Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

TK.V ·

Tinka Reports Updated PEA FOR Ayawilca Project: Highlights Potential to Become TOP‐10 Global Zinc Producer After‐tax NPV8% of US$433M and IRR of 32% at $1.20/lb Zinc

Economic Studies

TINKA REPORTS UPDATED PEA FOR AYAWILCA PROJECT: HIGHLIGHTS POTENTIAL TO BECOME TOP‐10 

GLOBAL ZINC PRODUCER 

After‐Tax NPV8% of US$433M and IRR of 32% at $1.20/lb Zinc 

Vancouver,  Canada  –  Tinka  Resources  Limited ( “Tinka”  o r  t h e  “Company”)  (T S X V  &  B V L :  T K)  (OTCQB:  TKRFF)  is 

pleased  to  announce  strongly  positive  financial  results  from  an  updated  Preliminary Economic  Assessment  (“PEA”) 

prepared for its 100%‐owned Ayawilca Zinc Zone project in centr al Peru. The updated PEA is disclosed in accordance 

with National Instrument 43‐101  Standards of Disclosure for Mineral Projects  (“NI 43‐101”) and prepared by Mining 

Plus Peru S.A.C. (“Mining Plus”) as principal consultant, Transmin Metallurgical Consultants (“Transmin”), Envis E.I.R.L 

(“Envis”),  and  SLR  Consulting  (Canada)  Ltd  (“SLR” ) .   T h e  u p d a t e d  P E A  p r o v i d e s  the  economic  assessment  for  an 

underground ramp‐access mine development with an 8,500 tonnes per day processing plant, a significant throughput 

increase from the 2019 PEA.  

PEA Highlights  

 After‐tax NPV8% of US$433 million (up 19% from 2019 PEA) using base case metal prices of US$1.20/lb zinc, US$22/oz 

silver, and US$0.95/lb lead on a 100% equity basis (pre‐tax NPV8% of US$720 million); 

 Initial Capex of US$264 million with after‐tax IRR of 31.9% (pre‐tax IRR of 42.6%); 

 At current spot price of $1.50/lb zinc, the after‐tax NPV 8% increases to US$785 million and IRR increases to 45.7% 

(pre‐tax NPV8% of US$1.27 billion and IRR of 61%); 

 Average  annual  production  of  approximately  155,000  tonnes  of  zinc  in  concentrate  per  year,  which  would  make 

Ayawilca the largest primary zinc producer in South America and a top‐10 global zinc producer;  

 43.5 million tonnes mined over 14.4 years using bulk underground mining methods (sub level stoping combined with 

overhand cut and fill) with daily mill throughput of 8,500 tonnes per day (tpd); 

 Project located in a major mining region close to a paved highw ay under construction, ~200 km from an operating 

zinc refinery and port; 

 Designed to minimize risk and environmental impact ‐ 40% of tai lings used as underground backfill and on‐surface 

tailings treatment and storage facility to use filtered dry‐stack technology; 

 Numerous opportunities to add further value, including 

o exploration upside for additional zinc discoveries including at Far South, Yanapizgo, and Zone 3 areas; 

o further optimization of zinc and silver metallurgical recoveries; 

o incorporating high grade Tin Zone resources into the mine plan. 

Note: The PEA is preliminary in nature and includes inferred mi neral resources that are considered too speculative 

geologically to have the economic considerations applied to them that would enable them to be categorized as mineral 

reserves, and there is no certai nty that the preliminary econom ic assessment will be realized.  Mineral resources are 

not mineral reserves and do not have demonstrated economic viability. 

Tinka’s President and CEO, Dr. Graham Carman, stated: “We are very excited to release the results of our updated PEA, 

which shows Ayawilca to be an outstanding zinc project located  in a mining friendly jurisdiction, well positioned to be 

one of the next major zinc development projects worldwide.  At current spot zinc prices (around US$1.50 per pound) the 

PEA shows the project to be highly profitable with a post‐tax N PV8% of ~US$785 million.  At our base case zinc price of 

October 14, 2021 

T: 604.685.9316    [email protected]  

TSXV & BVL: TK   OTCQB: TKRFF NEWS RELEASE 

US$1.20 per pound, the PEA has excellent economics with a post‐ tax NPV8% of US$433 million. The updated PEA takes 

advantage of a relatively modest initial capital as well as access to a local refinery and port.” 

“The updated Ayawilca PEA demonstrates that, through the use of  bulk tonnage underground mining methods and a 

larger  resource,  Ayawilca  has  the  potential  to  be  the  largest  p rimary  zinc  producer  in  South  America.  Further 

opportunities still exist to add more value at Ayawilca, including seeking to improve the zinc recoveries (currently 92%) 

to a zinc concentrate and silver recovery to a silver‐lead concentrate (currently 45%), and also incorporating a tin circuit 

into the mine plan.”   

“Tinka is also committed to the highest standards of ESG performance. With the use of dry stack tailings and 100% use 

of  waste  rock  and  40%  of  tailings  as  backfill,  Tinka  is  highlighting  its  strong  commitment  to  utilize  low  impact  and 

environmentally sound solutions for tailings disposal. Tinka ha s been working at Ayawilca for a number of years, and 

we believe an underground mine built using industry‐leading sta ndards incorporating a low environmental impact will 

provide positive life‐changing opportunities for our local stak eholders. We look forward to continuing to advance the 

Ayawilca project towards development.”  

”Exploration remains a strong focus for Tinka, and the potentia l remains for significant new discoveries at Ayawilca to 

further increase the resource along strike and at depth.  Sever al targets at Ayawilca remain to be drill‐permitted, and 

we have filed for an extended permit to cover those areas.  Exploration is currently focused at the adjacent Silvia copper‐

gold project, where we recently announced the discovery of high grade copper‐gold skarn zones at Silvia NW (see news 

release dated October 7, 2021).” 

 Financial Summary – Base Case Zn at US$1.20/lb  Pre‐tax  After‐tax 

NPV (8% discount rate) 

IRR 

Payback period 

US$720 million 

42.6% 

2.0 years 

US$433 million 

31.9% 

2.6 years 

Pre‐production capital expenditure (Capex)1 

Sustaining Capex 

Life of Mine (LOM) Capex 

Closure Cost 

US$264.0 million 

US$186.8 million 

US$450.7 million 

US$15.2 million 

Notes: 1 Includes contingencies of US$44 million. 

Operating Summary     

Processing plant throughput  

Average annual zinc concentrate production 

Average annual lead‐silver concentrate production 

Average annual silver in lead concentrate  

Total LOM zinc production 

Net Smelter Return from zinc and lead concentrates 

  8,500 t/day 

309,000 dmt/year 

8,680 dmt/year 

632,000 oz/year 

4,450,000 tonnes 

US$4,156 million 

Mining costs 

Processing costs 

G&A costs 

Total Operating Costs (Opex) 

  US$32.79/t 

US$7.10/t 

US$4.27/t 

US$44.16/t 

Notes:  dmt = dry metric tonne.  

Numbers may not add due to rounding.    

Base Case Metal Prices & Exchange Rate Assumptions  Input value 

Zinc Price 

Lead Price 

Silver Price 

NSR Cut‐off value 

Exchange Rate ‐ Peruvian SOL/USD 

US$1.20/lb 

US$0.95/lb 

US$22/oz 

US$65/t 

3.87 

Total material processed (LOM)  43.5 million tonnes 

Mine Life  14.4 years 

Figure 1.  Ayawilca 2021 PEA – After tax cash flow by year of production 

PEA Mine Plan – 8,500 Tonnes per Day Underground Mining Operation 

The PEA for the Ayawilca Zinc Zone is based on an underground m ine operating at a minin g rate of 8,500 tonnes per 

day for a mine life of 14.4 years.  For the purposes of the PEA , production is assumed to commence in 2025 following 

18 months of construction and commissioning.  This initial mine  plan is based on mining a total of 43.5 million tonnes 

grading 5.56% Zn, 14.5 g/t silver and 0.20% lead over life of m ine (“LOM”) using an NSR cut‐off value of US$65/t.  The 

zinc‐rich mill feed will be trucked to the surface via a two‐wa y‐traffic ramp system connecting three mine portals to 

the underground infrastructure and accessing production areas starting at West and South Ayawilca (see Figure 3). 

Processing of the zinc mineralization will be through a standard crushing and grinding circuit followed by froth flotation, 

concentrate thickening and filtration.  The mine operation will produce two concentrates:  a zinc concentrate which is 

anticipated to assay 50% zinc based on metallurgical test work;  and a lead concentrate which is anticipated to assay 

50% lead and 2,272 g/t silver (calculated on assays and based o n similar base metal operations).  Approximately 60% 

of the tailings will be thickened and filtered for dry stack tailings disposal.  The remaining 40% will be mixed with cement 

and used as structural backfill in the underground operations. 

‐$1,200

‐$800

‐$400

$0

$400

$800

$1,200

‐$150

‐$100

‐$50

$0

$50

$100

$150

‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Cumulative After Tax Cash Flow (USD 

millions)

Annual After Tax Cash Flow (USD millions) After tax cash flow

Cumulative after tax cash flow

Based on preliminary mine plan analysis including resource geom etry, the scale of the deposit and grade distribution, 

sublevel  stoping  ("SLS")  and  overhand  cut  and  fill  with  pillars  ("OCF")  methods  were  selected.  The  mining  strategy 

involves dividing the deposit into five zones by spatial locati on and by mining method: West, South and Silver zones 

utilizing  the  SLS  method  (48.3%  of  mined  tonnes  for  processing),  and  the  Central  and  East  zones  utilizing  the  OCF 

method with pillars (36.9% of mined tonnes for processing). Dev elopment in ore represents 14.8% of the processed 

material.   

Figure 2.  Ayawilca Zinc Zone PEA ‐ Mining by Area showing average zinc grade by year of production 

The estimated operating costs, over the life of the project, are as follows: 

Operating Costs per Mining Method (Opex) 

Description  Cost p er Tonne Processed 

Mining – SLS (48.3% of mine plan) 

Mining – OCF (27.0% of mine plan) 

US$25.37 

US$29.79 

Average  Mining  Cost  ‐  including  development  (14.8%  of  mine  plan)  and 

Pillars (9.9% of mine plan) 

Process Plant 

G&A (US$13M/yr) 

Total Operating Cost 

US$32.79 

US$7.10 

US$4.27 

US$44.16 

 ‐

 1.00

 2.00

 3.00

 4.00

 5.00

 6.00

 7.00

 8.00

 ‐

 50,000

 100,000

 150,000

 200,000

 250,000

123456789 1 0 1 1 1 2 1 3 1 4 1 5 1 6

Average Zinc Grade Mined (%)

Annual Zinc Concentrate Production by Zone (t)

Production Year

Zinc Production by Area and Average Zinc Grade

SLS SOUTH SLS  WEST OCF  EAST SLS  SILVER

OCF  CENTRAL DEVELOPMENT ORE PILLARS Zn (%)

Figure 3.  Mine plan showing areas by zinc grade (red = >5% Zn; yellow = 2‐5% Zn) 

The major components of the initial capital expenditures of US$263.9 million include US$83.5 million for the processing 

plant, US$34.0 million for on‐site infrastructure, US$47.2 million for mine equipment and underground pre‐production 

development, US$9.1 million for off‐site infrastructure, and US$3.6 million for a starter filtered tailings storage facility 

direct costs.  Contingencies in the capital costs total US$43.8  million.  The major components of sustaining capital are 

US$95.3 million for mining equipment and underground developmen t, and US$91.6 million fo r tailings management 

over the 14.4 year mine life. 

Capital Cost Item  Initial (US$ M)  Sustaining (US$ M)  Total (US$  M) 

Mining & mine development 

Process plant 

On‐site infrastructure 

Off‐site infrastructure 

Filtered tailings storage facility 

Indirect + Owner costs 

Contingencies 

47.2 

83.5 

34.0 

9.1 

3.6 

42.7 

43.8 

95.3 

‐ 

‐ 

‐ 

91.6 

‐ 

‐ 

142.5 

83.5 

34.0 

9.1 

95.2 

42.7 

43.8 

TOTAL PROJECT  263.9  186.8  450.7 

CLOSURE COSTS      15.2 

   Numbers may not add due to rounding 

Metallurgical Recoveries and Off‐Site Charges 

As reported in the Company’s  news release on June 5th 2019, metallurgical testing of sa mples from Ayawilca indicate 

that a zinc concentrate grading 50% zinc can be produced with 92% of the zinc recovered to the concentrate.  The lead 

metallurgy has been assumed based on similar operations.  The l ead concentrate is expected to assay 50% lead and 

2,272 g/t silver on average over  the life of  mine. Based on  pre liminary  metallurgical test  work, 45% of the silver is 

expected to report to the lead concentrate and be payable, whil e 40% of the silver is expected to report to the zinc 

concentrate and not be payable.  The zinc concentrate is expected to be a marketable concentrate with no deleterious 

elements  other  than  an  iron  penalty.    Concentrate  grade  assumptions  and  recoveries  for  the  principal  metals  are 

provided in the table below.   

Composite Head Grade, Metallurgical Results and Recoveries 

Product  Average Grade LOM  Metallurgical Recoveries (%) 

Zinc (%)  Lead (%)  Silver (g/t)  Zinc Equiv. (%)  Av. NSR (US$/t)  Zinc  Lead  Silver 

Feed grade 

Zinc Concentrate 

Lead Concentrate 

5.56 

50.0 

4.0 

0.20 

0 to 0.1 

50.0 

14.5 

0‐100 

2,2722 

5.92  96.2  100 

92 

0 

100 

0 

70 

100 

40 

45 

   Notes:  Zinc Equivalent (%) = NSR/16.23.   NSR = Zn(%)*US$16.23+Ag(g/t)*US$0.27+Pb(%)*US$10.20 

   2 Silver grades were calculated for the PEA and range from 1,122 to 4,173 g/t 

All of the zinc concentrates are assumed to be delivered direct ly to a local refinery. All of the lead concentrates are 

assumed to be shipped overseas. Off‐site charges include treatm ent charges, refining charges, and iron penalties at 

refinery and summarized below.   

Off‐site Charges 

Description  Zinc Concentrate  Silver‐lead Concentrate 

Transport to Port/Local refinery 

Port Charges 

Shipping to overseas smelter (FOB) 

Local refinery Treatment Charge (TC) 

Overseas Treatment Charge (TC) 

Refining Charge (RC) 

Iron Penalty 

US$35/wmt 

‐ 

‐ 

US$190/dmt 

‐ 

‐ 

US$7.50/dmt 

US$35/wmt 

US$17.5/wmt 

US$45/wmt 

‐ 

US$150/dmt 

US$1.50/oz 

‐ 

Notes:  wmt = wet metric tonne.  dmt = dry metric tonne 

Tailings and Mine Waste Management 

The tailings and mine waste concept for Ayawilca is based on a  commitment to implementing best available practices 

and best available technologies, as described in the International Council of Mining and Metals (ICMM) Global Industry 

Standard for Tailings Management, and other, similar guides and standards.  Of note: 

 100% of mine waste rock and 40% of tailings production will be re‐used as underground mine backfill; 

 On‐surface tailings will be processed as dry‐filtered tailings,  and stacked at a secure, prepared facility.  This 

method will: reduce the environmental footprint; reduce risk of  failure and impacts; and reduce closure costs 

and schedule. 

NSR Calculation  

The mine plan for the PEA was based on a Net Smelter Return (“NSR”) cut‐off value of US$65 per tonne. The prices and 

NSR factors for each metal utilized in the NSR calculation for the 2021 PEA compared to the 2019 PEA are presented in 

the table below.  

Comparison of Metal Prices and NSR Factors from 2019 PEA to 2021 PEA 

Metal 

2019 PEA  2021 PEA * 

Metal Price 

Assumptions  NSR Factor  Metal Price 

Assumptions  NSR Factor 

Zinc (Zn) 

Lead (Pb) 

Silver (Ag) 

US$1.20/lb 

US$0.95/lb 

US$18.00/oz 

US$15.39 

US$12.25 

US$0.44 

US$1.20/lb 

US$0.95/lb 

US$22.00/oz 

US$16.23 

US$10.20 

US$0.27 

Notes:      * NSR for the 2021 PEA was calculated using the following formula:    

NSR = Zn(%)*US$16.23+Ag(g/t)*US$0.27+Pb(%)*US$10.20 

Sensitivities 

The Ayawilca zinc project is strongly leveraged to zinc price.  A 25% increase on the base case zinc price (around current 

spot price of US$1.50/lb) results in an after‐tax NPV8% of US$785M, an increase of US$352M (or 81%).   

Figure 4.  After‐tax NPV8% Sensitivities  

Note:  Arrow indicates current spot zinc price 

 (100.0)

 ‐

 100.0

 200.0

 300.0

 400.0

 500.0

 600.0

 700.0

 800.0

 900.0

‐40% ‐30% ‐20% ‐10% 0% 10% 20% 30% 40%

(US$M)

Change in Parameter

After Tax NPV @ 8.0% Sensitivity

Zinc selling price Lead selling price

Silver selling price Feed grades

Initial CAPEX Operating Cost

Opportunities and Exploration Potential 

The Ayawilca Zinc Zone has not been fully delineated and is open in several directions including to the northeast, south 

and southwest.   

Opportunities for additional value on the Ayawilca property not captured in the PEA include, but not limited to: 

1. Potential for new zinc‐silver discoveries outside of the existi ng resource at South, Far South, Yanapizgo, and 

Zone 3; 

2. Optimization  of  zinc  recovery  to  a  zinc  concentrate  (currently  92%)  and  silver  recovery  to  a  silver‐lead 

concentrate (currently 45%) through more detailed metallurgical test work; 

3. The potential to incorporate a tin circuit into the mine plan b y mining all, or some, of the adjacent Tin Zone 

resource (see news release dated September 27, 2021). 

Tinka is well positioned to continue to move Ayawilca forward towards development.  The project is fully permitted to 

carry out a Prefeasibility Study.  

A National Instrument 43‐101 Technical Report will be filed on SEDAR within 30 days. 

Figure 5.  Top‐10 world zinc mines by zinc production in 2020, with Ayawilca 2021 PEA highlighted                   

(Source: Stifel GMP and company data) 

 ‐

 100

 200

 300

 400

 500

 600

kt Zinc in Concentrate

Top Global Zinc Mine Production (2020 Production)