Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

TLG.TO ·

Troilus Reports Updated Technical Report Following Completion of Basic Engineering, Delivering After-Tax US$3.2 Billion NPV5%, 22% IRR, and Cashflow of US$6.9 Billion at Base Case Gold Price of US $3,600/oz Approximately 95,000 engineering hours and market validation of ~90% of pricing underpin AACE

Technical Reports (NI 43-101) Economic Studies

Troilus Reports Updated Technical Report Following Completion of Basic Engineering,

Delivering After-Tax US$3.2 Billion NPV5%, 22% IRR, and Cashflow of US$6.9 Billion at Base

Case Gold Price of US $3,600/oz

Approximately 95,000 engineering hours and market validation of ~90% of pricing underpin AACE Class 3

estimate accuracy across the full Project scope

September 9, 2026, Montreal, Quebec – Troilus Mining Corp. (“Troilus” or the “Company”) (TSX: TLG;

OTCQX: CHXMF; FSE: CM5), is pleased to report the results of an updated NI 43-101 Technical Report (the

“Technical Report”) for the gold-copper Troilus Project located in northcentral Quebec, Canada. Based on

the Company’s completed Basic Engineering program, the Technical Report confirms and improves upon

the strong economic fundamentals established in the May 2024 Feasibility Study (“2024 FS”), while

extending the Project’s mine life, strengthening its gold and copper production profile, and incorporating

a substantially more advanced level of engineering, design and cost definition.

The Technical Report outlines a large-scale, approximately 26-year mine life with an after-tax NPV5% of

$3.2 billion, after-tax IRR of 22% and 3.6-year payback period. Life-of-mine payable production is

estimated at 5.63 million ounces of gold, 472 million pounds of copper and 10.88 million ounces of silver,

reinforcing Troilus’ position as one of Canada’s largest undeveloped gold-copper projects.

Importantly, the updated capital estimate has been developed following completion of Basic Engineering,

representing approximately 95,000 engineering hours and C$21.3 million in engineering fees.

Approximately 90% of the pricing inputs have been validated against current market quotations, including

firm pricing for key equipment. The resulting estimate meets AACE Class 3 accuracy standards (+15%/-

10%) across the full Project scope, providing a substantially more advanced and higher-confidence basis

for project financing, procurement and execution planning.

All dollar values are in United States dollars unless stated otherwise.

Technical Report Highlights

Compelling Economics and Significant Cash Flow Generation

▪ Base case before-tax NPV(5%) of US$5.3 billion and IRR of 27%, based on long-term metal prices of

US$3,600/oz gold, US$5.00/lb copper and US$50.00/oz silver

▪ Approximately US$11.1 billion of cumulative before-tax cash flow over the life of mine

▪ Approximately US$4.2 billion in taxes paid over the life of mine, including Quebec mining tax,

Quebec income tax and Federal income tax

▪ Base case after-tax NPV(5%) of US$3.2 billion, IRR of 22% and 3.6-year payback, based on long-term

metal prices of US$3,600/oz gold, US$5.00/lb copper and US$50.00/oz silver

▪ Approximately US$6.9 billion of cumulative after-tax cash flow over the life of mine

▪ Strong leverage to metal prices: at US$4,500/oz gold, after-tax NPV(5%) increases to approximately

US$4.7 billion, IRR to 28%, with payback reduced to approximately 3.0 years

Large-Scale, Long-Life Gold-Copper Operation

▪ Approximately 26-year mine life based on a conventional open-pit operation and 50,000 tpd

nameplate processing rate

▪ Life-of-mine payable production of 5.63 million ounces of gold, 472 million pounds of copper and

10.88 million ounces of silver

▪ 304,000 payable gold-equivalent ounces of average annual production from 2031–2040, with peak

annual production of approximately 557,000 payable gold-equivalent ounces in 2042

▪ Average annual payable production during the 21-year active mining period of approximately

251,000 ounces of gold, 20.1 million pounds of copper and 466,000 ounces of silver

▪ Life-of-mine strip ratio improves to 2.4:1, compared with 3.1:1 in the 2024 Feasibility Study

Updated Capital and Competitive Cost Profile

▪ Initial capital of approximately US$1.428 billion1, reflecting a substantially more advanced and fully

defined Project design, supported by approximately 95,000 engineering hours, ~90% market-

validated pricing and AACE Class 3 (+15%/-10%) estimate accuracy across the full Project scope.

▪ Life-of-mine operating costs of approximately US$19.21/t milled ore

▪ Life-of-mine AISC of approximately US$1,340 per payable gold ounce, net of copper and silver

credits

Expanded Reserve Base with Further Upside

▪ Mine plan underpinned by a Mineral Reserve estimate of 478 million tonnes grading 0.44 g/t gold,

0.05% copper and 0.92 g/t silver, comprising 6.7 million contained ounces of gold, 568 million

contained pounds of copper and 14.2 million contained ounces of silver

▪ Reserve tonnage increased approximately 26% compared with the 2024 Feasibility Study

▪ Mineral Reserve estimate effective December 31, 2025, excluding drilling results announced during

2026 and preserving potential future resource growth and mine-plan optimization upside

▪ Numerous near-mine and regional targets provide additional opportunities for resource growth

and new discoveries beyond the current mine plan

▪ Ongoing infill and pit optimization drilling targeting inferred material and historically unsampled

intervals

Justin Reid, CEO of Troilus, commented, “The results presented in our updated technical report reinforce

Troilus’ position as one of the most compelling large-scale gold-copper development projects in North

America. The combination of a US$3.2 billion after-tax NPV, 22% IRR, 3.6-year payback and approximately

26-year mine life demonstrates the scale, longevity and economic strength of the Project, particularly

relative to an initial capital requirement of approximately US$1.43 billion. Just as importantly, these results

are now supported by a substantially greater level of engineering and cost definition than at the 2024

Feasibility Study stage. Basic Engineering has been completed across the full Project scope, procurement

has advanced materially, and the vast majority of pricing inputs have been validated against current

1 The initial capital cost estimate of US$1.428 billion includes capitalized operating costs and capitalized revenues

and excludes sunk costs planned to be incurred through Q1 2027.

market quotations. This gives us significantly greater confidence in the Project design, cost basis and

execution strategy as we advance through Detailed Engineering. The Project itself has also improved, with

a longer mine life, a lower strip ratio and approximately 21% higher life-of-mine payable copper production

compared with the 2024 Feasibility Study. With engineering, procurement, permitting and project

financing advancing in parallel, Troilus is moving decisively from study and design toward execution and a

future construction decision.”

Table 1: Gold-Copper Troilus Project Technical Report Summary

Technical Report Summary

Units Values

Base Case Assumptions

Gold Price (Long Term) USD/oz 3,600

Copper Price (Long Term) USD/lb 5

Silver Price (Long Term) USD/oz 50

Exchange Rate CAD:USD 1.37

Discount Rate % 5

Production

Mine Life Years 26

Total Mined and Milled M Tonnes 478.2

Strip Ratio W:O 2.4:1

Daily Mill Throughput tpd 50,000

Annual Mill Throughput M Tonnes/year 18.3

Gold Grade g/t 0.44

Copper Grade (%) 0.05

Silver Grade g/t 0.92

Total Payable Gold Production koz 5,631

Average Annual Payable Gold Production (Yrs 1-21)* koz/year 251

Total Payable Copper Production Mlbs 472

Average annual Payable Copper Production (Yrs 1-21)* Mlbs/year 20.1

Total Payable Silver Production koz 10,880

Average Annual Payable Silver in Gold doré (Yrs 1-21)* koz/year 466

Average Concentrate Production (Yrs 1 - 21)* DMT/year 63,022

Average Gold Grade g/t 79.3

Average Copper Grade (%) 15.5%

Average Silver Grade g/t 248

Operating Costs (LOM)

Open Pit Mine Operating Cost $/t milled 11.25

Process Operating Cost $/t milled 5.55

General and Administration Cost $/t milled 2.40

Royalties (% of NSR) 1.0

Total Operating Costs $/t Mill Feed 19.21

All-in-Sustaining Cost (AISC**) (after metal credits) $/oz 1,340

Capital Costs

Initial Capital Cost*** $M 1,428

Sustaining Capital Cost $M 198

Reclamation and Closure Costs $M 52.4

Financial Analysis Summary

Pre-Tax Cash Flow $M 11,129

Pre-Tax NPV(5%) $M 5,266

Pre-Tax IRR % 27

Pre-Tax Payback Period Years 3.3

After-Tax Cash Flow $M 6,927

After-Tax NPV(5%) $M 3,206

After-Tax IRR % 22

After-Tax Payback Period Years 3.6

* Years 22-26 is production from stockpile with average annual production of 65koz/year gold, 9.4Mlbs/year copper

and 200koz/year of silver.

**All-in sustaining cost per ounce is a non-GAAP ratio. This measure has no standardized meaning under

IFRS Accounting Standards (IFRS) and may not be comparable to similar measures used by other issuers.

Refer to the “Non-GAAP Financial Measures” section of this press release for more information,

including a detailed description of these measures.

*** The initial capital cost estimate of US$1.428 billion includes capitalized operating costs and capitalized revenues

and excludes sunk costs planned to be incurred through Q1 2027.

Technical Report Overview

The Technical Report was prepared in accordance with NI 43-101 for Troilus with contributions from BBA

Inc. (“BBA”), AGP Mining Consultants Inc. (“AGP”) and WSP Canada Inc. (“WSP”), and incorporates the

results of the Company’s completed Basic Engineering program.

The Technical Report outlines a large-scale, conventional open-pit operation processing 50,000 tonnes

per day from the 87, J, X22 and SW deposits. The mine plan is underpinned by 478 million tonnes of Proven

and Probable Mineral Reserves grading 0.44 g/t Au, 0.05% Cu and 0.92 g/t Ag. The 26-year mine life

includes approximately one year of pre-production processing, followed by 21 years of active mine

production and a subsequent period of stockpile rehandle and processing.

Life-of-mine payable production totals approximately 5.63 million ounces of gold, 472 million pounds of

copper and 10.88 million ounces of silver. During the 21-year active mining period, annual payable

production averages approximately 251,000 ounces of gold, 20.1 million pounds of copper and 466,000

ounces of silver. At base case metal prices of US$3,600/oz gold, US$5.00/lb copper and US$50.00/oz silver,

the Project generates an after-tax NPV(5%) of approximately US$3.2 billion, IRR of 22%, cumulative after-

tax cash flow of approximately US$6.9 billion and a 3.6-year payback period.

Processing is based on a conventional flowsheet incorporating crushing, HPGRs, ball milling, gravity

concentration and flotation, producing a gold-rich copper concentrate and gold-silver doré.

Key Project Optimizations and Advancements

The Technical Report incorporates the results of Basic Engineering, expanded metallurgical testwork,

current vendor pricing and more advanced execution planning, resulting in a substantially more

developed Project design than the 2024 Feasibility Study. Key advancements include:

Additional Front-End Processing Capacity and Flexibility: The updated flowsheet incorporates two

parallel 35,000 tpd HPGR units within the 50,000 tpd nameplate processing plant. This will provide

additional front-end processing capacity, along with additional plant availability with two lines, and

operating flexibility to support throughput capacity across variable ore characteristics throughout the

ramp-up period and into commercial production.

Higher-Confidence Comminution and Process Design: Additional metallurgical testwork has identified

higher ore hardness in the SW Zone which will be mined in early years of operation, and this harder ore

has been used as the benchmark to inform processing equipment sizing and the updated grinding design

basis. The resulting configuration is designed to support reliable throughput and reduce ramp-up and

operating risk.

Gold Doré Production from Initial Start-up: The gold room has been advanced into initial construction

rather than deferred as was the case previously. This will enable gravity-recovered gold to be poured as

doré from the outset of operations, supporting earlier cash generation and working capital during ramp-

up.

Refined Infrastructure and Execution Planning: Basic Engineering materially advanced site-wide

electrical, water, tailings and civil design, while integrating engineering and procurement with

construction sequencing, long-lead equipment planning and commissioning readiness. This provides a

more developed basis for Project execution as Troilus advances through Detailed Engineering.

Capital Costs

Updated Capital Estimate Reflects Advanced Engineering and Project Optimization

Initial capital is estimated at US$1.428 billion, reflecting substantially greater project definition achieved

through Basic Engineering, updated market pricing and design enhancements incorporated as the Project

has advanced from feasibility-level engineering toward execution.

Since completion of the 2024 Feasibility Study, approximately 95,000 engineering hours have materially

advanced design definition across the full Project scope. The largest areas of refinement relate to EPCM

requirements, construction labour, concrete and structural steel quantities, owner’s costs and other

indirect costs, all of which are now defined at a significantly greater level of detail than at the 2024

Feasibility Study stage. Approximately 90% of pricing inputs have been validated against current market

quotations, including firm pricing for key equipment, and the resulting capital estimate meets AACE Class

3 accuracy standards (+15%/-10%) across the full Project scope.

The updated estimate also incorporates current mechanical, electrical and civil pricing, together with

design changes intended to improve Project robustness and operating flexibility. These include two 35,000

tpd HPGR units, providing additional front-end processing capacity while maintaining the Project’s 50,000

tpd nameplate throughput; advancement of the gold room into initial construction, enabling doré

production from the outset of operations and supporting early working capital; and updated electrical,

civil and water-management infrastructure.

Together, these changes reflect both a substantially higher level of cost certainty and a more fully

engineered Project than was contemplated at the 2024 Feasibility Study stage.

Table 2. Troilus Project Capital Costs

Description Cost (US$ million)

On-Site and Off-Site Infrastructures 147.7

Energy & Site Power Distribution 18.4

161kV Hydro Quebec Transmission Line Compensation 12.8

Emergency Generators 9.3

Synchronous capacitance power factor correction 24.2

Mining Infrastructures 64.8

Dry Comminution 227.2

Processing Plant 385.7

Tailings & Water Management 87.0

Owner’s Project Costs 84.1

EPCM Services 123.7

Construction Indirects 107.7

Spares parts, freight & Vendor Support 47.9

Contingency* 131.9

Mining 202.9

Sunk Capital Costs (145.2)

Capitalized Operating Costs 78.8

Capitalized Revenue (180.8)

Total Initial Capital** 1,428

Sustaining Capital Costs 198.0

Reclamation and Closure Costs 52.4

*Contingency was estimated at P50

**The initial capital cost estimate of US$1.428 billion includes capitalized operating costs and capitalized

revenues and excludes sunk costs planned to be incurred through Q1 2027.

Operating Costs

Operating costs have been developed at a substantially greater level of definition through Basic

Engineering, using a combination of first principal estimates, project-specific design criteria, metallurgical

testwork, current supplier quotations and Québec labour benchmarks. Mine operating costs are based on

detailed equipment, productivity, fuel and labour assumptions, while process operating costs incorporate

equipment-specific power requirements, testwork-based reagent consumption, supplier pricing and

maintenance requirements.

This more detailed and market-informed approach provides a higher-confidence operating cost basis as

the Project advances through Detailed Engineering. Average life-of-mine operating costs are estimated at

US$19.21 per tonne of mill feed, as summarized in Table 3 below.

Table 3. Troilus Project Operating Costs

Area Units Year 1-5 Year 6-21 LOM (Year 1-26)

Open Pit Mining $/tonne moved 3.20 3.22 3.12

$/t mill feed 15.91 12.49 11.25

Processing $/t mill feed 5.82 5.54 5.55

G&A $/t mill feed 2.98 2.43 2.40

Total Operating Cost $/t mill feed 24.70 20.45 19.21

Table 4. Troilus Production Costs per Payable Gold Ounce (Cash Costs + AISC)

Mine Production

(Years 1–21)

Stockpile Reclaim

(Years 22-26) Life-of-mine

Cash Cost (US$/payable Au oz) $1,282 $1,541 $1,297

AISC (US$/payable Au oz) $1,321 $1,642 $1,340

Operating Margin (US$/payable Au oz) $2,318 $2,059 $2,303

Cash cost per ounce and AISC are a non-GAAP ratios. These measures have no standardized meaning under

IFRS and may not be comparable to similar measures used by other issuers. Refer to the “Non-GAAP

Financial Measures” section of this press release for more information, including a detailed description of

these measures.

Project Economics and Sensitivity

The Technical Report demonstrates strong cash flow generation and robust economic returns across a

range of metal price assumptions. At long-term base case metal price assumptions of US$3,600/oz gold,

US$5.00/lb copper and US$50.00/oz silver, the Project generates an after-tax NPV(5%) of US$3.206 billion,

an after-tax IRR of 22% and a 3.6-year payback period, together with cumulative life-of-mine cash flow of

approximately US$11.1 billion pre-tax and US$6.93 billion after-tax (see Figure 1).

The Project remains highly leveraged to metal prices, with after-tax NPV(5%) increasing to US$3.866

billion at US$4,000/oz gold, US$4.668 billion at US$4,500/oz and US$5.484 billion at US$5,000/oz, based

on the corresponding sensitivity assumptions (see Table 5).

Figure 1: Troilus Project, Cumulative Cash Flows

Table 5. Troilus Project, Economic Sensitivity Analysis

Gold Price (US$/oz) 2,000 2,500 3,000 3,600 4,000 4,500 5,000

After Tax NPV 5% (US$M) 384 1,322 2,190 3,206 3,866 4,668 5,484

After-Tax IRR 7.4% 12.8% 17.2% 22.0% 24.7% 27.9% 30.9%

Payback (years) 9.4 6.3 5.3 3.6 3.3 3.0 2.6

Mineral Resource & Reserves Summary

Mineral Reserve Estimate

The updated Mineral Reserve estimate totals 478 million tonnes of Proven and Probable Mineral Reserves

grading 0.44 g/t gold, 0.05% copper and 0.92 g/t silver, containing approximately 6.7 million ounces of

gold, 568 million pounds of copper and 14.2 million ounces of silver. This compares with 380 million

tonnes in the 2024 Feasibility Study, representing a 26% increase in Reserve tonnage. The updated mine

plan also benefits from a lower life-of-mine strip ratio of 2.4:1, compared with 3.1:1 in the 2024 Feasibility

Study.

The Mineral Reserves are derived from Measured and Indicated Mineral Resources within the 87, J, X22

and SW open pits and have an effective date of December 31, 2025. Accordingly, drilling results

announced during 2026 are not incorporated into the current Reserve estimate and represent potential

future opportunities for resource and reserve growth and mine-plan optimization.