Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

TK.V ·

Tinka Reports Updated PEA and Mineral Resource Estimate FOR the Ayawilca Polymetallic Zinc‐tin‐silver Deposit

Resource Estimates Economic Studies

1 

February 28, 2024 

TINKA REPORTS UPDATED PEA AND MINERAL RESOURCE ESTIMATE FOR THE AYAWILCA POLYMETALLIC 

ZINC‐TIN‐SILVER DEPOSIT  

Vancouver,  Canada  –  Tinka  Resources  Limited ( “Tinka”  o r  t h e  “Company”)  (T S X V  &  B V L :  T K)  (OTCQB:  TKRFF)  is 

pleased to announce the results from an updated Preliminary Economic Assessment (“PEA”) on the Company’s 100%‐

owned polymetallic Ayawilca project  (“Ayawilca” or the “Project” ) in central Peru. The updated PEA shows Ayawilca 

to be an excellent base metals project with significant enhance ments from the previous PEA study.  The Project now 

features  a  smaller,  more  efficient  zinc‐silver‐lead  plant,  introduces  a  separate  tin  plant  for  additional  revenue  and 

commodity diversification and highlights the development path forward for Ayawilca to become a producing mine. 

PEA Highlights: 

 Robust economics: After‐tax Net Present Value (“ NPV”) at 8% discount of US$434 million (pre‐tax NPV8% of 

US$732 million) and after‐tax Internal Rate of Return (“IRR”) of 25.9% (pre‐tax IRR of 34.8%).  

 Payback period after‐tax of 2.9 years (pre‐tax of 2.4 years).  

 Initial Capital Expenditure (“Capex”) of US$382 million. 

 Long 21‐year life of mine (“ LOM”) for a 2.0 million tonnes per annum (Mtpa) zinc‐silver‐lead o peration with 

15‐years of tin production at 0.3 Mtpa. 

 Average C1 cash cost of US$0.55/pound zinc and all in sustaining cost (“AISC”) of US$0.68/ pound zinc.  

 Average annual metal production (in concentrate) of 200 million pounds of zinc (90,000 tonnes Zn), 3.26 million 

pounds of tin (1,500 tonnes Sn), 560,000 ounces of silver and 5.7 million pounds of lead (2,590 tonnes Pb). 

 Zinc Zone Indicated Mineral Resource tonnage increased 49% from the previous Mineral Resource estimate. 

 Tin Zone Indicated Mineral Resource declared for the first time. 

 Excellent location in a world‐class mining jurisdiction, close to a zinc smelter and port. 

 Compact  mine  footprint  and  planned  use  of  filtered  tailings  technology  provides  the  lowest  risk  and  most 

water‐efficient solution for tailings storage while 40% of tailings to be stored underground as backfill.   

Dr. Graham Carman, Tinka’s President and CEO, stated:  

“We are very pleased to release the results of the updated 2024 PEA for the Ayawilca project.  We believe the results of 

the PEA show Ayawilca to be an outstanding polymetallic project  with several improvements from the previous study. 

While zinc continues to be the primary revenue source, Ayawilca's polymetallic nature includes important contributions 

from tin and silver providing valuable commodity diversificatio n. The updated PEA is marked by the incorporation of a 

smaller, more efficient, zinc‐silver‐lead plant and a separate  tin plant and a more compact mine footprint. Despite an 

increase in the initial capex, due to efficiencies in the mine  design there was no significant impact on valuation. The 

strong financial metrics include an after‐tax NPV8% of US$434 million, an after‐tax IRR of 25.9%, and a post‐tax payback 

period of only 2.9 years which highlight the potential for Ayawilca to become a producing mine.” 

“A revised Mineral Resource estimation has significantly improv ed the level of confidence in the resource as a result of 

an  additional  11,000  metres  of drilling  completed  in  2023.  The Zinc  Zone  Indicated  Mineral  Resource  tonnage  has 

increased 49% over the previous estimate while zinc content has  increased by 22% and silver content by 45%.  The Tin 

Inferred  Mineral  Resource  has  increased  in  tonnage  and  metal  content  by  51%  and  13%,  respectively,  while  a  Tin 

T: 604.685.9316    [email protected] 

TSXV & BVL: TK   OTCQB: TKRFF NEWS RELEASE 

2 

Indicated Mineral Resource is declared for the first time. The  Company has chosen to adopt the highest standard for 

reporting underground mine resources to satisfy the “Reasonable Prospects for Eventual Economic Extraction (RPEEE)” 

as  required  by  CIM  (2014)  in  the demonstration  of  spatial  continuity  of  mineralization  within  potentially  mineable 

shapes (i.e., stopes). With the market increasingly moving towards RPEEE resource reporting for underground deposits, 

we are adopting this method of resource reporting for the first time.” 

“ T h e  u s e  o f  f i l t e r e d  t a i l i n g s  i s  t h e  l o w e s t  r i s k  a n d  m o s t  w a t e r‐efficient  solution  for  tailings  storage  at  surface,  and 

highlights our commitment to minimize environmental risks.  The storage of a substantial quantity of tailings as backfill 

underground also reduces surface tailings storage, again helping to minimize the environmental impact.”  

”There remains significant exploration potential for further di scoveries at Ayawilca, and several of the resource bodies 

remain open at depth, with a potential feeder system remaining largely untested by drilling particularly at the Tin Zone.” 

T h e  r e s u l t s  o f  t h e  P E A  u p d a t e  w i l l  b e  d i s c l o s e d  i n  a n  i n d e p e n d ent  technical  report  in  accordance  with  National 

Instrument 43‐101 Standards of Disclosure for Mineral Projects (“NI 43‐101”) and prepared by independent consulting 

firm SRK Consulting (UK) (“ SRK”) with specific subject matter expertise including Transmin Me tallurgical consultants 

(“Transmin”), Envis Peru S.A.C. (“Envis”) tailings consultants and MineFill Services (“MineFill”) backfill consultants.  SLR 

Consulting (Canada) Ltd (“SLR”) has prepared the updated Mineral Resource estimate for the P EA update.  A National 

Instrument 43‐101 Technical Report (“the Technical Report”) will be filed on SEDAR within 45 days. 

Note: The PEA is preliminary in n ature and includes Inferred Mi neral Resources that are c onsidered too speculative 

geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral 

Reserves, and there is no certainty that the preliminary economic assessment will be realized.  Mineral Resources are 

not Mineral Reserves and do not have demonstrated economic viability.   

A summary of the key financial information for the updated PEA is provided in Table 1.  

Table 1.   PEA Summary 

 Financial Summary – Base Case   Pre‐tax  After‐tax 

NPV (8% discount rate) 

IRR 

Payback period 

US$731.7 million 

34.8% 

2.4 years 

US$433.5 million 

25.9% 

2.9 years 

Pre‐production capital expenditure (Capex)1 

Sustaining Capex 

Life of Mine (LOM) Capex 

C1 Cash Cost / Pound of Payable Zinc 

All‐in Sustaining Cost (AISC) / Pound of Payable Zinc 

Closure Cost 

US$382 million 

US$313 million 

US$695 million 

US$0.55 

US$0.68 

US$20 million 

Notes: 1 Includes contingencies of US$76 million. 

A summary of the Life of Mine (LOM) operating summary for the updated PEA is provided in Table 2. The after‐tax cash 

flow by year of production is presented in Figure 1.  

3 

Table 2.  LOM Operating Summary for the updated PEA with Metal Prices assumptions 

Operating Summary  Value 

Operating days per year 

Processing plant throughput Zn/Ag/Pb 

Processing plant throughput Sn 

Average annual zinc concentrate production 

Average annual tin concentrate production 

Average annual lead‐silver concentrate production 

Average annual silver in lead concentrate  

Total LOM zinc in concentrate 

Net Smelter Return from zinc and lead concentrates 

Net Smelter Return from tin concentrate 

360 days/year 

2.0 Mtpa 

0.3 Mtpa 

180,000 dmt/year 

3,000 dmt/year 

5,500 dmt/year 

0.56 million oz/year 

1.9 million tonnes 

US$4,000 million 

US$460 million 

Mining costs (including backfill) 

Processing costs Zn/Ag/Pb 

Processing costs Sn 

Tailings 

G&A costs 

LOM Average Operating Cost (Zn/Ag/Pb) 

LOM Average Operating Cost (Sn) 

US$16.88/t 

US$11.00/t 

US$23.63/t 

US$0.94/t 

US$6.23/t 

US$35.06/t 

US$47.68/t 

Notes:  dmt = dry metric tonne.  

Numbers may not add due to rounding.    

Base Case Metal Prices & Exchange Rate Assumptions  Value 

Zinc Price 

Lead Price 

Silver Price 

Tin Price 

NSR Cut‐off value ‐ Zinc Zone and Silver Zone 

NSR Cut‐off value – Tin Zone 

Exchange Rate ‐ Peruvian SOL/USD 

US$1.30/lb 

US$1.00/lb 

US$22/oz 

US$11.00/lb 

US$60/t 

US$80/t 

3.70 

Total LOM tonnage processed  45.55 million tonnes 

Mine Life Zn/Ag/Pb 

Mine Life Sn 

21 years 

15 years 

4 

Figure 1.  Ayawilca 2024 PEA – After‐Tax Cash Flow by Year of Production (in US$) 

Mining 

The  Ayawilca  Project  is  planned  as  an  underground  mine  operation.    For  the  purposes  of  the  PEA,  the  Zinc  Zone 

(together with the Silver Zone) will be mined at a rate of 2.0  Mtpa, whilst the Tin Zone will be mined at a rate of 0.3 

Mtpa.  Mining of both zinc and tin zones commence together with each feeding separate processing plants.  The LOM 

is 21 years for the Zinc Zone and 15 years for the Tin Zone.  Mining in the Zinc and Tin Zones will utilize a long hole open 

stoping (“LHOS”) method in a transverse direction with level sp acing ranging from 15 to 20 m.  The Silver Zone uses 

LHOS in a longitudinal direction at a 20 m level spacing. A top‐down overhand mining sequence is applied, working on 

top of paste‐fill between sill pillars which are recovered.  Three declines are planned from surface, initially two declines 

to access the South, Silver, and West areas and in later years  the Central and East areas will be accessed by a third 

decline. The Tin Zones are also accessed through these planned declines.   

Production is assumed to commenc e following 18 months of constr uction and commissioning.  The mine plan for the 

Zinc and Silver Zones is based on mining a total of 41.2 million tonnes grading 5.02% Zn, 17.3 g/t silver and 0.19% lead 

over a 21‐year LOM using an NSR  cut‐off of US$60/t.  The Tin Zo ne is based on mining a total of 4.32 million tonnes 

grading 0.92% tin over a 15‐year LOM using an NSR cut‐off of US $80.  The mill feed will be trucked to the surface via 

multiple ramp systems connecting the three mine portals to the underground infrastructure and accessing production 

areas starting at the South and West areas of the Zinc Zone, the Silver Zone, and the high recovery area of the Tin Zone 

(see Figures 2 and 3).  

5 

Figure  2.    Mining Schedule for Zinc‐Silver‐Lead Plant (left) and Tin Plant (right) showing Average Grades by Year 

Figure  3.     Oblique view of Ayawilca mine design and stopes showing LOM Schedule  

6 

Metallurgy and Processing 

Processing of the zinc‐rich mineralization will be through a conventional crushing and grinding circuit followed by froth 

flotation, concentrate thickening and filtration.  Metallurgica l test work indicates a zinc concentrate grading 50% zinc 

can be produced from Zinc and Silver Zones with 92% of the zinc  in the Zinc Zone recovered to the zinc concentrate 

(see news release of June 5, 2019), and 87% of the zinc in the Silver Zone recovered to the zinc concentrate.  The lead 

concentrate  is  expected  to  contain  47%  lead  and  average  3,140  g/ t  s i l v e r  o v e r  t h e  L O M .  B a s e d  o n  p r e l i m i n a r y  

metallurgical test work, 45% of the silver in the Zinc Zone is expected to report to the lead concentrate and be payable, 

while 40% of the silver is expected to report to the zinc concentrate and not be payable.  In the Silver Zone, 85% of the 

silver (and 85% of the lead) is expected to report as a credit to a commercial lead concentrate. The zinc concentrate is 

expected to be a marketable concentrate with no deleterious elements other than an iron penalty.  Concentrate grade 

assumptions and recoveries for the principal metals in the Zinc and Silver Zones are summarized in Table 3 below.   

Table 3.   LOM Head Grades and Metallurgical Recoveries for the Zinc‐Silver‐Lead Circuit 

Product  Zinc/Silver‐Lead Concentrates Average Grade LOM  Metallurgical R ecoveries (%)1 

Zinc (%)  Lead (%)  Silver (g/t)  Av. NSR (US$/t)  Zinc  Lead  Silver  

Feed grade 

Zinc Concentrate 

Lead Concentrate 

5.02 

50.0 

4.0 

0.19 

0 to 0.1 

47 

17.3 

0‐100 

3,1402 

99  92/87 

0 

0 

70/85 

40/0 

45/85 

1 First number relates to recovery in Zinc Zone and second number to Silver Zone  

2 Silver concentrate grades were calculated for the PEA and range from 897 to 5,849 g/t  

The first 200,000 wmt/a of zinc concentrates are assumed to be  delivered directly to a local refinery (around 90% of 

LOM production); the balance is assumed to be sold to refinerie s in east Asia. The zinc concentrate also contains high 

indium  (around  650  ppm  In)  and  receives  a  US$20/dmt  credit  in  conc e nt r at e sh i p p e d t o Asi a.  A l l  of th e si l ve r ‐ l e ad 

concentrates are assumed to be sold overseas. Off‐site charges  include transport costs, treatment charges, refining 

charges, and iron penalties at refinery are summarized below in Table 4.   

Table 4.   LOM Head Grade and Metallurgical Recovery for the Tin Circuit 

Product  Average Grade LOM  Metallurgical Recoveries (%) 

Tin (%)  Av. NSR (US$/t)  Tin – Coarse  Tin – Fine 

Feed grade 

Tin Concentrate 

0.92 

50.0 

106  90  50 

Initial metallurgical testwork indicates that a tin concentrate grading 50% with 90% recovery can be produced from the 

high  recovery  (i.e.,  coarse  tin)  part  of  the  Tin  Zone,  and  a  tin  concentrate  grading  50%  with  50%  recovery  can  be 

produced from the lower recovery (i.e., fine tin) part of the T in Zone. The coarse tin represents 19% of the overall tin 

feed. The tin concentrates are anticipated to have markets in Asia and therefore all of the tin concentrate produced is 

assumed to be shipped overseas. Off‐site charges include transport, treatment charges, refining charges, and penalties 

at refinery and summarized below in Table 5.   

7 

Table 5.   Off‐Site Charges 

Description  Zinc Concentrate  Silver‐Lead 

Concentrate 

Tin Concentrate 

Transport to Port/Local refinery 

Port Charges 

Shipping to overseas smelter (FOB) 

Local refinery Treatment Charge (TC) 

Overseas Treatment Charge (TC) 

Ag Refining Charge (RC) 

Indium Credit (Overseas only) 

Sulphur Penalty 

Iron Penalty 

US$40/wmt 

US$25/wmt 

US$45/wmt 

US$220/dmt 

US$220/dmt 

‐ 

US$20.00/dmt 

US$7.50/dmt 

US$40/wmt 

US$50/wmt 

US$15/wmt 

‐ 

US$50/dmt  

US$0.80/oz 

‐ 

US$40/wmt 

US$50/wmt 

US$15/wmt 

‐ 

US$750/dmt 

‐ 

‐ 

US$75/dmt 

0.7 units 

Notes:  wmt = wet metric tonne.  dmt = dry metric tonne 

For silver‐lead concentrates grading less than 2,500 g/t Ag, treatment charge is $150/dmt and refining charge is $1.00/oz Ag.     

Approximately 60% of the tailings will be thickened and filtered for dry stack tailings disposal.  The remaining 40% will 

be prepared as pastefill and reticulated to the underground mine to be used as structural backfill. 

Infrastructure 

Access 

There is a good existing road network from the Project to the c oast of Peru.  The Project lies approximately 250 km 

from the Port of Callao and a zinc refinery.  The road leaving  the Project is an all‐weather gravel road that crosses the 

high central Andes for about 60 km before joining a bitumen roa d to the coast and then to the Port of Callao via the 

Pan‐American highway.  The Cajamarquilla zinc refinery is situa ted on the eastern outskirts of the city of Lima with 

good access from the highway.  

Tailings and Mine Waste Management 

The tailings and mine waste concept for the Ayawilca PEA is bas ed on a commitment to implementing best available 

practices and best available technologies, as described in the  International Council of Mining and Metals (“ICMM”) 

Global Industry Standard for Tailings Management.  The location of the TSF has been selected to minimize any potential 

risks for downstream areas. It is envisaged that: 

 100% of mine waste rock and 40% of tailings production will be re‐used as underground mine backfill; 

 On‐surface  tailings  will  be  processed  as  filtered  tailings  and stacked  at  a  secure  and  prepared  facility.  This 

method  will  reduce  the  environmental  footprint  and  the  risk  of failure  and  the  attendant  environmental 

impacts, while also minimizing water consumption. 

 The filtered tailings facility has been located adjacent to the  process plant area, minimi zing the haul distance 

for the tailings and reducing environmental and social impacts. 

Power 

A new electricity substation is currently under construction 4.7 km from Ayawilca by a 3rd party mining company.  The 

P r o j e c t  w i l l  i n c l u d e  c o n s t r u c t i o n  o f  a t r a n s m i s s i o n  l i n e  f r o m  this  substation  to  a  substation  at  Ayawilca.    Tinka  has 

recently received approval of a  pre‐operation environmental stu dy (“EPO”) to access 220kV / 23 MW power supply 

through a substation at Ayawilca.  Ayawilca is now planned to become connected to the national electrical grid. 

Capital and Operating Costs 

The major components of the initial capital expenditure of US$$382 million include US$89.4 million for the zinc‐silver‐

8 

lead processing plant, US$29.0 million for the tin processing p lant, US$34.0 million for on‐site infrastructure, US$56.6 

million for mine equipment and underground pre‐production development, US$17.8 million for site preparation of the 

filtered tailings storage facilit y and related mobile equipment , $15.5 million for the pastefill plant, $52.4 million for 

other surface facilities, and US$45.0 million other costs including indirects and owners costs.  Contingency in the initial 

capital  totals  US$76.2million.    T otal  sustaining  capital  is  $31 3.1  million  over  the  21‐year  mine  life.  The  major 

components  of  sustaining  capital  are  US$176.3  million  for  minin g  equipment  (including  major  components  and 

rebuilds) and materials handling, $49.8 million for mine develo pment, ventilation and water management, US$46.0 

million for tailings management. Contingency in sustaining capital totals US$40.8 million. 

The estimated capital costs, over the life of the Project, are as follows in Table 6. 

Table 6.   Capital Costs Summary 

Capital Cost Item  Initial (US$ M)  Sustaining (US$ M)  LOM Total  (US$ M) 

Mining & mine development 

Process plant – Zn/Ag/Pb 

Process plant ‐ Sn 

Pastefill plant 

Tailings 

Other surface facilities 

Subtotal 

Other indirects 

Owner’s costs 

Contingency 

56.6 

89.4 

29.0 

15.5 

17.8 

52.4 

261.7 

34.7 

10.3 

76.2 

226.3 

‐ 

‐ 

‐ 

46.0 

‐ 

272.2 

‐ 

‐ 

40.8 

282.9 

89.4 

29.0 

15.5 

63.7 

52.4 

534.0 

34.7 

10.3 

117.0 

TOTAL PROJECT (US$ M)  381.8  313.1  694.9 

CLOSURE COSTS (US$ M)      19.5 

   Numbers may not add due to rounding 

The estimated operating costs, over the life of the Project, are as follows in Table 7.  

Table 7.   Operating Costs per Mining Method for the Zinc and Tin Plants 

US$/t Processed

Operating Cost Item Zinc Plant Tin Plant  Weighted Average 

Zinc + Tin

Mining 

Backfill 

Sub‐total 

Processing 

Tailings 

G&A 

13.15 

3.73 

16.88 

11.00 

0.94 

6.23 

13.15 

3.73 

16.88 

23.63 

0.94 

6.23 

13.15 

3.72 

16.88 

12.20 

0.94 

6.23 

TOTAL PROJECT  35.06  47.68  36.25