Trilogy Metals Drills 16.4 metres of 5.3% Copper and 0.21% Cobalt

and Provides Corporate and Project Updates

August 23, 2018 - Vancouver, British Columbia – Trilogy Metals Inc. (TSX/NYSE

American: TMQ) (“Trilogy Metals” or the “Company”) is pleased to provide an update on its

summer activities at the Upper Kobuk Mineral Projects (“UKMP”) located within the Ambler

Mining District of northwestern Alaska. The Company is working on several fronts to advance

both the Arctic and Bornite Projects. All amounts are in US dollars.

Bornite Project

Initial Bornite Drilling Results

As of August 19 th, the Company has completed five drill holes comprising a total of 5,267

metres at Bornite. The objective of the 2018 drilling campaign is to infill and expand the

currently defined open pit and underground mineral resources . Mineralization occurs as a

series of “Reefs” hosted by both the Upper and Lower Bornite Carbonate sequences separated

by a generally unmineralized phyllite unit. The Cu-Co mineralization at Bornite occurs in three

distinct carbonate zones, the Upper Reef, the Lower Reef, and the South Reef. All three zones

are being drill tested this year.

The Company has received , on an expedited basis, initial assay results from drill hole RC18 -

0247 which is designed to test extensions of high-grade copper mineralization at depth, along

the South Reef trend . At a copper cut -off grade of 1 .5%, RC18-0247 contains an interval of

16.4 metres grading 5.34% copper and 0.21% cobalt . The mineralized interval was

intersected at a depth of 791.9 metres (total mineralized interval was between 7 91.9 metres

to 808. 3 metres). The high -grade mineralized zone in RC18 -0247 consists of massive

chalcopyrite occurring as breccia infill with intergrown pyrite and within dolomite-quartz veins

as centimetre scale blebs. Bornite and chalcocite mineralization replace chalcopyrite within

the breccia matrix in the highest-grade intervals from 795. 9 to 799.3 metres and 803.9 to

808.3 metres . Large (4 to 10 centimetres wide) carbonate/quartz veins also host a

chalcopyrite-bornite-chalcocite mineral assemblage. Massive cobaltiferous pyrite occurs as 10

to 20 centimetre-wide stringers between the two higher grade zones. This mineralized interval

is within the Lower Reef. Figure 1 and Table 1 shows the location of RC18-0247 while Figure 2

is a cross-section showing the location of RC18-0247 relative to other holes on the section.

Additional drilling results from the upper portion of the mineralized interval of this drill hole

will be made available as they are rece ived by the Company along with results for other drill

holes that have been completed and are in the laboratory.

Rick Van Nieuwenhuyse, President and CEO commented : ”We are pleased to report that the

high-grade copper and cobalt zones demonstrate continuity and continue down dip. We look

forward to reporting additional results as they become available”.

TSX/NYSE American

Symbol: TMQ

2

Trust | Respect | Integrity

Table 1 – Location of Drill Hole RC18-0247 at the Bornite Project

Drill hole East (m) North (m) Elev. (m) Azimuth Dip

RC18-0247 590524 7440658 312 206 80

Expansion of Bornite Drilling Program

The Company is also pleased to announce that its partner, South32 Limited (ASX, LSE, JSE:

S32; ADR: SOUHY) (“South32”), has agreed to increase its contribution to this year’s Bornite

drilling program by funding an additional $800,000 to the Company. The additional funding

will reduce South32’s 2019 minimum exploration budget commitment of $10 million to $9.2

million. The $800,000 is expected to allow the Company to add two drill rigs that are expected

to complete four holes totaling 1,500 to 2,100 metres.

Figure 1. Location of 2018 Bornite Drilling

The original program envisaged an 8,000 metre exploration program of in-fill and expansion

drilling to better define the high -grade copper resources at the Bornite Project Five drills are

3

Trust | Respect | Integrity

expected to be in operation for at least a month with the drilling campaign extendin g into the

middle of September.

Updated Bornite Resource Estimate

Once the drilling program is completed, the Company intends to move forward on an updated

copper-cobalt resource estimate at the Bornite Project. The updated resource estimate is

expected to incorporate the infill and expansion drilling that has been carried out during the

2017-2018 exploration campaigns. The resource estimate is expected to be completed in the

first half of 2019.

Figure 2. Cross-section RC18-247

Bornite Metallurgical Program

On June 5th, 2018 the Company announced a n initial cobalt resource estimate for the Bornite

Project of 77 million pounds of inferred cobalt resources (see Table s 2 and 3 for details

including grade ). An updated technical report entitled “NI 43 -101 Technical Report on the

Bornite Project, Northwest Alaska, USA” including the inferred cobalt resources was filed by

the Company on July 20, 2018, and is available on the Company’s website at

www.trilogymetals.com and on the Company’s profile at www.sedar.com and www.sec.gov.

With the completion this resource estimate the Company has now embarked on a metallurgical

study to investigate various methods of recovering both the copper and cobalt at Bornite.

Initial results from the metallurgical program are expected to be made available to the

Company in Q1, 2019.

4

Trust | Respect | Integrity

Initial Bornite Preliminary Economic Assessment

Once the updated resource estimate and metallurgical results are made available, the

Company expects to move forward on a Preliminary Economic Assessment (“PEA”) on the

Bornite Project. The PEA is expected t o investigate the viability of a combined open pit and

underground mining operation. The PEA is expected to be completed by the end of the second

quarter of 2019.

Table 2: Estimate of Copper Mineral Resources for the Bornite Deposit

Type

Cut-off

(Cu%)

Tonnes

(million)

Average Grade

Cu (%)

Contained Metal

Cu (Mlbs)

In-Pit 0.5 40.5 1.02 913

Total Indicated 40.5 1.02 913

In-Pit 0.5 84.1 0.95 1,768

Below-Pit 1.5 57.8 2.89 3,683

Total Inferred 141.9 1.74 5,450

(1) Resources stated as contained within a pit shell developed using a metal price of US$3.00/lb

Cu, mining costs of US$2.00/tonne, milling costs of US$11/tonne, G&A cost of US$5.00/tonne,

87% metallurgical recoveries and an average pit slope of 43 degrees.

(2) Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

There is no certainty that all or any part of the Mineral Resources will be converted into Mineral

Reserves.

(3) It is reasonably expected that the majority of Inferred mineral resources could be upgraded to

Indicated mineral resources with additional exploration.

Table 3: Estimate of Inferred Cobalt Mineral Resources for the Bornite Deposit

Type Cut-off

(Cu%)

Tonnes

(million)

Average Grade

Co (%)

Contained Metal

Co (Mlbs)

In-Pit 0.5 124.6 0.017 45

Below-Pit 1.5 57.8 0.025 32

Total Inferred 182.4 0.019 77

(1) Resources stated as contained within a pit shell developed using a metal price of US$3.00/lb

Cu, mining costs of US$2.00/tonne, milling costs of US$11/tonne, G&A cost of US$5.00/tonne,

87% metallurgical recoveries and an average pit slope of 43 degrees.

(2) Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

There is no certainty that all or any part of the Mineral Resources will be converted into Mineral

Reserves.

(3) It is reasonably expected that the majority of Inferred mineral resources could be upgraded to

Indicated mineral resources with additional exploration.

5

Trust | Respect | Integrity

Arctic Project

The Company has recently completed its summer activities at the Arctic Project, which include

592 metres in 24 holes of geotechnical/hydrological drilling which is providing geotechnical and

hydrological information at the proposed tailings dam, waste rock facility and grinding mill

locations. The Company intends to continue with baseline environmental studies which

includes hydrology, wetlands delineation, meteorological and archeology data collection.

Arctic Ore Sorting Program

Ore sorting test work at the Steinert Labs facility in Kentucky, USA has been completed. Early

indications are that the application of ore sorting technology could improve the head grades of

material being processed at the proposed Arctic grinding mill by eliminating waste rock . The

recent pre-feasibility study estimated 20 -30% dilution at the mine face within the proposed

Arctic pit. Reducing the dilution to 10-20% may result in an improvement of the economics of

the Arctic Project. The Company expects to evaluate the potential for capital and operating

cost savings based on these initial results from the ore sorting test work before the end of the

end of the year.

Permitting of the Arctic Mine

The Company is continuing with its baseline environmental work and permitting application

work with a view of submitting its 404 Wetland Permit application to the U.S. Army Corps of

Engineers (“USACE”) during the first half of 2019. The USACE is expected to be the lead agency

for the permitting of the Arctic Project. Given that the Arctic Project is located on State and

private lands owned by NANA Regional Corporation, Inc. (no Federal lands) the Comp any

estimates a two to three-year permitting timeline for the project.

Ambler Mining District Industrial Access Project (“AMDIAP”)

On July 9th, 2018 at a joint session in Barrow, Alaska the Northwest Arctic Borough (“NWAB”)

Assembly and the North Slope Borough (“NSB”) Assembly, together, unanimously voted to

support evaluation of an industrial road in the Ambler Mining District which is located within

the NWAB.

Specifically, the two Boroughs Assemblies, which are the local g overnments in northern and

northwest Alaska, have jointly approved the following resolutions:

• Support for the Alaska Industrial Development Export Agency’s (“AIDEA”) evaluation of

an industrial road in the Ambler Mining District; and

• That food security and public benefit be considered a priority by evaluating agencies

and that public engagement and consultation be meaningfully incorporated into a final

decision; and

• That the NWAB shall commit to continuing its role as a cooperating agency; and

• That both Boroughs will examine ways to maximize community benefit and economic

development opportunities while undertaking an analysis of impacts and ways to

minimize or mitigate any adverse effects; and

• That both Boroughs shall explore opportunities for co-investment and ownership in the

Ambler Mining District Industrial Access Project (AMDIAP).

Mr. Nasruk Carl Weisner, the Assembly President for the NWAB stated, “The Northwest Arctic

Borough and North Slope Borough governments represent home -rule governments of the

people of northern Alaska. We support resource development in our Boroughs that respects

6

Trust | Respect | Integrity

the Inũpiat culture and protects our subsistence resources and the environment. We support

completing the Environmental Impact Assessment Statement on the Ambler Access Road.”

Background: Ambler Mining District Industrial Access Project

As announced in the Company’s press release dated May 29, 2018, AIDEA submitted permit

applications for the AMDIAP, a proposal for the construction and operation of a 211-mile (340

Km) long all -season controlled-access industrial road connecting the Ambler Mining District

with the Dalton Highway.

On April 30, 2018, the Bureau of Land Management (“BLM”) released the Ambler Road

Environmental Impact Statement Scoping Summary Report (s ee BLM’s website at

https://BLM's AMDIAP Website). Permitting of the AMDIAP under the National Environmental

Policy Act (“NEPA”) EIS process has now concluded the “Scoping Phase” of permitting and has

moved to the “Draft EIS Phase”. Per the BLM’s website, the Draft EIS is scheduled for the end

of March 2019 (Figure 1).

Approximately 20 miles of the proposed AMDIAP road crosses lands managed by the National

Park Service (“NPS”). The Alaska National Interest Lands Conservation Act (“ANILCA”) requires

that right-of-way access be permitted across NPS lands for this project. In addition, ANILCA

directs that an Environmental and Economic Analysis (“EEA”) be prepared for the right-of-way

across NPS lands in order to: 1) determine a preferred road alignment, and 2) develop

appropriate terms and conditions for the right-of-way permit. Two alternative routes are being

considered: North Route and South Route. The NPS has published a Project Schedule indicating

completion of the Final EEA by the end of 2018 on their website at

https://www.nps.gov/gaar/learn/management/ambler-row.htm.

Figure 3. Timeline of Permitting for the Ambler Mining District Industrial Access

Project

7

Trust | Respect | Integrity

QA/QC Program

The drill program and sampling protocol are managed by qualified persons employed by the

Company. Diamond drill holes were typically collared at PQ or HQ diameter drill core and

reduced to HQ and NQ diameter during the drilling process. Samples were collected using a

0.2-metre minimum length, 2.5-metre maximum length and 1.7-metre average sample length.

Drill core recovery averaged 9 0% overall and 94% wi thin the prospective lithologies . Three

quality control samples (one blank, one standard and one duplicate) were inserted into each

batch of 20 samples. The drill core was sawn, with half sent to ALS Minerals in Fairbanks for

sample preparation and the sam ple pulps forwarded to ALS's North Vancouver facility for

analysis. ALS Minerals in North Vancouver, B.C., Canada, is a facility certified as ISO

9001:2008 and accredited to ISO / IEC 17025:2005 from the Standards Council of Canada.

The Company will submit 5% of the assay intervals from prospective lithologies to an

independent check assay lab.

Qualified Persons

Andrew W. West, Certified Professional Geologist, Exploration Manager for Trilogy Metals Inc.,

is a Qualified Person as defined by National Instrument 43-101. Mr. West has reviewed the

technical information in this news release and approves the disclosure contained herein.

About Trilogy Metals

Trilogy Metals Inc. is a metals exploration and development company focused on exploring and

developing the Ambler mining district located in northwestern Alaska. It is one of the richest

and most-prospective known copper-dominant districts located in one of the safest geopolitical

jurisdictions in the world. It hosts world -class polymetallic volcanogenic massive sulphide

(“VMS”) deposits that contain copper, zinc, lead, gold and silver, and carbonate replacement

deposits which have been found to host high -grade copper and cobalt mineralization.

Exploration efforts have been focused on two deposits in the Ambler mining district - the Arctic

VMS deposit and the Bornite carbonate replacement deposit. Both deposits are located within

the Company's land package that spans approximately 143,000 hectares. The Company has

an agreement with NANA Regional Corporation, Inc., a Regional Alaska Native Corporation that

provides a framework for the exploration and potential development of the Ambler mining

district in cooperation with local communities. Our vision is to develop the Ambler mining

district into a premier North American copper producer.

Company Contact

Patrick Donnelly

Vice President, Corporate Communications & Development

[email protected]

604-630-3569

604-638-8088 or 1-855-638-8088

# # #

8

Trust | Respect | Integrity

Cautionary Note Regarding Forward-Looking Statements

This press release includes certain "forward -looking information” and "forward -looking

statements” (collectively "forward -looking statements”) within the meaning of applicable

Canadian and United States securities legislation including the United States Private Securities

Litigation Reform Act of 1995. All statements, other than statements of historical fact, included

herein, including, without limitation, further drilling activity, the potential advancement of the

AMDIAP, the timing and the filing of updated reports on the Company’s projects, the future

price of copper, the estimation of mineral reserves and mineral resources, the realization of

mineral reserve and mineral resource estimates, the timing and amount of estimated future

production, costs of production, capital expenditures, costs and timing of the development of

projects, the likelihood and timing of the AMDIAP, the potential future development of Bornite,

the future operating or financial performance of the Company, planned expenditures and the

anticipated activity at the UKMP Projects , are forward-looking statements. The assay results

from drill hole RC18-0247 should not be considered representative of other drilling results for

the 2018 drilling campaign. Forward-looking statements are frequently, but not always,

identified by words such as "expects”, "anticipates”, "believes”, "intends”, "estimates”,

"potential”, "possible”, and similar expressions, or statements that events, conditions, or

results "will”, "may”, "could”, or "should” occur or be achieved. These forward -looking

statements may include statements regarding perceived merit of properties; exploration plans

and budgets; mineral reserves and resource estimates; work programs; capital expenditures;

timelines; strategic plans; market prices for precious and base metals; or other statements

that are not statements of fact. Forward -looking statements involve various risks and

uncertainties. There can be no assurance that such statements will prove to b e accurate, and

actual results and future events could differ materially from those anticipated in such

statements. Important factors that could cause actual results to differ materially from the

Company's expectations include the uncertainties involving success of exploration,

development and mining activities, permitting timelines, requirements for additional capital,

government regulation of mining operations, environmental risks, unanticipated reclamation

expenses; mineral reserve and resource estimates and the assumptions upon which they are

based; assumptions and discount rates being appropriately applied to the PFS; our

assumptions with respect to the likelihood and timing of the AMDIAP; capital estimates; prices

for energy inputs, labour, materials, supplies and services the interpretation of drill results,

the need for additional financing to explore and develop properties and availability of financing

in the debt and capital markets; uncertainties involved in the interpretation of drilling results

and geological tests and the estimation of reserves and resources; the need for cooperation of

government agencies and native groups in the development and operation of properties as

well as the construction of the access road ; the need to obtain permits an d governmental

approvals; risks of construction and mining projects such as accidents, equipment breakdowns,

bad weather, non -compliance with environmental and permit requirements, unanticipated

variation in geological structures, metal grades or recovery rates; unexpected cost increases,

which could include significant increases in estimated capital and operating costs; fluctuations

in metal prices and currency exchange rates; and other risks and uncertainties disclosed in the

Company’s Annual Report on Fo rm 10-K for the year ended November 30, 201 7 filed with

Canadian securities regulatory authorities and with the United States Securities and Exchange

Commission and in other Company reports and documents filed with applicable securities

regulatory authorities from time to time. The Company's forward-looking statements reflect

the beliefs, opinions and projections on the date the statements are made. The Company

assumes no obligation to update the forward -looking statements or beliefs, opinions,

projections, or other factors, should they change, except as required by law.