Titan Reports Q3 2022 Results
1
Titan Reports Q3 2022 Results
Vancouver, BC – November 10 , 2022 – Titan Mining Corporation (TSX: TI) (“ Titan” or the
"Company") today announces the results for the third quarter ended September 30, 2022. (All
amounts are in U.S. dollars unless otherwise stated)
“Titan continued to build momentum in the third quarter with key metrics achieved in safety and
production. While costs were up slightly and grade below budget for the period, continued
development into Q4 will ensure a record year for ESM. Also, during the quarter ESM received
key permits that will allow operations to expand mining in the Sphaleros area which will begin to
benefit the operations in Q2/23.” said Don Taylor, President and Chief Executive Officer of Titan.
Q3 2022 HIGHLIGHTS:
• Zinc production totaling 11.6 million payable pounds and sales of 12.6 million pounds of
zinc during the quarter
• Cash balance of $13.6 million on September 30, 2022
• Net loss of $0.2 million or $nil per share
• Declared fifth consecutive special cash dividend of C$0.01 per share
• Received approval for surface activities at the Sphaleros site
TABLE 1 Financial and Operating Highlights
1 Net Debt is a non-GAAP measure. This term is not a standardized financial measure under IFRS and might not be
comparable to similar financial measures disclosed by other issuers. See Non-GAAP Performance Measures below
for additional information.
2
OPERATIONS REVIEW
Mining efforts in the third quarter of 2022 focused on the Mahler, New Fold and N2D zones.
Waste development continued to advance on the New Fold and Mahler ramp systems to access
high grade material expected to be mined in the fourth quarter of 2022 and into 2023. Lower grade
feed to the mill was largely due to mining in Mahler and New Fold where ore grades were lower
than anticipated.
Joel Rheault, Mine General Manager at ESM said, “With the delays in permitting throughout 2022,
the team took a different view on the project and instead looked at mining the underground in the
Sphaleros area. We are looking forward to implementing development in this area in the first half
of 2023.”
EXPLORATION UPDATE
Underground:
Underground drill programs in the third quarter of 2022 were focused on exploration. Exploration
drilling targeted down dip extensions of Mud Pond Main, New Fold, and Fowler wi th a total of
6,055 ft drilled, and six holes completed. Drilling was underway at New Fold and Fowler at the
end of the quarter. One utility hole was completed in Mahler, totaling 121 ft. All underground
drilling was completed with Company owned underground drills by Company employees.
Underground drilling in the fourth quarter will continue at New Fold and Fowler and commence at
Mahler and N2D.
Surface:
In the third quarter of 2022, surface exploration drilling focused on testing the regional Beaver
Creek, Morrison Road, and North Gouverneur t argets. One hole totalling 1,136 ft was drilled at
Beaver Creek completing the 2022 program. Four holes were completed at Morrison Road
totalling 3,845 ft. Two holes were completed at North Gouverneur, totaling 2,502 ft. Drilling was
ongoing at this target at the end of the quarter. Beaver Creek and North Gouverneur have historic
mining activity with drilling aimed at testing these structures and their potential for mineralization
at depth. Drilling at Morrison Road was targeting anomalous surface geochemical samples, and
mapped mineralization identified as stratabound.
In addition to regional drilling eleven holes were drilled to test near mine mineralization in the
Sphaleros project area (West Ridge, Pump House, and Streeter). This drilling was completed with
Company-owned equipment and Company Employees. A total of 2,077 ft was drilled.
Regional surface drilling in the fourth quarter is planned for North Gouverneur and Bostwick
Creek. Near mine drilling will commence in December and target Streeter and Turnpike.
3
CONSOLIDATED FINANCIAL STATEMENTS
Titan’s unaudited interim consolidated financial statements and management’s discussion and
analysis for the nine months ended September 30, 2022, are available on the Company’s website
at www.titanminingcorp.com and under the Company’s profiles on SEDAR.
Qualified Person
The scientific and technical information contained in this news release and the sampling,
analytical and test data underlying the scientific and technical information has been reviewed,
verified and approved by Donald R. Taylor, MSc., PG, President and Chief Executive Officer of
the Company, a qualified person for the purposes of NI 43- 101. Mr. Taylor has more than 25
years of mineral exploration and mining experience and is a Registered Professional Geologist
through the SME (registered member #4029597). The data was verified using data validation and
quality assurance procedures under high industry standards.
Assays and Quality Assurance/Quality Control
To ensure reliable sample results, the Company has a rigorous QA/QC program in place that
monitors the chain- of-custody of samples and includes the insertion of blanks and certified
reference standards at statistically derived intervals within each batch of samples. Core is
photographed and split in half with one-half retained in a secured facility for verification purposes.
Sample preparation (crushing and pulverizing) has been performed at ALS Geochemistry (“ALS”),
an independent ISO/IEC accredited lab located in Sudbury, Ontario, Canada. ALS prepares a
pulp of all samples and sends the pulps to their analytical laboratory in Vancouver, B.C., Canada,
for analysis. ALS analyzes the pulp sample by an aqua regia digestion (ME -ICP41 for 35
elements) with an ICP – AES finish including Cu (copper), Pb (lead), and Zn (zinc). All samples
in which Cu (copper), Pb (lead), or Zn (zinc) are greater than 10,000 ppm are re- run using aqua
regia digestion (Cu- OG46; Pb-OG46; and Zn -OG46) with the elements reported in percentage
(%). Silver values are determined by an aqua regia digestion with an ICP-AES finish (ME-ICP41)
with all samples with silver values greater than 100 ppm repeated using an aqua regia digestion
overlimit method (Ag- OG46) calibrated for higher levels of silver contained. Gold values are
determined by a 30 g fire assay with an ICP-AES finish (Au-ICP21).
The Company has not identified any drilling, sampling, recovery, or other factors that could
materially affect the accuracy or reliability of the data set out in this news release.
Non-GAAP Performance Measures
This document includes non-GAAP performance measures, discussed below, that do not have a
standardized meaning prescribed by IFRS. The performance measures may not be comparable
to similar measures reported by other issuers. The Company believes that these performance
measures are commonly used by certain investors, in conjunction with conventional GAAP
measures, to enhance their understanding of the Company's performance. The Company uses
4
these performance measures extensively in internal decision- making p rocesses, including to
assess how well the Empire State Mine is performing and to assist in the assessment of the
overall efficiency and effectiveness of the mine site management team. The tables below provide
a reconciliation of these non-GAAP measures to the most directly comparable IFRS measures as
contained within the Company's issued financial statements.
Net Debt
Net debt is calculated as the sum of the current and non- current portions of long-term debt, net
of the cash and cash equivalent balance as at the balance sheet date. A reconciliation of net debt
is provided below.
September 30 December 31
2022 2021
Current portion of debt $ 144 $ 95
Non-current portion of debt 35,870 34,617
Total debt $ 36,014 $ 34,712
Less: Cash and cash equivalents (13,568) (6,041)
Net debt $ 22,446 $ 28,671
About Titan Mining Corporation
Titan is an Augusta Group company which produces zinc concentrate at its 100%-owned Empire State
Mine located in New York state. Titan is built for growth, focused on value and committed to excellence.
For more information on the Company, please visit our website at www.titanminingcorp.com
Contact
For further information, please contact: Investor Relations: Email: [email protected]
Cautionary Note Regarding Forward-Looking Information
Certain statements and information contained in this new release constitute "forward-looking statements", and
"forward-looking information" within the meaning of applicable securities laws (collectively, "forward- looking
statements"). These statements appear in a number of places in this news release and include statements
regarding our intent, or the beliefs or current expectations of our officers and directors, including that continued
development into Q4 will ensure a record year for ESM; that the Company received key permits that will allow
operations to expand mining in the Sphaleros area which will begin to benefit the operations in Q2/23;that waste
development continued to advance on the New Fold and Mahler ramp systems to access high grade material
expected to be mined in the fourth quarter of 2022 and into 2023; that the Company will implement development
in the Sphaleros area in the first half of 2023; underground drilling in the fourth quarter will continue at New Fold
and Fowler and commence at Mahler and N2D; that regional surface drilling in the fourth quarter is planned for
North Gouverneur and Bostwick Creek; and that near mine drilling will commence in December and target Streeter
and Turnpike.. When used in this news release words such as “to be”, "will", "planned", "expected", "potential", and
similar expressions are intended to identify these forward-looking statements. Although the Company believes that
5
the expectations reflected in such forward-looking statements and/or information are reasonable, undue reliance
should not be placed on forward -looking statements since the Company can give no assurance that such
expectations will prove to be correct. These statements involve known and unknown risks, uncertainties and other
factors that may cause actual results or events to vary materially from those anticipated in such forward-looking
statements, including the risks, uncertainties and other factors identified in the Company's periodic filings with
Canadian securities regulators. Such forward-looking statements are based on various assumptions, including
assumptions made with regard to the ability to advance exploration efforts at ESM; the results of such exploration
efforts; the ability to secure adequate financing (as needed); the Company maintaining its current strategy and
objectives; and the Company’s ability to achieve its growth objectives. While the Company considers these
assumptions to be reasonable, based on information currently available, they may prove to be incorrect. Except as
required by applicable law, we assume no obligation to update or to publicly announce the results of any change
to any forward-looking statement contained herein to reflect actual results, future events or developments, changes
in assumptions or changes in other factors affecting the forward-looking statements. If we update any one or more
forward-looking statements, no inference should be drawn that we will make additional updates with respect to
those or other forward-looking statements. You should not place undue importance on forward-looking statements
and should not rely upon these statements as of any other date. All forward-looking statements contained in this
news release are expressly qualified in their entirety by this cautionary statement.