Copper Grade (Total) % Cu 0.409

2

Copper Production – cathode Cu ktonnes 6,411

Initial Capital Cost USD Millions $2,444

Sustaining Capital Cost USD Millions $2,793

C1 Cost (Life of Mine) USD/lb Cu $1.04

All-in Sustaining Costs (AISC) USD/lb Cu $1.54

After Taxes

Internal Rate of Return (IRR) % 23.9%

Net Present Value (NPV) @ 8% USD Millions $3,701

Pay Back Period Yr 2.7

Project Development Schedule

The Gantt chart below presents a conceptual project development timeline based on regional contractor inputs

and long-lead equipment and materials delivery assumptions provided by vendors. The schedule assumes that

the feasibility study work is completed by the end of 2024, finalization o f the environmental permitting process

(IIA/DIA) and other necessary permits to begin work are completed during the proposed feasibility study and

preliminary timeframe and financing are in place to achieve the scheduled milestones. Following this conceptu al

schedule, the SX/EW plant start-up could occur in Q1 2029.