Troilus Announces Feasibility Study Results FOR the GOLD-Copper Troilus Project: Outlines a Large Scale, 22-YEAR Open Pit Project IN Tier-One Jurisdiction with USD$884.5 Million NPV5%
TROILUS ANNOUNCES FEASIBILITY STUDY RESULTS FOR THE GOLD-COPPER
TROILUS PROJECT: OUTLINES A LARGE SCALE, 22-YEAR OPEN PIT PROJECT IN
TIER-ONE JURISDICTION WITH USD$884.5 MILLION NPV5%
WEBINAR TO BE HELD TODAY, MAY 14, 2024, AT 4:00PM ET TO DISCUSS RESULTS. REGISTER HERE TO
JOIN.
May 14, 2024, Montreal, Quebec – Troilus Gold Corp. (TSX: TLG; OTCQX: CHXMF) (“Troilus” or the
“Company”) reports results from a Feasibility Study (“FS” or the “Study”) completed on the gold-copper
Troilus Project (the “Project”) located in northcentral Quebec, Canada. The Study incorporates an initial
mineral reserve estimate (“MRE”) that supports a long life, large scale, 50,000 tonnes per day (“tpd”)
open-pit mining operation; a project in a tier-one mining jurisdiction that stands out in the Quebec and
Canadian mining landscapes.
Troilus has taken a focused and conservative approach to all costs and inputs to deliver a realistic and
compelling Feasibility Study that we believe maximizes the scope and scale of this mineral asset over the
long term. All amounts are in United States dollars, unless otherwise stated.
2024 FEASIBILITY STUDY HIGHLIGHTS
Large Scale Open-Pit Project
Open pit mine life of 22 years with the potential for future underground development.
Life-of-mine (“LOM”) average payable gold production of 244,600 ounces annually, 17.3 million
pounds of copper and 446,700 ounces of silver annually.
Peak annual payable gold production of 456,100 ounces, 31.8 million pounds of copper and
613,600 ounces of silver in year 7.
Open pit mine, processing 50,000 tonnes-per-day (“tpd”); a 43% larger scale operation than the
35,000 tpd processing rate contemplated in the Preliminary Economic Assessment (“PEA”) from
2020.
An economical and energy-efficient process to produce a desirable gold-rich copper concentrate
for sale to smelters, with a cyanide-free gravity concentration circuit to produce doré after Year 1.
Supported by an initial Mineral Reserve estimate of 380Mt grading 0.59 g/t gold equivalent
(“AuEq”) (0.49 g/t Au, 0.058% Cu and 1.0 g/t Ag) for a contained 7.26Moz AuEq (6.02 Moz Au, 484
Mlbs Cu and 12.2 Moz Ag).1
LOM total payable gold of 5.4 million ounces, 382 million lbs of copper and 9.9 million ounces of
silver.
1 AuEq was calculated using metal prices of $1,550/oz Au; $3.50/lb Cu and $20.00/oz Ag.
Average LOM strip ratio of 3.1:1.
Low-Cost Production2
All-in sustaining cash operating costs (“AISC”) of $1,109/oz.
Average operating costs of $19.06/t milled ore.
Strong Economic Results
Base Case after-tax NPV5% of USD$884.5 million and IRR of 14%, reflecting long-term forecast
prices of US$1,975/oz Au, $4.05/lb Cu, $23/oz Ag and $0.74 USD/CAD exchange rate.
After-tax NPV5% of USD$1.55 billion and IRR of 19.5% at April 2024 average metal prices (Au:
$2,332/oz; Cu: $4.30/lb; Ag: $27.50/oz).
Cumulative after-tax cashflow of $2.2 billion on base case assumptions; increasing to $3.4 billion
using average metal prices for April 2024.
Attractive Capital Intensity Given Inflationary Environment and Scale of Operation
Initial development capital of (“CAPEX”) of $1,074 million, including all mine pre-production costs,
net of existing infrastructure.
Existing and upgraded infrastructure, including powerlines and 50MW substation, all-weather
access roads and tailings facility among other infrastructure, reduce capital requirements for the
project and overall capital intensity.
Exploration Upside:
Numerous targets ranging from grass roots geochemical anomalies to early-stage drill targets are
actively being explored and advanced, both near mine and regionally, representing significant
future upside potential.
Justin Reid, CEO of Troilus, commented, “The entire Troilus team is proud to present results that clearly
demonstrate the potential for our project to become a major North American copper and gold producer.
The FS outlines a generational-scale asset, with a 22-year mine life and compelling economics, both at
discounted and current metal prices. The project has reasonable CAPEX and capital intensity, including
bottom quartile operating costs among the major Canadian gold mines. With a life-of-mine average
payable gold production of nearly 245,000 ounces annually, more than 17 million pounds of copper and
nearly 447,000 ounces of silver, Troilus stands not only as a strategically significant project that aligns with
the Province of Quebec’s priority on the production of strategic metals but is also positioned to be amongst
the largest scale, lowest cost gold and copper projects across Canada.
In today's challenging market, the value of our existing infrastructure has become even more critical,
reducing the capital intensity required to build project infrastructure and providing ongoing access to low-
cost renewable energy supplied by Hydro-Quebec. The Troilus Project has been designed to minimize the
environmental footprint of the future operation including using a cyanide free process, engaging in
progressive reclamation, making use of the existing tailings facility and minimizing GHG emissions through
reliance on sustainable energy sources.
2 See Non-IFRS Measures at the end of this news release.
The Study provides a strong foundation to continue building and growing the Company. Our geology team
has proven their ability to identify new targets and rapidly add significant ounces, and we believe there is
strong potential to further expand the scale of this project and extend the mine life beyond the 22 years
presented in this Study with further exploration and drilling.
With the FS now complete, Troilus is focused on next steps, namely the finalization of the Environmental
& Social Impact Assessment and ongoing exploration of the geological potential of the 435 km² Troilus
property. We look forward to working with our partners in the Eeyou Istchee James Bay region, including
the Cree Nation of Mistissini, the Cree Nation Government and Grand Council of the Crees, the local
communities of Chibougamau and Chapais, as well as the governments of the Province of Quebec and
Canada, to advance the Troilus Project.”
2024 Feasibility Study Summary
PRODUCTION
Mine Life 22 years
Daily Mill Throughput 50,000 tpd
Annual Mill Throughput 18.3Mt/year
Average Annual Metal Production (Payable) Gold (oz) Copper (Mlbs) Silver (oz)
Years 1-5 256,200 16.1 475,200
Years 6-22 241,200 17.7 438,300
Life of Mine 244,600 17.3 446,700
Proven & Probable Reserves 380 Mt containing 7.26 Moz AuEq
(6.02 Moz Au, 484 Mlbs Cu, 12.2 Moz Ag)
Proven & Probable Average Grades 0.59 g/t AuEq
(0.49 g/t Au, 0.058% Cu, 1.0 g/t Ag)
Strip Ratio 3.1:1
Average LOM Gold/Copper/Silver Recoveries 92.7% / 91.8% / 91.9%
COST METRICS
Initial Capital Expenditure $1,074 million
Sustaining Capital Expenditure $276.6 million
All-in-sustaining-cost (life-of-mine)¹ $1,109/oz
ECONOMIC RESULTS
Base Case (Au: $1,975/oz; Cu: $4.05/lb; Ag: $23/oz)
After-tax NPV @ 5% discount rate $884 million (C$1,208 million)
After-tax IRR 14%
Payback (years) 5.7 years
April 2024 Average (Au: $2,332/oz; Cu: $4.30/lb; Ag: $27.50/oz)
After-tax NPV @ 5% discount rate $1,553 million (C$2,121 million)
After-tax IRR 19.5%
Payback (years) 4.7 years
*Assuming a US$:C$ exchange of $0.74.
¹ See Non-IFRS Measures at the end of this news release.
Project Overview
The Troilus Project is comprised of four main zones of mineralization, which are located on a NE-SW trend
covering approximately seven kilometres. These deposits will be mined using conventional open pit
mining methods over a 22-year period. Ore will be processed in a flotation mill to produce gold-rich copper
concentrate for sale to a smelter, with provision for gravity gold recovery to produce doré after Year 1.
The projected payable gold production averages 256,200 oz per year over the first 5 years, 241,200 oz per
year for the remaining 17 years, for a LOM average of 244,600 oz per year. Copper payable annual
production averages 16.1 million pounds per year for the first five years, 17.7 million pounds per year for
the remaining 17 years and 17.3 million pounds for the life of mine average. Silver payable annual
production is 475,200 oz per year for the first five years, 438,300 oz per year for the remaining 17 years
with a life of mine annual average of 446,700 oz per year. The production profile is shown in Figure 1.
Total payable metal over the 22-year mine life is estimated at 5.4 million ounces of gold, 381.8 million
pounds of copper, and 9.9 million ounces of silver.
Figure 1: Production Profile - Payable Gold, Silver, and Copper
Economic Analysis
The Troilus Project’s estimated Base Case after-tax NPV (5%) is $884 million and IRR is 14%, assuming
metal prices of $1,975 per ounce gold, $4.05 per pound copper, $23 per ounce silver and a USD:CAD
foreign exchange rate of $0.74:1. Payback on initial capital is expected to be achieved in 5.7 years under
the base case scenario.
Assuming April 2024 average gold price of $2,333 per ounce, the after-tax NPV(5%) increases to $1.55
billion and IRR increases to 19.5%, with the payback decreasing to 4.7 years.
Base Case April 2024 Avg.
Gold Price (per oz) $1,975 $2,332
Copper Price (per lb) $4.05 $4.30
Silver Price (per oz) $23.00 $27.50
Pre-Tax NPV (5%) $1,564 MM $2,670 MM
Pre-Tax IRR 18.1% 25.0%
Post-Tax NPV (5%) $884 MM $1,553 MM
Post-Tax IRR (%) 14.0% 19.5%
Post-Tax Payback 5.7 4.7
Table 1: Troilus Project NPV and IRR Sensitivity to Metal Prices
Under the base case scenario, the Project generates cumulative cash flow of $2.2 billion on a post-tax
basis and $3.5 billion on a pre-tax, based on a throughput of 50,000 tpd over 22 years (see Figure 2).
Figure 2: Cumulative After-Tax Free Cash Flow After Repayment of Capital at Base Case and April 2024
Average Metal Prices
Capital Costs
The initial CAPEX for the Troilus Project is $1,075 million, net of existing infrastructure that includes all-
weather access roads, power lines and a 50MW substation, a tailings facility, water treatment plants and
site roads. Sustaining CAPEX over the life of the mine is an additional $276.6 million. A breakdown of the
capital requirements is presented in Table 2.
Table 2: Troilus Project Capital Expenditure Estimates Breakdown (US$)
Capital Costs ($ million)
Mining $258.3
Process Plant $443.0
Infrastructure $100.3
Indirects $173.0
Contingency $89.3
Subtotal – Initial Capital $1,063.9
Environmental $10.7
Total – Initial Capital $1,074.6
Sustaining Capital $209.1
Closure Costs $67.4
Total Sustaining Capital $276.6
*Net of existing infrastructure (access road, power line, substation, tailings facility, water treatment plant,
site roads)
Operating Costs
Total all-in-sustaining costs of $1,109 per ounce. Total operating costs are expected to average $19.06 per
tonne of ore processed. A breakdown of the operating costs is presented in Table 3.
Table 3: Troilus Project Operating Cost Estimates (US$)
Average Life-of-Mine Operating Costs
Mining $11.60/t
Processing $5.64/t
G&A, Trucking, Port, Shipping $1.82/t
Total Operating Cost/Tonne Ore $19.06/t
All-in Sustaining Cost $1,109/oz
Mining
The Study considers a conventional open pit mining operation using a 100% owner-operated equipment
fleet peaking at 41–227 tonne trucks, electric hydraulic shovels, wheel loaders and drills. The mine has
been designed to deliver 18.3 million tonnes per year (50,000 tonnes per day) of mill feed. The FS
contemplates a mine that delivers 379.5 million tonnes with an average head grade of 0.49 g/t Au, 0.058%
Cu, 1.0 g/t Ag.
The process plant is expected to have three months of commissioning in pre-production, followed by nine
months of production ramp-up during the first year of production.
The project will mine four areas: Z87, J Zone, Southwest (SW) Zone and X22. Mining commences in the
Z87 pit area in the pre-production period and will be mined continuously until Year 8. The final phase of
the 87 Zone pit area will be mined from Year 12 until Year 19. The SW Zone pit area starts production in
Year 1 and is mined continuously until completion in Year 9 and will then be used for deposition of tailings
from year 10 to 16. The J Zone pit area starts production in Year 5 and is mined continuously until early
Year 15. The X22 pit will be mined from Year 18 to 21. Waste from the Z87 and X22 open pits will be
backfilled over the SW tails from Year 16 onward. When Z87 pit area is completed in Year 19, waste is also
backfilled into it from the X22 pit area, reducing the overall size of the waste storage facilities.
The average strip ratio for the open pit life of the mine is estimated at 3.1:1. Material movement averages
86 million tonnes (feed and waste) in the first 5 years with the peak at 86 million tonnes in Year 5. The
open pit will provide 379.5 million tonnes of feed to the process plant over the 22-year mine life. Open
pit bench heights of 10 metres will be mined and ore hauled with 227-tonne haul trucks and matching
loading equipment including electric hydraulic shovels. The open pit mining fleet will be leased. Best
practice grade control drilling will be done with reverse circulation drilling and rock sampling on mine
benches prior to blasting. This provides the greatest flexibility for grade control during operations while
maintaining reasonable mine operating costs and production capability.
During the mining operation a stockpile will be maintained adjacent to the primary crushing plant to be
used as supplemental feed as required to meet production targets, weather events, and as mill feed in
the later years of the operation. Waste rock will be hauled to dedicated waste management facilities near
the open pits, backfilled into the 87 Zone pit, placed in lifts over the tails in SW Zone pit, and also used for
lifts of the tailings management facility. Concurrent reclamation of the waste management facilities is
planned.
Metallurgy
The flowsheet, similar to the original Troilus Mill operated by Inmet, has been developed based on
testwork completed at Eriez, FLS/Knelson, Base Met and Kappes Cassidy. The process plant consists of
primary and secondary crushing, HPGR and ball milling, copper/gold flotation with a regrind circuit,
concentrate filtration and tailings thickening and disposal. Copper concentrate, enriched with gold, will
be sent to a smelter for refining. Provision has been made to install gravity gold concentration for the
primary and regrind circuit in Year 1 where gold dorés will be produced. Overall recovery is estimated to
be 92.7% for gold, 91.8% for silver, and 91.9% for copper based on the LOM average head grades.
Figure 3: Troilus Project Process Flowsheet
Location and Infrastructure
The Troilus Gold Project is located in Quebec, Canada, approximately 120 kilometres north of
Chibougamau, where Inmet Mining Corporation operated a large mine/concentrator complex from 1996
to 2010. Access to the mine site from Chibougamau is by the Route du Nord.
The Troilus Project benefits greatly from the upgraded, and substantial infrastructure on site, which
includes:
Power line and 50MW substation sufficient for project power requirements,
All-weather access road,
Tailings facility and water treatment plant,
Camp facilities,
Site roads,
Water supply,
Septic system.
As part of the design, it is proposed to develop the tailings dyke as a downstream raise constructed
containment from the existing tailings management facility which will limit the overall footprint
disturbance. This structure will have the capacity to accommodate the first 10.5-year life of mine
production and then from years 11-22, the tailings will be disposed subsequently into the mined-out SW
pit, J pit and 87 pit as described in this FS. Waste rock from the mine operation placed along the tailings
facility’s containment dyke will enhance the facility’s stability and safety and will also limit the footprint
disturbance.